HomeMy WebLinkAbout24SITE7 - Transmittal Letter
John U. Faulise, Jr., L.S. David C. McKay, P.E.
Gerald J. Stefon, L.S. (1952-2021) Jacob S. Faulise, E.I.T.
Boundaries LLC
179 Pachaug River Drive
P.O. Box 184
Griswold, CT 06351
T 860.376.2006 | F 860.376.5899
www.boundariesllc.net
TRANSMITTAL
October 22, 2024
To: Ms. Meredith Badalucca
Assistant Town Planner
310 Norwich-New London Turnpike
Uncasville, CT 06382
RE: Final Plans
Application: 24 SITE 7
Location: 480 Route 32, Uncasville, CT
Applicant: KDS Realty, LLC.
Boundaries LLC Job I.D. No. 24-3488
Dear Ms. Badalucca;
Please find enclosed the following revised plans prepared in accordance with the Planning and Zoning
Commission’s Conditions of Approval from their October 22, 2024 meeting:
· Six (6) copies of site plans entitled “Site Development Plan, prepared for KDS Realty, LLC., 480
Route 32, Montville, Connecticut, October 2024, Rev. A – Per Conditions of Approval – 10/23/24.”
Per Condition of Approval Number 12 please consider the following as the list of how the conditions of
approval will be met:
· General Conditions 1 through 6 are acknowledged and will be met during construction as
appropriate.
· Site Specific Conditions 7 through 9 are acknowledged and will be met post-construction as
appropriate.
· Conditions to be met prior to signing of plans:
o Condition 10: Requested plan revisions are incorporated into Revision A.
o Condition 11: Live signed and sealed plans are included with this letter.
o Condition 12: The digital PDF and AutoCAD file of the plans have been submitted by email.
o Condition 13: The list included in this transmittal is intended to satisfy Condition 13.
o Condition 14: The change made to the plans include the addition of the Conditions of
Approval to Sheet 2, and notes indicating the location of the Conditions of Approval on
Sheets 1 and 3. A note and detail for the catch basin hood has been added to Sheet 2.
The notes on Sheet 3 have been updated per Condition 10. The Narrative on Sheet 3 has
Page 2
been updated to state that there will be a maximum of three patients at any time in the
kennel addition.
· Conditions to be met prior to the issuance of Zoning permits:
o Condition 15: The required paper plans are included with this letter.
o Condition 16: No certificates or permits from State or Federal agencies are required for
the construction of this site plan.
o Condition 17: The applicant will post the required erosion and sediment control and site
restoration bond in accordance with Town requirements.
o Condition 18: A pre-construction meeting will be scheduled with the Zoning Enforcement
Officer prior to the start of construction of this site plan.
· Conditions which must be met prior to Issuance of Certificate of Zoning Compliance:
o Condition 19: As-built plans with required certifications will be provided at the completion
of construction.
o Condition 20: The requirement for ZEO sign-off prior to issuance of a Certificate of
Occupancy is acknowledged.
If you have any questions regarding this correspondence or the enclosed documents, please contact me
at your convenience.
Sincerely,
David C. McKay, P.E.
Boundaries LLC