Loading...
HomeMy WebLinkAbout72324 FINAL 303 Draft MotionSUGGESTED APPROVAL MOTION (7/23/24) MOTION to APPROVE with the following conditions and modifications, Application 24SITE 5, modification of approved site plan application 22SITE10 and approved phasing plan for 303 Norwich-New London Turnpike (070/004/000) in accordance with the Montville Zoning Regulations and the application, supporting documentation and a plan set entitled “Modified Site Plan, Multi-family development, 303 Route 32, Uncasville, CT, Dated received July 11, 2024, Prepared by Green Site Design, LLC”. General Conditions: 1. This approval is for the specific use, site and structure(s) identified in the application. Any change in the nature of use, site or structures will require new approvals from the Planning and Zoning Commission or its duly authorized agent. 2. This project shall be constructed and maintained in accordance with the approved plans. 3. A Modified Zoning Permit is required prior to the start of any work on Phase I. 4. A Zoning Permit is required prior to the start of any work on Phase II, including partial building demolition. 5. No Zoning Permit for Phase II shall be issued until all Phase I requirements have been met, and a CZC has been issued for Phase I. 6. By acceptance of this permit and conditions, the applicant and owner acknowledge the right of Town staff to periodically enter upon the subject property for the purpose of determining compliance with the terms of this approval. 7. Prior to issuance of a CZC for Phase I, all site improvements shall be completed and an accurate and complete certified as built survey shall be provided for review/approval by the ZEO. 8. No occupancy under this permit/approval shall be initiated until a Certificate of Zoning Compliance is approved by the Zoning Officer. 9. The applicant and any successors and assigns agree to maintain the site in the condition as permitted and required by the Site Plan approval. Conditions to be met prior to signing of Final Plans: The plans shall be revised as follows: 1. The following notes shall be added to the plans: Unless otherwise specified herein, this approval shall expressly exclude offsite encroachments that are not essential to the functional and physical integrity of required and approved on-site improvements. The acceptance of the alternative design for the retaining wall(s) is based on the professional certification provided by the applicant’s licensed design engineer and the Commission accepts no liability. The responsibility to maintain the site in the condition as approved lies with the owner and any successors/assigns. 2. The plans shall be modified as follows: The site plans shall include all detail and information required by Section 17 of the zoning regulations. The existing conditions survey shall be revised to show accurate, current and complete existing conditions. The site plans shall be revised to be consistent with the proposed architectural elevations and floor plans. Eliminate all out of date/superseded details (i.e. improvements no longer proposed/approved) on the proposed modified site plan. The proposed retaining wall detail shall be eliminated and a reference substituted to the approved building permit for the alternative design, certified by the project engineer of record. The plan shall indicate the removal of the existing dumpster pad, replacement with bituminous pavement and restriping of the parking stall as originally approved. The existing and proposed surface treatment in the right of way shall be shown as grass/lawn. The plan shall be revised to indicate installation of the traffic “island” as per the original site plan approval. Show the limits of the easement for the light base and reference the easement in the survey notes. Show parking in the SW of the site to be installed as per the originally approved plan, including shifting the pavement north, and replacement evergreen plantings a minimum of 6 (six) feet high at planting, along the property line from the street line extending east for 85 (eighty-five) feet. Indicate surface treatment for landscape area as stone or mulch. Shift the dumpster location north to accomplish this modification and remove the note (proposed mod to remove vegetation). Show pavement, curbing and parking in the NE area to be installed per the originally approved plan. At the proposed concrete pad for the relocated dumpster, extend curb to the end of the adjacent parking space as well as along the east side of the concrete pad. Provide curbing where dumpster was initially relocated, per the originally approved plan. Provide one call out for the approved location of the concrete dumpster pad & enclosure. Show installation of Handicap Ramps. Show DOT improvements as permitted and constructed. Show freestanding sign in location that does not increase the lawful nonconforming front setback. Conditions to be met prior to the issuance of a modified Zoning Permit for Phase I: • Bond in a form and amount approved by the Town Attorney and Town Engineer, sufficient to cover the labor/materials for the final course of bituminous paving and parking lot striping. • Evidence of recording of the light pole easement on the Montville Land Records. • Final architectural elevations and floor plans for Building I. • Final plans as approved by the Commission in a digital format per ZR section 17.3. • Three (3) sets of paper plans with any required revisions incorporated. • Any required certificates and/or approvals from State or Federal agencies (i.e. CT-DOT, DEEP, Army Corps of Engineers) shall be provided. Any changes to the plans required by such entities may require a plan modification from the Planning and Zoning Commission or its duly authorized agent. • A pre-construction meeting between the applicant, site contractors, project engineer and Town Staff shall be held. Conditions to be met prior to Issuance of a Certificate of Zoning Compliance for Phase I: Completion of all required site work per the approved modified site plan Complete as-built survey certified to Class A-2 accuracy. The as-built plan shall also contain a certification by a Professional Engineer that they have inspected the site improvements and that they have been installed in accordance with the approved plans. Any deviations or omissions must be noted. Conditions to be met prior to the issuance of a modified Zoning Permit for Phase II: Completion of all required work in Phase I and issuance of a CZC for Phase I Copy of the approved demolition permit for phase II building. Final Elevations and Floor Plans for Building II. A preconstruction meeting with the PE of record, the contractor and Town staff. Conditions to be met prior to the issuance of a certificate of zoning compliance for Phase II: Completion of all required site work per the approved modified site plan, including final pavement course and parking area striping/pavement markings. Complete as-built survey certified to Class A-2 accuracy. The as-built plan shall also contain a certification by a Professional Engineer that they have inspected the site improvements and that they have been installed in accordance with the approved plans. Any deviations or omissions must be noted. Written evidence of ConnDOT approval of work within the State right of way.