HomeMy WebLinkAbout25SITE2 - Applicant Response to Comments 03-18-2025FULLER ENGINEERING & LAND SURVEYING, LLC
525 John Street – Second Floor – Bridgeport, CT 06604
Phone: (203) 333-9465 Fax: (203) 336-1769
The Quill Group
Fuller Engineering & Land Surveying, LLC Civil Engineering, Landscape Architecture, Surveying
Atlantic Consulting & Engineering, LLC Geotechnical, Structural, Mechanical, Electrical, & Plumbing
Fairfield Testing Laboratories, LLC Materials Testing, Inspection, & Certifications, Special Inspections
P a g e | 1
18 March 2025
Mrs. Meredith Badalucca
Assistant Planner
Town of Montville
RE: Response to Comments
Madison Place, Luxury Townhouse Development
145 Route 32 & 18 Powerhouse Road
Montville, Connecticut
The following are our responses to comments from the Wright-Pierce. Our responses are designated in
bold and italics. Engineers, Inc.
Technical Review by Wright-Pierce dated 3/5/2025
Water System Comments
1. Provide a range for the expected water demand (standard and fire flow conditions) of the
Madison Place development and confirm that the 2-inch service lines are adequate.
Response: Please see the attached Sanitary Sewer & Water System Calculations for the
anticipated water demand analysis.
A 2” water main has been calculated as adequate to serve the project.
2. It is understood that the existing hydrant on Powerhouse Road will be used for fire protection, is
this sufficient for the entire development? Confirm with Town of Montville Fire Marshall.
Response: All comments from the current Fire Marshal have been addressed under
previous comment responses.
3. The Water Line Trench detail indicates 3.5-ft depth. The water pipe depth is to be 4-ft minimum
below ground level.
Response: The minimum pipe depth has been increased to 4 feet minimum as shown on
Sheet C-6.1.
4. Maintain a horizontal separation distance of at least 10’ between water, sewer, and stormwater
mains. Confirm and verify that the proposed water service line meets the required State of
Connecticut Department of Health and WPCA Specifications vertical and horizontal separation
distances from the proposed sewer and storm lines.
Response: Water main has been relocated to create a 10’ minimum separation distance
from the sanitary sewer main. The crossing separation of the water main over the
sanitary main elevation difference has been increased to 1.8’
The Quill Group
Fuller Engineering & Land Surveying, LLC Civil Engineering, Landscape Architecture, Surveying
Atlantic Consulting & Engineering, LLC Geotechnical, Structural, Mechanical, Electrical, & Plumbing
Fairfield Testing Laboratories, LLC Materials Testing, Inspection, & Certifications, Special Inspections
P a g e | 2
5. A minimum 4-inch layer of sand shall be provided under the entire length of service line. Clarify
sand thickness on all sides of the service line.
Response: Detail on Sheet C-6.1 has been clarified to indicate 7” minimum sand bed, 6”
minimum side sand bed, and 12” sand cover.
6. Note location of water meter(s). WPCA Specifications require that each separate residential
unit be separately metered. Confirm that each building service line will have its own water
meter.
Response: Water meters have been added to Sheet C-3.2.
7. 2” blow-off hydrants at the end of each service line should not be directly adjacent to the corner
of buildings.
Response: Blow-off hydrants have been located further away from the building corners.
Sanitary Sewer Comments
1. Provide anticipated average day and peak sanitary sewer flows for the development.
Response: Please see the attached Sanitary Sewer & Water System Calculations for the
anticipated water demand analysis.
Sanitary main size of 6” was determined sufficient
2. Specify size of proposed PVC piping.
Response: Sanitary sewer pipe sizes have been added to Sheet C-3.2 indicating 4” PVC
laterals and a 6” PVC main.
3. Provide explanation on why new manhole is required as opposed to tying into existing manhole
on Powerhouse Road.
On-site manhole has been eliminated and direct connection to the existing Powerhouse
Road manhole has been made.
Additionally, the two existing houses are now proposed to retain their existing sewer
connections to Powerhouse Road and RT 32.
4. Masonry manholes are not considered to be acceptable. Precast manholes only.
Response: A precast sanitary manhole has been added to sheet C-6.3.
5. Flows discharged to the sewer from this development will flow through a series of isolated pipes
further down Route 32 identified in the 2011 wastewater facility plan and 1/1 study as
potentially having capacity limitations during high-flow / storm events. Depending on the
estimated peak flows proposed to be discharged from the site, these pipes may need to be
reviewed and considered for replacement to provide adequate capacity during peak flow
events.
The Quill Group
Fuller Engineering & Land Surveying, LLC Civil Engineering, Landscape Architecture, Surveying
Atlantic Consulting & Engineering, LLC Geotechnical, Structural, Mechanical, Electrical, & Plumbing
Fairfield Testing Laboratories, LLC Materials Testing, Inspection, & Certifications, Special Inspections
P a g e | 3
Response: See calculations provided under Comment 1 of this section to analyze the
system capacity.
6. A sewer main near to and below the bottom of the infiltration basin means the sewer pipe is
going to be below groundwater for a period of time every significant rain. This a potential long
term 1/1 problem.
Response: No ground water was identified to 14 feet within the additional test pit areas
within the infiltrations system. It is our opinion the proximity of the sanitary main should
not be of concern.
7. Design should consider proximity of sewer line to infiltration basin. If the required separation
distances are not met, the inclusion of impervious dam materials in the sewer bedding may be
necessary for steep pipe segments to avoid groundwater collection and downstream
groundwater issues.
Response: No ground water was identified to 14 feet within the additional test pit areas
within the infiltrations system. It is our opinion the proximity of the sanitary main should
not be of concern.
8. A cleanout or manhole at the intersection of main and line to buildings 1-4 should be present.
Response: A sanitary manhole has been added at the requested location.
9. Each occurrence of a pipe direction change and every 75’ of continuous piping without a service,
a cleanout should be present per Montville WPCA specifications.
Response: Cleanouts have been added at 75’ increments and at changes in pipe direction
as required on Sheet C-3.2.