HomeMy WebLinkAboutRFI 007 - Helical Pile work - answered by PBA - 190913Distribution to: OWNER X ARCHITECT X ENGINEER 13 Wheeling Ave Woburn, MA 01801 781-935-6100 REQUEST FOR INFORMATION NO. 7 PROJECT:OXOBOXO LOFTS RFI #7 INITIATION DATE:09/11/19 FROM:Maggiore Construction Corporation DATE NEEDED:09/20/19 13 Wheeling Avenue Woburn, MA 01801 REQUESTED BY:Gifford Perry EMAIL: gifford@maggiorecos.com TO:Paul B. Bailey Architect 110 Audubon Street New Haven, CT 06510 ATTENTION:Susan Odell- email: susan@pbbarchitect.com Frank Brachanow-Email Fbrachanow@dakotaPartners.net SUBJECT: REQUEST: 1)Yantic River Consultants wrote a scour report about the helical pile installation and associated work. Should you contact them about us starting the helical piles October 1st?I will notify Dan Morrissey, Brandon Hatfield & Frank Vacca. Should they or someone else witness the installation and observe?Dan Morrissey should comment on the need for observation. Should the grout bags after placement be covered with riprap? This is time sensitive and needs quick turn around, pile work is scheduled to start October 1, 2019 Answered By: Company: Date:9/12/2019 Helical Pile work Susan Odell Paul B. Bailey Architect LLC Riprap was eliminated from the design based on scour report recommendation. Structural drawing S3.3 refers to civil drawings for backfill of grout bags, but cannot find information Riprap backfill was eliminated from the design based on scour report recommendation.