MEMORANDUM FOR THE RECORD
APPLICATION# 25 IWC 29
REGULAR MEETING – THURSDAY, FEBRUARY 19, 2026
Prepared by Stacy Radford, Zoning & Wetlands Officer
Owner/Applicant: City of Norwich, Department of Public Works
Address: New London Tpke., Uncasville
Date of Receipt: December 11, 2025
Date Received by IWC: December 18, 2025 (DRD – February 21, 2026)
Applicant Request: Regulated activities within the upland review area in conjunction with the
installation of sidewalks.
Activity Description:
Wetland Disturbance Area 0 SF
Watercourse/Waterbody Disturbance Area 0 LF
Upland Review Disturbance Area Applicant states approx. 30,000 SF
TECHNICAL REVIEW COMMENTS:
• Plan Set - Sheet 5 of 5 (upper left corner) Erosion & Sediment Control Notes #1-7.
Please remove the duplicate language in each of the (7) lines.
• Plan Set – Sheet 5 of 5 (upper right corner) Erosion and Sediment Control Narrative.
Section II. Narrative. A. Description of Development. Please correct the spelling of
Montville.
• Plan Set – Sheet 5 of 5 (upper right corner) Erosion and Sediment Control Narrative.
Please add Montville WEO to be present for any inspection of the silt fence in each of the
stages, prior to the commencement of any construction.
STAFF COMMENTS IN REVIEW:
• This Application is for regulated activities within the upland review area in conjunction
with the installation of sidewalks in accordance with the New London Turnpike Sidewalks
and Road Rehabilitation.
• This entire scope of the overall project involves the installation of a 0.75 mile sidewalk to
complete pedestrian access between Route 82 and Route 32, enhancing safety and roadway
conditions along the corridor.
• The work will include approximately 1,130 LF of work within the roadway which is within
the upland review area. The work will include the installation of approximately 240 linear
feet of 5’ wide concrete sidewalks, milling and replacement with 2.5 inches of bituminous
pavement in two lifts, and construction of approximately 68 linear feet of new embankment
wall. Additional work includes the removal and resetting of approximately 43 linear feet
of metal beam rails, replacement of six catch basin tops with ADA-compliant grates,
removal of two utility poles, and minor grading and site adjustments, as required. The
project includes the resurfacing of the bridge surface only over the brook, with no cut, fill
or removal activities planned within the actual watercourse or wetland area.
H:\IWC\Applications\2025\25IWC29 - New London Tpke (to install sidewalk in URA, regulated activities)\Staff\25IWC29-New London
Tpke - Staff Report 3 2-19-2026.docx
• Erosion and sediment controls will be implemented within the project area to protect
drainage inlets and adjacent vegetated areas outside of the project limits. Erosion controls
will include silt sacks for catch basins and double-row silt fencing along downslope areas
to protect the wetlands. All practices will be in accordance with the 2023 Connecticut
Guidelines for Soil Erosion and Sediment Control.
• This project provides improvements to pedestrian connectivity and roadway safety while
minimizing impacts to upland and wetland areas. The project work will be limited to within
the roadway for repaving and minor work for the installation of the sidewalk. All bridge
work will be contained to the road surface with no impacts to the bridge structure.
• On January 6, 2026 the Applicant provided a response to Staff’s Technical Review
comments of December 18, 2025 and a revised Plan. All Staff comments have been
addressed.
• This Application was referred to the Town Soil Scientist on December 12, 2025 and
comments were received on January 8, 2026 (copy attached). These comments were
forwarded to the Applicant for their response which was received on January 15, 2026
(copy attached). The responses were forwarded to the Town Soil Scientist and additional
comments are pending.
• One of the comments of the Town Soil Scientist was that the wetlands were not
delineated on the Site Plan by a certified Soil Scientist. Staff had discussion with the
Town Soil Scientist after receipt of the Applicant’s responses to his comments regarding
same and he inquired if the Commission deemed the regulated activities as significant, to
which I responded that the Commission did not. Pursuant to Section 7.6 of the Inland
Wetlands and Watercourses Regulations for the Town of Montville, should the
Commission deem the proposed activities as significant impact, the Commission “shall
require the applicant to have the wetlands delineated in the field by a soil scientist and
that the field delineation be incorporated onto the site plan”. Bob Russo, certified Soil
Scientist for the Town of Montville gave his verbal recommendation that this activity not
be deemed significant activity because the work is not within the wetlands and the work
is within an existing developed area.
• The Applicant has submitted a request for waiver of fees with their original Application,
which this Commission will need to make a determination on. At this time, Staff would
not recommend the approval of a waiver of the Application fees as this Application has
been referred out to the Soil Scientist and fees are beginning to accrue, in excess of the
$200.00 Application fee.
AGENCY COMMENTS:
• Town Soil Scientist – The referral for comments was forwarded on December 12, 2025
and comments were received on January 8, 2026. These comments were forwarded to the
Applicant for response, which was received on January 15, 2026. Responses were
forwarded to the Town Soil Scientist and final comments were received on January 20,
2026.
NEW STAFF COMMENTS:
• Final review comments were received by the Town Soil Scientist on January 20, 2026,
indicating that all previous comments had been addressed.
• No new comments.
H:\IWC\Applications\2025\25IWC29 - New London Tpke (to install sidewalk in URA, regulated activities)\Staff\25IWC29-New London
Tpke - Staff Report 3 2-19-2026.docx
CONSIDERATION FOR ACTION:
If the Commission is inclined to approve the request of the Applicant for a permit for proposed
activity, the following language for a Motion of Approval is suggested:
MOTION (to Approve)
After giving due consideration to all relevant factors including those in Section 10 and/or Section
6 of the Montville Inland Wetlands and Watercourses Regulations and Section 22a-41 of the
Connecticut General Statutes, I move to approve Application #25 IWC 29 – New London Tpke
(Parcel ID: N/A), Uncasville, CT: Owner/Applicant: City of Norwich, Department of Public
Works; for regulated activities within the upland review area in conjunction with the installation of
sidewalks, per the Application and associated documents dated December 11, 2025 and plan
entitled, “New London Turnpike Topographic Survey prepared for the City of Norwich,
Connecticut, dated May 6, 2022 and revised January 14, 2026.”
Standard reasons for approval and standard conditions of approval apply.