HomeMy WebLinkAbout22SITE5 Bond Est East and West sidesErosion Control and Site Restoration Bond Estimate
Gateway Montville, LLC
125 and 133 Depot Road
Uncasville, CT
DATE: 6/17/2022
Page 1 of 1
Item No.Description Quantity Unit Cost Amount
WEST OF RAILROAD
EROSION AND SEDIMENTATION CONTROLS
1a Anti-tracking pad, per square yard 160 $30.00 $4,800.00
1b Sediment barrier, install and maintain, per linear foot 1,490 $8.00 $11,920.00
SITE RESTORATION
2a Hay, 1" deep, power mulcher, large, per 1,000 square feet 220 $77.50 $17,049.32
2b Spread topsoil 4" deep from pile to rough finish grade, front end loader, per cubic yard 2,700 $7.69 $20,760.70
2c Fescue, tractor spreader, per 1,000 square feet 220 $30.88 $6,793.09
EROSION AND SEDIMENTATION CONTROLS $16,720.00
SITE RESTORATION $44,603.11
PROPOSED BOND TOTAL FOR WEST SIDE $61,323.11
EAST OF RAILROAD
EROSION AND SEDIMENTATION CONTROLS
1a Anti-tracking pad, per square yard 200 $30.00 $6,000.00
1b Sediment barrier, install and maintain, per linear foot 2,330 $8.00 $18,640.00
SITE RESTORATION
2a Hay, 1" deep, power mulcher, large, per 1,000 square feet 500 $77.50 $38,748.46
2b Spread topsoil 4" deep from pile to rough finish grade, front end loader, per cubic yard 6,150 $7.69 $47,288.26
2c Fescue, tractor spreader, per 1,000 square feet 500 $30.88 $15,438.84
EROSION AND SEDIMENTATION CONTROLS $24,640.00
SITE RESTORATION $101,475.57
PROPOSED BOND TOTAL FOR EAST SIDE $126,115.57
Note: Bond estimate prepared using RSMeans Heavy Construction Cost Data, 30th Edition, 2016, New London, adjusted for inflation.