TOWN OF MONTVILLE
OFFICE OF THE PLANNING DIRECTOR
310 Norwich-New London Turnpike, Uncasville, CT 06382
Telephone: (860) 848-6779
Email: lburdick@montville-ct.org
MEMORANDUM FOR THE RECORD
January 25, 2022 PZC Meeting
Prepared by Liz Burdick, Planning Director
Date: 01/19/2022
Property Address: 1967-1981 Route 32 (Parcel Ids: Map 99, Lots 61, 62, 64, 66, 68, 67)
Application: PZ #221Site4 for Site Plan review/approval.
Applicant(s): Garret Homes, LLC
Property Owner(s): Deborah Parker, Trustee of the Doris Antonino Family Trust.
Agent, if any: Matthew J. Bruton, PE, BL Companies
Legal: Submitted to Planning Dept. on 10/29/21. Date of Receipt by PZC: 11/9/2021.
Tabled to 12/14/21 Meeting on 11/9. Extension granted by the Applicant on 12/26/21 to
(new) DRD: 1/25/2022.
IN REVIEW:
PROPOSAL: Application states “The proposed activity includes construction of a +/-10,700
[SF] retail building with new paved parking and loading areas, site lighting, concrete
walkways, stormwater management system, associated utilities and landscaping.”
REFERRALS COMMENTS:
UNCAS HEALTH DISTRICT: See comments 11/8 & 12/7/21. See recommended condition of
approval #1 below.
TOWN ENGINEER: All comments have been addressed. FIRE MARSHAL: No comments.
BUILDING DEPARTMENT: No comments.
WPCA: All previous comments have been addressed.
STCT DOT: Encroachment Permit approval outstanding.
BOND: $12,300 approved by Town Engineer in a form acceptable to Finance Director.
INLAND WETLANDS COMMISSION: N/A. No on-site wetlands/upland areas.
STATE OF CT DEPT. OF HEALTH: N/A.
PLANNER COMMENTS: STCT DOT encroachment permit comments/approval pending.
PLANNER RECOMMENDATION: APPROVE WITH CONDITIONS.
The following MOTION is suggested for any favorable approval:
I make a MOTION to APPROVE Application #221SITE4 1967-1981 Route 32, Uncasville, CT
in accordance with the application, supporting documents and a plan entitled “Land
Development Plans for Site Plan Application, Proposed Retail Development, 1981
Norwich-New London Turnpike (Route 32, Map 99, Lots 61, 62, 64, 66, 67, 68), Montville,
CT, Prepared for Garrett Homes, LLC, Prepared by BL Companies, Dated 10/29/21,
Revised to 12/10/21.”
This is a conditional approval. Each and every condition is an integral part of the
Commission decision. Should any of the conditions, on appeal from this decision, be
2
\\planning\planningoffice$\PZC\Applications\2021\221 SITE 4 1967 - 1981 Rte 32 -Proposed Retail
Development\Staff\PLANNER\221SITE4 1967Rte32 PlannerComments 3 1252022Mtng.doc
found to be void or of no legal effect then this conditional approval is likewise void.
Should any of the conditions not be implemented by the applicant or his successors
within the specified permit time period, then this conditional approval is void. The
applicant may re-file another application review.
The conditions of approval are:
1. Prior to approval of a zoning permit to start work, the plan sheet entitled “Lot Line
Modification Plan, Sheet No. BS-1, Land of Deborah Parker, Trustee, Route 32,
Montville, CT Dated 10/26/21, Revised to 12/13/21” shall be filed on the Montville
Land Records in the office of the Town Clerk.
2. Final plan sets shall be submitted and shall be signed and sealed by P.E. & L.S.
3. Per Uncas Health District, All existing wells must be abandoned by licensed well
driller and an asbestos inspection must be conducted for each house and
abatement done, if necessary, prior to any demolition.
4. Prior to issuance of a zoning permit to start work, a soil erosion & sediment control
bond shall be posted in the amount of $12,300 in a form acceptable to the
Finance Director. Soil Erosion and Sediment Controls shall be installed and
inspected by the ZEO prior to the start of any work.
5. A separate application shall be submitted for any future site signage.
6. An approved State of Connecticut DOT Encroachment Permit is required prior to
the issuance of a zoning permit to start work. Any changes to the above-
referenced approved site plan require review and approval by the Planning
Director and/or the Planning & Zoning Commission.
7. An approved zoning permit is required prior to the start of any work.
8. The ZEO must be contacted and a pre-construction meeting shall be held at least
24- hours prior to start of any work.
9. Post-Construction Requirements as follows:
After construction is completed and accepted by the Owner, it shall be the
responsibility of the Owner to maintain all drainage structures as shown on Plan
Details Sheet DN-6. In addition, the following inspection and maintenance
guidelines shall be the responsibility of the Owner, beginning the first year period
following construction completion and acceptance, and shall be followed each
year thereafter:
1. Inspect every six (6) months during the first year of operation and adjust
the Inspection Interval based on previous observations of sediment accumulation
and high water elevations.
2. Conduct jetting and vactoring annually or when inspection shows that
maintenance is necessary.
3. Drainage and other Paved Areas: Inspect on a regular basis not to exceed
weekly for litter and debris. Sweep at least twice a year, with the first
3
\\planning\planningoffice$\PZC\Applications\2021\221 SITE 4 1967 - 1981 Rte 32 -Proposed Retail
Development\Staff\PLANNER\221SITE4 1967Rte32 PlannerComments 3 1252022Mtng.doc
occurring as soon as possible after first snowmelt and the second not less than
90 days following the first.
4. Catch Basin Sumps: Inspect semi-annually and cleaned when the sump is one
half full of silt and/or debris.
5. Landscaped Areas: Inspect semi-annually for erosion or dying vegetation.
Repair and stabilize any bare or eroded areas and replace vegetation as
soon as possible.
Please contact me with any questions or comments. Thank you.