EROSION and SEDIMENTATION CONTROL BOND COST ESTIMATE
Breezeline - Uncasville, CT
Date:2/16/2023
Plan Date:2/13/2023
Location:Breezeline Uncasville CT
Uncasville, CT
UNIT TOTAL
DESCRIPTION UNIT QUANTITY COST COST SUBTOTAL
EROSION CONTROL
Silt Fence LF 430.00 2.91$ 1,251.30$
Stabilized Construction Entrance EA 1.00 2,500.00$ 2,500.00$
Temporary Sediment Basin CY 70.00 49.35$ 3,454.50$
SC150BN (Slope stabilization)ROLL 1.00 205.55$ 205.55$
7,411$
This is an engineers opinion of probable
cost. Civilworks New England has no control
over the cost of labor, materials, equipment
or services furnished by others or over the
Contractor(s) methods of determining prices
or over competitive bidding or market
conditions. Civilworks New England cannot
and does not guarantee that actual costs will
not vary from this opinion of probable cost.
TOTAL 7,411$
NOTES
22102 - Breezeline E&S Control Bond Estimate - 021623 Rev 1 2/16/2023]