HomeMy WebLinkAboutApplicant ResponsesFULLER ENGINEERING & LAND SURVEYING, LLC
525 John Street – Second Floor – Bridgeport, CT 06604
Phone: (203) 333-9465 Fax: (203) 336-1769
The Quill Group
Fuller Engineering & Land Surveying, LLC Civil Engineering, Landscape Architecture, Surveying
Atlantic Consulting & Engineering, LLC Geotechnical, Structural, Mechanical, Electrical, & Plumbing
Fairfield Testing Laboratories, LLC Materials Testing, Inspection, & Certifications, Special Inspections
P a g e | 1
8 March 2022
Mrs. Liz Burdick
Planning Director
Town of Montville
RE: Response to Comments
22 Unit Condominium
245 Route 32
Uncasville, Connecticut
The following are our responses to comments from multiple departments in a letter from various review
agencies. Our responses are designated in italics.
Engineering - Thomas Cummings, P.E., CLA Engineers, Inc. dated 2/7/2022
1. Sidewalk installation on Rt. 32 must be provided on the plans
Response: A 5’ wide concrete sidewalk has been added to plans.
2. Handicap parking must be shown in the visitor parking area.
Response: Two (2) van accessible (16’ wide) handicap parking spaces have been added
to the plan.
3. Pedestrian access to Route 32 and from the visitor parking area must be provided on the plans.
Response: A walk way connection has been added to the new pedestrian walk along
Route 32.
4. The construction of Building 1 immediately adjacent to the existing house is impractical.
Response: The existing house will be modified to provide a seamless connection to the
new Unit 2.
5. Evidence of submission to CT DOT District 2 must be provided.
Response: The project has been submitted to CT DOT.
6. Tree clearing must be adjusted for installation of a drainage outfall.
Response: The tree clearing limit line has been modified to reflect the revised drainage
outfall.
7. A detail of the decorative wall must be provided on the plans.
Response: As Stone wall with mortar core has been added to the details Sheet C-6.1.
The Quill Group
Fuller Engineering & Land Surveying, LLC Civil Engineering, Landscape Architecture, Surveying
Atlantic Consulting & Engineering, LLC Geotechnical, Structural, Mechanical, Electrical, & Plumbing
Fairfield Testing Laboratories, LLC Materials Testing, Inspection, & Certifications, Special Inspections
P a g e | 2
8. The plans show a stockade fence and the wall details shows a chain link fence; this must be
clarified.
Response: The intent is for a proposed stockade fence. The detail has been modified.
9. The rear eaves and setback lines may be in conflict.
Response: The buildings have been shortened to provide a one-foot (1’) separation
between the building setback line and the building.
10. The exterior lighting must be shown on the plans.
Response: Lighting has been added to the plan sets and detailed on Sheets C-5.1 and C-
6.1.
11. The proposed signage on the site must be added to the plans.
Response: Signage has been added to Sheet C-2.1.
12. A detail of the walls at the front of several units must be added to the plans.
Response: A low wall detail has been added to Sheet C-6.1.
13. Sheet C-3.1 Note 5 must be updated.
Response: The note has been updated to refer to the 2002 Connecticut Erosion &
Sedimentation Guidelines.
14. Past test pit locations must be shown on the plans. Additional testing may be needed in the
proposed subsurface drainage areas including permeability test – 5 per CT DEEP
recommendations.
Response: Test pit locations have been added to Sheet C-3.1.
15. Spot grades must be shown on the plans as needed in parking areas and the dumpster pad.
Response: Additional spot elevations have been added to Sheet C-3.1.
16. A note must be added to the plans regarding a CT Licensed Engineer designing and inspecting
the block wall installation..A wall detail more appropriate to the filling required on the site must
be provided.
Response: Note 9 has been added to Sheet C-3.1 indicating final design by a licensed
Connecticut engineer and approval prior to issuance of a building permit.
17. The installation of the wall at the property line is impractical.
Response: All walls along the property line have been moved to provide one foot (1’)
minimum separation to the property line.
18. The installation of fencing along the retaining wall must be shown behind the wall on the site
plan.
The Quill Group
Fuller Engineering & Land Surveying, LLC Civil Engineering, Landscape Architecture, Surveying
Atlantic Consulting & Engineering, LLC Geotechnical, Structural, Mechanical, Electrical, & Plumbing
Fairfield Testing Laboratories, LLC Materials Testing, Inspection, & Certifications, Special Inspections
P a g e | 3
Response: Fencing is now shown behind the retaining wall.
19. Access to the rear of the property for any reason is impractical.
Response: A gated access ramp has been added to the southwestern wall corner.
20. The landscaping shows trees being installed in the area of gravity and force main locations along
with stoops and walls and other services.
Response: Although tree placement is schematic, the utility lines and trees have been
shifted to avoid conflict. Since utilities will be installed prior to tree placement, actual
locations of trees will be adjusted as required.
21. The plans indicate 10” dia. RCP pipe?
Response: The designation “RCP” has been replaced with “SCH 80 PVC”.
22. The subsurface retention systems must provide a method for inspection.
Response: Staggered 18” diameter observation ports have been placed on opposing
ends of each galley on Sheet C-3.1.
23. The proposed plunge pool will concentrate flow that is now shown as sheet flow to the
downstream neighbor. A method to spread the stormwater flow must be provided.
Response: The plunge pool has been replaced by a level spreader which will provide
overland sheet flow on Sheet C-3.1.
24. The silt fencing shown on the plans will conflict with wall installation. The easterly side of the
site must have more substantial sediment control.
Response: The silt fence has been adjusted to provide more room for installation.
Haybale backing has been added to the silt fence line to provide stronger backing.
25. A temporary sediment pond in the easterly side of site must be provided on the plans.
Response: A temporary sediment basin (pond) has been added at the location of the
level spreader and sized per the 2002 Connecticut Guidelines for Soil Erosion and
Sediment Control.
Temporary diversion berms with stone check dams at 50’ intervals have been added to
direct water to the sediment basin
26. The E&S Control Plan must site specific with the proposed construction sequence detailed as
well as specific individuals responsible for the E&S Controls.
Response: E&S notes and detail sheet has been revised on Sheet C-
27. An E&S Control Bond Estimate must be provided for review.
Response: A bond estimate is provided herein.
The Quill Group
Fuller Engineering & Land Surveying, LLC Civil Engineering, Landscape Architecture, Surveying
Atlantic Consulting & Engineering, LLC Geotechnical, Structural, Mechanical, Electrical, & Plumbing
Fairfield Testing Laboratories, LLC Materials Testing, Inspection, & Certifications, Special Inspections
P a g e | 4
Planning - Liz Burdick, Planning Director dated 03/02/22
1. ZR Section 4.11.5 (Multi-Family Dwellings):
Response: Acknowledged.
2. Revise plan set to add Title Sheet with Sheet Index, names of applicants, property owners,
property address with map/block/lot numbers, etc.
Response: Sheet C-0 has been added to the plan set.
3. Sheet “Zoning Improvement Location Plan”:
a. Delete duplicate zoning compliance table on this sheet
Response: Only one zoning compliance table is included on this sheet.
b. Benchmark needs to be shown on plan
Response: The existing nail found in SNET pole 2749 has been added.
c. ZR Sec 17.2.4 – survey / site plan requirements can be found in this section.
Response: Acknowledged. All materials in this submission package are certified
by a licensed engineer or surveyor as required by ZR Sec 17.2.4..
d. Notes –
1. Note 3 – Note map reference for dependent resurvey.
Response – Reference to “Map References” added.
2. Note 8 – revise to add “and is located in the Route 32 Overlay Zone (OZ).
Response: Overlay zone added.
3. Note 10 – Show FEMA map info.
Response – FEMA map reference added.
4. Sheet C-2.1:
a. Map references #2 – Third Line – Delete “Dennis A” and throughout the plan set as
needed.
Response: All references to Dennis A have been removed throughout the plan
set.
b. Notes: Remove multiple references to Town of Norwalk and Note 8 Show FEMA info for
the subject property.
Response: References to Norwalk have been removed. Note 8 has been updated
with specific map information.
The Quill Group
Fuller Engineering & Land Surveying, LLC Civil Engineering, Landscape Architecture, Surveying
Atlantic Consulting & Engineering, LLC Geotechnical, Structural, Mechanical, Electrical, & Plumbing
Fairfield Testing Laboratories, LLC Materials Testing, Inspection, & Certifications, Special Inspections
P a g e | 5
c. Plan notes 2 “2-car garage”, floor plans show 1-car garage. Revise to identify 1-car
garage and 1 parking space.
Response: Plans have been revised to indicate “1” Car garages.
d. “Existing House to Remain” appears to be only partially connected to new construction,
but connected on elevation drawings. Please clarify.
Response: The gap between the existing house to remain and proposed Unit 2
will be merged with a common wall.
e. Outlet structure is shown outside limits of clearing. Revise clearing limits and add notes
clearing limits shall be clearly identified prior to start of any work.
Response: The clearing limit line has been revised to allow room for construction
of outlet structure.
A Note 9 has been added to the plan indicating establishment of the clearing
limit line prior to any sitework activities.
f. How will refuse area (see Dumpster Pad Enclosure” detail) be accessible to trash
removal trucks.
Response: The refuse area has been moved to the northwest parking area. A
standard gated refuse area which allows for more efficient front loading is now
provided.
g. Revise zoning compliance table to show accurate “requirements” (min. lot area
40,000/10,000 public sewers, frontage 80, Maximum height – none.)
Response: The zoning table has been revised with data from the C-1 and OZ
zone.
5. Sheet C-3.1 – Note 4 – add zoning dept. & fire marshal’s office.
Response: Note 4 has been updated to include the departments above.
Note 5 Reference 2002 CT E&S Guidelines.
Response: Note 5 has been updated to the current 2002 CT E&S Guidelines reference.
Wetlands Table – update with recent soil scientist identification (v. GIS).
Response: Wetland table has been updated to indicate the absence of wetlands as
flagged by Aleksandra Moch on February 12, 2022.
6. Sheet C-3.2 – Note 9 – Revise to remove reference to Norwalk. Note 13.1 – typo.
Response: The note has been corrected to indicate the Town of Montville.
The Quill Group
Fuller Engineering & Land Surveying, LLC Civil Engineering, Landscape Architecture, Surveying
Atlantic Consulting & Engineering, LLC Geotechnical, Structural, Mechanical, Electrical, & Plumbing
Fairfield Testing Laboratories, LLC Materials Testing, Inspection, & Certifications, Special Inspections
P a g e | 6
7. Sheet C-4.1 (E&S Control Plan) Silt fence is shown outside clearing limits.
Response: The silt fence has been modified to the revised clearing limits.
Silt fence at toe of slope needs to be reinforced with hay bales and other measure, topsoil
stockpile area with silt fence needs to be added to the plan.
Response: The plan has been revised to include a double row of silt fence and haybale
protection.
Show any construction staging areas (office trailer, laydown, etc.).
Response: A topsoil stockpile area has been added to the north west corner of the
property.
Note 3, line 2. Delete “and will require review and approval by Town of Montville Building
Dept.”.
Response: Montville Building Dept wording has been removed.
Note 4 – Reference 2002 CT E & S Guidelines.
Response: Reference to the 2002 CT E&S Guidelines has been added to Note 4.
Add construction sequencing notes.
Response: Construction sequencing notes have been added to Sheet C4.2.
8. Sheet C-6.1 to 6.3 – Add notes regarding maintenance of drainage structures.
Response: An Operations and Maintenance Plan has been added to Appendix O of the
Engineering report.
9. ZR Sec. 15.1 (SESC) – Submit SESC bond estimate for review & approval by Town Engineer.
Response: An SESC bond estimate has been included in this response.
10. ZR Sec. 17.3 (GIS) – Digital data in accordance with this section shall be provided to the Planning
Office prior to issuance of any zoning permit to start work.
Response: Acknowledged – the required digital data will be provided prior to issuance of
any zoning permit.
11. ZR Sec. 17.4.11 – Revise to show locations, size, and arrangement of pedestrian walkways /
sidewalks (guest parking).
Response: Plans have been revised to show additional parking per zoning requirements.
Pedestrian walkways have been added to the plans.
The Quill Group
Fuller Engineering & Land Surveying, LLC Civil Engineering, Landscape Architecture, Surveying
Atlantic Consulting & Engineering, LLC Geotechnical, Structural, Mechanical, Electrical, & Plumbing
Fairfield Testing Laboratories, LLC Materials Testing, Inspection, & Certifications, Special Inspections
P a g e | 7
12. Revise plan to show sidewalks along Rte. 32 for the length of the property frontage.
Response: A pedestrian walkway has been added along Route 32.
13. 14.4.14 (Lighting) – Add lighting plan sheet showing site lighting locations and details.\
Response: Pole and accent lighting has been added to Sheet C-5.1. Lighting details have
been added to Sheet C-6.1
14. ZR 17.4.21 – Revise plan to add signature blocks (PZC, IWC, Plan expiration, SEC Plan approval,
etc. to lower right hand corner of plan set.
Response: Signature block has been revised to include additional department approvals.
15. ZR Sec. 18.3.2 (Parking Multi-family Dwellings) 2 ½ spaces for each unit required. Revise
parking table and show additional parking spaces needed to comply.
Response: Additional spaces and a revised parking table have been provided on Sheet C-
2.1.
16. ZR Sec. 19 (Signs) – The location and details of any proposed new complex signage, directional
signage, traffic signage shall be shown on the plan sheet to be approved as part of this site plan
application OR a separate zoning permit for review & approval of the Zoning Official will be
required.
Response: Directional signage has been added to the C-2.1. A proposed complex sign is
proposed on the face of the proposed decorative stone wall along Route 32.
17. Elevation Drawings – Basement level of proposed units appears to contain a fourth bedroom.
Please clarify. Review by Building Official required.
Response: Elevation drawings have been revised to remove implication of a fourth
bedroom.
Fire - Paul D. Barnes, Fire Marshal dated 3/7/22
1. 2 hour rating for garage.
Response: Acknowledged – will be addressed with the building department submission
phase.
2. Min 1 hour rated fire door from garage to residence.
Response: Acknowledged – will be addressed with the building department submission
phase.
3. Stepped construction requires 2 hour fire separation from slab to roof peak.
The Quill Group
Fuller Engineering & Land Surveying, LLC Civil Engineering, Landscape Architecture, Surveying
Atlantic Consulting & Engineering, LLC Geotechnical, Structural, Mechanical, Electrical, & Plumbing
Fairfield Testing Laboratories, LLC Materials Testing, Inspection, & Certifications, Special Inspections
P a g e | 8
Response: Acknowledged – will be addressed with the building department submission
phase.
4. No indications of smoke alarms / CO2 alarms.
Response: Acknowledged – will be addressed with the building department submission
phase.
5. Identify heating system.
Response: Acknowledged – will be addressed with the building department submission
phase.
6. Concern about one way in / one way out IFC sect 503.1.2.
Response: Maximum width of main driveways has been provided for 2 way circulation
(24’) No Parking signage has been added to prevent parking within the travel lane area.
7. Require parking signs to deter on street parking.
Response: No Parking signs have been added at the island areas along the main
driveway to maintain maximum access for emergency vehicles, if required.
8. Add one hydrant midway down driveway.
Response: One hydrant has been added in an island on the northern side of the main
driveway.
Sedimentation and Erosion Controls Bond Estimate
245 Route 32
Montville, Connecticut
NO.DESCRIPTION UNIT QUANTITY UNIT PRICE COST
1 General Sedimentation and Erosion Control
Measures (aprons, swales etc)L.S. 1 2,000 2,000
2 Silt Fence L.F. 1,075 4.00 4,300
Haybales L.F. 250 4.00 1,000
3 Topsoil, Seed, Fertilizing, and Mulch
(Disturbed Area)S.F. 67,400 0.20 13,480
4 Landscaping (extent to provide for
restorationj and aesthetic considerations)L.S. 1 2,000 2,000
5 Grading for site restoration that will
provide safe and stable conditions.L.S. 1 2,000 2,000
6 Other
Subtotal 24,780
10% Contingency 2,478
TOTAL 27,258.00
NOTES:
The Quill Group
Fuller Engineering & Land Surveying, LLC Civil Engineering, Landscape Architecture, Surveying
Atlantic Consulting & Engineering, LLC Geotechnical, Structural, Mechanical, Electrical, & Plumbing
Fairfield Testing Laboratories, LLC Materials Testing, Inspection, & Certifications, Special Inspections
3/9/2022
Quantities and values provide our estimate for the restoration of the disturbed site to a stabilized condition and does not include drainage, paving, curbing,
landscaping or other improvements as specified on the plans.