HomeMy WebLinkAboutte note 1-21-08 Gay Hill Road subdivisionFrom: Thomas Fenton, P.E. [TFenton@nlja.com]
Sent: Monday, January 21, 2008 5:22 PM
To: Colleen Bezanson; planningdept@montville-ct.org.
Cc: Don Bourdeau
Subject: Gay Hill Road subdivision
On Friday, I met with Rima (Project Engineer), Don and the Fire Marshall concerning the emergency access out to Swanty Johnson.
The preference of Don and the Fire Marshall would be to have the short section of road between the subdivision and Swanty Johnson paved instead of gravel as now shown, but to also have
a gate installed. The preference for a gate would be a metal bar gate with some clearance below it to make it a easier for winter maintenance and operation.
We discussed options for Phasing of the subdivision based on the comments of my last letter. Rima is going to come back with a revised phasing plan that will allow a first phase to
stand on its own.
I will be in Town tomorrow and will stop by later in the morning.
Tom
Thomas H. Fenton, P.E.
Associate
Nathan L. Jacobson & Associates, Inc.
86 Main Street, P.O. Box 337
Chester CT 06412-0337
860-526-9591
tfenton@nlja.com