ARCHITECT’S PLAN REVIEW REPONSE
PROJECT: Montville Animal Shelter Date: November 2, 2023 225 Maple Avenue Montville, Ct 06791 SPA #22.130
☒ REVIEWER: CLA Engineers on October 26, 2023
REMARKS:
FROM: P. Jorgensen JOB NUMBER: 22.130
DISTRIBUTION: SP+A FILE
NO. COMMENT ARCHITECT RESPONSE
1 The orientation of the building with the front facing
away from Maple Avenue should be reconsidered
Town input needed – bldg located per prior direction
2. The trees along Maple Avenue have been
removed, additional screening should be provided.
Town input needed – bldg located per prior direction
3. The site lighting should be described on the plans
with notes regarding glare and spillage.
See Electrical plans for fixtures, etc
4. The yard drain outlet culvert should be straight, or
an additional yard drain added at the proposed
culvert angle point.
DWS Will address
5. Trash removal should be described on the plans. Town input needed .. do they want/ need a dumpster
pad or is trash kept inside and removed daily?
6. A detail of the timber guard rail should be added to
the plans.
DWS Will address
7. The silt sack detail should be included in the E&S
plan, and the sacks removed once the site is
stabilized.
DWS Will address
8. A cross section of the stormwater management
area should be included on the plans and surface
treatment detailed.
DWS Will address
9. The soil testing results should be included with the
application.
DWS Will address
10. The need for fencing to separate the adjacent
playground for the proposed facility should be
considered.
Town input needed