HomeMy WebLinkAboutStaff Report (10-18-2010)
Michael Matera
137 Oxoboxo Dam Rd
Permit Renewal of 205 IWC 31
Meeting Date: October 21, 2010
Date Received by Commission: October 21, 2010
H:\APPLICATIONS\IN PROCESS\WETLANDS ONLY\OxoboxoDamrd-M45L8A-Matera renewal\Staff\Inland Wetlands\Staff
Review\Oxoboxo Dam rd 137-M45L8A- Matera renewal staff report 10-18-10.doc
Assessor Map
Applicant Request
- Renewal of Permit 205 IWC 31 for the restoration of an existing dam and the
expansion of an existing pond
Activity Description
Wetland Disturbance 8,900 sq ft
Upland Review Disturbance 6,500 sq ft
Creation of New Wetlands 4,800 sq ft
Staff Comments
Original permit was granted in October of 2005 therefore this is the first renewal
Since that time the applicant has been working with state agencies to acquire
additional permits
Additional permitting had put a financial hardship on the project until now
There will be no changes from the original permit
H:\APPLICATIONS\IN PROCESS\WETLANDS ONLY\OxoboxoDamrd-M45L8A-Matera renewal\Staff\Inland Wetlands\Staff
Review\Oxoboxo Dam rd 137-M45L8A- Matera renewal staff report 10-18-10.doc
H:\APPLICATIONS\IN PROCESS\WETLANDS ONLY\OxoboxoDamrd-M45L8A-Matera renewal\Staff\Inland Wetlands\Staff
Review\Oxoboxo Dam rd 137-M45L8A- Matera renewal staff report 10-18-10.doc
Draft Motion
After giving due consideration to all relevant factors including those in Section 10 and or
Section 4 of the Montville Inland Wetland Regulation and Section 22a-41 of the
Connecticut General Statutes, I make a motion to approve the following application
210 IWC 23 Michael Mater: The renewal of application 205 IWC 31 for the restoration of Dam
No. 8624 and the expansion of existing pond on the property located at 137 Oxoboxo Dam Road,
Oakdale, Ct. As shown on Assessor’s Map 45 Lot 8A. As depicted on the planes titled “Pond
Improvement Plan Prepared for Michael J. Matera 137 Oxoboxo Dam Rd Prepared by CME
Associates Inc, 110 Broadway, Norwich Ct” dated 10/5/2005 and the renewal application and
narrative dated 10/17/10.
This is a conditional approval. Each and every condition is an integral part of the
Commission decision. Should any of the conditions, on appeal from this decision, be
found to be void or of no legal effect then this conditional approval is likewise void.
Should any of the conditions not be implemented by the applicant or his successors
within the specified permit time period, then this conditional approval is void.
Conditions of approval are:
Standard Reasons for approval apply