July 8, 2025
Town of Montville Inland Wetlands Commission ATTN: Douglas K. Brush, Chair Montville Town Hall
310 Norwich-New London Turnpike
Uncasville, CT 06382 Re: Ebdath Chowdhoury Residential Development
Glen Road
Montville, CT CLA-8020 Project Description
This project proposes the construction of a residential 5-bedroom home on the 11.5-acre lot.
This home will include an onsite 1500-gal concrete septic tank and leaching fields. A retaining wall
will be constructed next to the home. A well will be installed on the property just below the
home for drinking water. There will also be a few drainage features installed including, curtain
drain constructed of 6” pvc attached to it, a rip rap inlet with a 12” HDPE pipe which leads to a
rip-rap drainage outlet, and a footing drain and a riprap footing drain outlet. All of this would be
outside of the 50-foot upland review area and accounts for most of the site disturbance.
Some of the proposed development is located within the 50-foot upland review area
which includes the riprap outlet for the slope drain and part of the driveway which accounts for
6,500 square feet of disturbance. This proposal also calls for construction that would cause 4,200
square feet of disturbance within the regulated wetland area. This includes the construction of a
driveway that leads up to the house and the installation of modified riprap inlet on the side of the
driveway with a round 12” concrete pipe going under the driveway feeding to a riprap outlet.
This would help redirect stormwater away from the driveway. The reason for these proposed
activities being within the regulated area is due to the adjacent property line. Since the
neighboring property cuts into the regulated area, the only place for a driveway onsite would be
through the wetlands. The part of the driveway connecting to Glen Rd which goes through the
regulated area is designed to have the least amount of disturbance. The work in the wetland
would likely be completed by September or October of 2025 and the remaining work for the
project would be completed by the end of 2026.
CLA Engineers, Inc.
Civil Structural Survey
317 MAIN STREET NORWICH, CT 06360 (860) 886-1966 (860) 886-9165 FAX
This project would require the use of an excavator for grading and for installing the
driveway and the septic system. Large trucks and a drill rig will also be needed to transport fill
and to install the well. The soil removed during grading will be stockpiled onsite outside of the
50-foot upland review area. The fill material that will be used for the septic system and the
driveway within the flood zone and regulated areas will consist of clean sand or sand & gravel
free from any organic matter and foreign substances. There will be about 600 cubic yards of
wetland and flood zone filled and a total site net cut of 360 cubic yards. To offset the wetland
and floodplain area being filled, 545 cubic yards will be excavated from upland to re-create
floodplain storage area. Overall, there will be about 75,430 square feet of disturbance on this
site.