HomeMy WebLinkAboutConditions of Approval2
TOWN OF MONTVILLE PLANNING & ZONING COMMISSION CERTIFICATE OF NOTICE OF DECISION
APPLICATION: PZ #23 SITE 10 LOCATION: 225 Maple Avenue (Parcel ID 077-041-000), Uncasville CT APPLICANT/OWNER: Town of Montville REPRESENTATIVE(S): Attorney Matthew Willis - Halloran & Sage PROJECT: Site Plan approval for the construction of an Animal Control Facility and associated site improvements DATE OF APPROVAL: November 14, 2023 EXPIRATION DATE: November 14, 2028 COMMISSION ACTION: APPROVE WITH CONDITIONS as follows:
APPROVE Application 23SITE10 β 225 Maple Avenue (Parcel ID 077-041-000), Uncasville, CT β
Applicant/Property Owner: Town of Montville for Site Plan Review for a proposed Animal Control Facility
and associated site improvements. in that the application, supporting documents and a plan entitled βNew
Animal Control Facility at: Montville Animal Shelter, 225 Maple Ave., Montville, CT, Prepared by: Silver
Petrucelli & Associates, Dated: 10/2/2023, Revised 11/8/2023β comply with all applicable sections of the
Montville Zoning Regulations, with the following conditions:
1. Final plan set shall be revised to add maintenance schedule for stormwater structures.
2. Applicant shall meet all of the requirements of the Montville Building Department, Office of the Fire
Marshal, WPCA, Uncas Health District for required permitting and inspections prior to issuance of a
certificate of zoning compliance.
3. All drainage structures proposed for the project shall be constructed and maintained post
construction in accordance with the approved Plan Set.
4. Final revised plan sets, along with a digital copy of the final plan, shall be submitted to the Land Use Dept. & shall be signed and sealed with original signatures by P.E.
5. An approved Zoning Permit is required prior to the start of any work.
6. The Zoning Officer must be contacted and a pre-construction meeting shall be held at least 24-hours
prior to start of any work. Soil Erosion and Sediment Controls shall be installed in accordance with the
approved plan set and inspected by the Zoning Officer prior to the start of any work.
7. After work has commenced, any substantive changes to the approved site plan require review and
approval by the Land Use Director and/or the Planning & Zoning Commission.
8. A final As-Built plan, including finished grades, shall be submitted to the Zoning Officer for review
and approval prior to issuance of a certificate of zoning compliance.
Each and every condition is an integral part of the Commission decision. Should any of the conditions, on appeal from this decision, be found to be void or of no legal effect then this conditional approval is likewise void. Should any of the conditions not be implemented by the applicant or his successors within the specified permit time period, then this conditional approval is void.
Elizabeth Burdick, Director
Department of Land Use & Development