HomeMy WebLinkAboutMaggiore - RFI - LOG - 191010OXOBOXO LOFTS 10/10/2019
RFI TRACKING LOG
Resubmit
Or
Number Description Prepared By Sent To Date Sent Date Needed Date Returned Complete
1 Courtyard access GP PBB 29-Jul-19 5-Aug-19
2 Follow up to addendum#06 GP PBB 30-Jul-19 6-Aug-19
3 Gas service & meters GP PBB 1-Aug-19 9-Aug-19
4 Buildng M basement GP PBB 1-Aug-19 9-Aug-19
5 Sprinkler service off Route 32 GP PBB 1-Aug-19 9-Aug-19
6 Rotted beams GP PBB 6-Sep-19 20-Sep-19
7 Helical Piles GP PBB 11-Sep-19 20-Sep-19
8 Grout bag work at Helical piles GP PBB 20-Sep-19 23-Sep-19
9 Building B sub-basement walls GP PBB 26-Sep-19 11-Oct-19
10 Roofing questions at eaves & rakes per SHPO GP PBB 2-Oct-10 16-Oct-19
11 Bldg B level B existing conditions GP PBB 9-Oct-19 23-Oct-19
12 AB Connector foundation GP PBB 9-Oct-19 23-Oct-19
13 Bldg G window height GP PBB 10-Oct-19 24-Oct-19
14 Fire protection clarifications for on code GP PBB 10-Oct-19 24-Oct-19
15 Building B floor infilling GP PBB 10-Oct-19 24-Oct-19