HomeMy WebLinkAboutRFI Log - Oxoboxo - 191011STATUS
OPEN
CLOSED
CLOSED
OPEN
CLOSED
OPEN
OPEN
OPEN
OPEN
OPEN
OPEN
CLOSED
CLOSED
CLOSED
CLOSED
OPEN
OPEN
NUMBER
RFI 01
RFI 02
RFI 03
RFI 04
RFI 05
RFI 06
RFI 07
RFI 08
RFI 09
RFI 10
RFI 40
RFI DP 101
RFI DP 102
RFI DP 103
RFI DP 104
RFI DP 105
RFI DP 106
TITLE
Entry Access into Courtyard
Addendum Six Questions
Gas Service
Building M Basement Access
Incoming Sprinkler Service
Rotted and Failing Beams
Helical Pile work
Grout for Helical Piles
Structural walls B Bldg
Roofing
Mechanical Heat Pumps
Ejector Pump gravity Loads
Sanitary Line on Pink Row (inverts-cross section)
Building Inspector's Queries
Utility Plan Update for 2nd Generator
Wright-Pierce WPCA Requests - Sanitary & Water
Sewage Ejector Pump
QUESTION
The courtyard at M building does not have any permanent access. Doesn't it make sense to install doube doors in the connector
for not only construction but for permanent access?
How will the courtyard be maintained if you can't get into it?
Can existing brick sidewalls take lateral pressure from gravel fill against it if we use soils to elevate the slabs in Buildings G, H, and J ???
Can onsite stone/gravel material be used for interior structural fill?
Provide structural details on how over framing is configured in K and M.
Confirm no gypcrete is needed in J and M now.
The gas company is requesting the following clarifications:
How many has meters do we have? Gas company recommends one.
The two generators should be fed from the base building per the gas company.
If you have separate meters for generators they would charge a demand fee since it's not use very much.
See attached gas company questions with initials for each company to review:
BSC- Town approved utility site plan showing location of gas mains and service risers. Plans must be stamped by town or a letter stating plans of date.
BSC - Plans should show the number of meters at each service riser.
BSC- A plan that identifies the site location on the street. ( see site plans)
PB- The average square foot of each of the building/apartment/home. Drwg R.3 divide 100,088/73 units? 1,371 SY? Assume you use gross SF? Please confirm. If applicable- How many apartment
units or homes will be constructed. (73)
A- Number of gas meters needed. (1) ?
A- List of gas fired equipment, Btu's and delivery pressure needed for equipment. (Will provide drawing P1 .1)
BSC- Will there be a gas fired generator? On it's own meter? Provide BTU input and delivery pressure for the gas fired generator.( need to show added second generator)
MC- If your equipment is currently operating on propane or oil please provide the gallons used over the last two years.
MC- Will there be phases to your project?
MC-How many years do you expect the project to take? ( 15 months)
(The natural gas agreement will provide the number of minimum meters needed with in a timeframe. If you do not meet the requirement, there could possibly be a penalty to make whole.)
MC- Your time frame of construction should tell me when you will need natural main, gas services and when you expect the meters to be turned on.
MC- Let me know if you will be using natural gas for construction heat. If so the BTU input for the temp heaters. Address and Name of Customer (if customer is an LLC, the entity must
be registered with the State of CT Sec. Of State).
Billing Address. (provide one if it will it be different from site location).
A natural gas easement will be needed if there are proposed gas mains being installed. Please provide the name of your Attorney and Surveyor (Point of contact, address and telephone
number). Please provide an A2 Survey.
1)There would appear to be no permanent access below building M first floor.
Is the reason it's in a flood zone and will not be used at all? If there is another reason should we install a permanent bulkhead for access at the old ramp to the basement or install
at the other end of the building?
2)I also don’t see any heat called for and concern about plumbing waste line
freezing. Should you specify heat trace? If we install heat trace access will be needed.
3)The drawings doesn’t specify after the ramp is removed how to close up the existing foundation opening, please show details.
4)The basement sub slab calls to be infilled and a new poured slab.
In order to save money can we leave the slab as is and not place new concrete?
If new slab is required confirm what elevation to pour to.
5)Sprinkler company is using NFPA rule that requires sprinkler coverage in the basement
not NFPA-R. We are planning to install a dry system, we need to discuss placement of equipme for the dry system. Again permanent access will be required. Please clarify.
There is an existing 8" sprinkler service that was installed approx. 1989 and enters the pump house off building A
Can this service be reused and extended into building B?
See attached permit application and attached picture. You can see the new line far right of the picture before the backflow preveter.
There are numerous locations of failed or rottted beams. The current location is Building A level 2. We suspect this could be an ongoing issue as more areas are now open and become
known as demolition has started, however we can't wait until it's all completed.
Yantic River Consultants wrote a scour report about the helical pile installation and associated work.
Should you contact them about us starting the helical piles October 1st?
Should they or someone else witness the installation and observe?
Should the grout bags after placement be covered with riprap?
Structural drawing S3.3 refers to civil drawings for backfill of grout bags, but cannot find information.
This is time sensitive and needs quick turn around, pile work is scheduled to start.
In an effort to reduce the construction cost of the project to a level acceptable to the owner, the V/E consideration of changing
the nature of the Heat Pump units has been proposed for a substantial cost savings, inclusive of the ellimination of the ductwork. If selected these units would require a vertical space
in all units in the living room area.
Please update the Ejector Pump Fixture load count. The last revision of 2/22/19 indicated 50 units + common area
fixtures. The present count appears to be 59 units (1 studio, 30 1 BR, & 26 2BR units).
Attached is the 2/22/19 Loading sheet, along with the marked up Unit Mix R.3 sheet indicating the respective
gravity and ejector loads. Please confirm and revise.
In addition, please indicate the estimated Water Consumption for the project:
Domestic & Irrigation
WPCA requests the following:
1. Correct (on the plans) the Domestic Water Line connection on Pink Row.
2. BSC to check the inverts of the existing Sanitary line at Pink Row, and document same, and develop a crosssection
of the sanitary connection.
Attached is a brief summary of a meeting with WPCA on 7/18/19.
Attached are the Building Inspector’s 7/8/19 questions required for sign-off for the Building Permit.
Please respond.
Please update the Utility Plan to identify the 2nd Generator and gas connection to same.
Attached is a memo from Wright-Pierce dated 8-1-19 regarding the sanitary system & water meter locations.
Please respond to the respective items required:
1. BSC to follow up w/ DP #102
2. PBBA/AZTEC to confirm w/ Fire Marshall & design Engineer, fire protection needs.
3. PBBA/AZTEC/Williamson to confirm pump capacity avoids backups in the sanitary sewer.
4. PBBA/AZTEC to locate water meters.
Attached is a 1st draft proposal for the Sewage Ejector Pit.
Please review and advise.
2019-08-07 OX WILLIAMSON EJECTOR QUOTE
2019-08-07 OX EJECTOR OPTIONS
2019-08-07 OX WILLIAMSON SK EJECTOR DRAWING
ANSWER
1)Permanent access to Building M basement is provided at an areaway on South exterior wall per civil drawings issued 6/11/19 (CD Set).
2)Building M basement will be unconditioned space. Pipe insulation to be provided for all sanitary lines.
3)Details to be provided.
4)The basement sub slab can remain as is.
5)Dry system sprinkler system equipment is to be located in Sprinkler Room at Southeast corner of first floor of Buliding M.
Fixture load count provided by Aztech:
Ejector Load: 675.5 D.F.U.
Gravity Load: 155.0 D.F.U.
Domestic Usage: 163 G.P.M.
No irrigation is provided in Project.
Revised tables submitted 7/24/19
Frank Vacca completed items 1 and 2.
Final Utility Plan to be issued.
Answers to building Inspectors questions provided in Addendum 07 (8/5/19) and Addendum 07 additional items (8/16/19).
Draft Utility Plan C-5.0 (8/29/19) shows location of both generators.
Final Utility Plan to be issued.
RESPONDENT
PBA
PBA-Morrissey
PBA-BSC-Aztech
PBA-Aztech
PBA-BSC
Morrissey
Morrissey
RECEIVED
7/22/2019
7/30/2019
7/25/2019
7/25/2019
7/25/2019
9/6/2019
9/11/2019
7/8/2019
7/22/2019
7/22/2019
7/22/2019
7/22/2019
8/5/2019
8/8/2019
FORWARD
7/29/2019
7/29/2019
9/13/2019
9/13/2019
7/24/2019
7/24/2019
RETURN
10/3/2019
10/3/2019
9/13/2019
9/13/2019
7/29/2019
9/13/2019
7/29/2019
9/13/2019
DUE
ADDENDUM
DRAWINGS
NOTES
To be reviewed/approved by Dakota.
Raised floor design is to be wood framing and no gravel fill will be used.
Structural details for wood framing has been provided by structural engineer 9/12/19.
On hold for Gifford's review
Provide 1 meter for residential and generators combined.
On hold for Frank B.'s review
Provide foundation details.
8" water line from Route 32 can be used for both 4" domestic and 6" fire water with a tee close to building B. Frank Vacca to revised Utility Plan to indicate one existing 8" water
line from Route 32 to be tee'd near Building B to supply 4" domestic and 6" fire service. Meter locations need to be determied. Pink Row water service location to be determined.
Structural engineer to site visit and offer solution.
Dan Morrissey, Brandon Hatfield & Frank Vacca notified.
Dan Morrissey should comment on the need for observation.
Riprap was eliminated from the design based on scour report recommendation.
Architectural and MEP drawings providing the new vertical heat pump design to be submitted on 10/11/19.
Frank Vacca to revise Draft Utility Plan to show gas to generators coming from single meter location at Building F.
1. BSC to follow up w/ DP #102
Done
2. PBBA/AZTEC to confirm w/ Fire Marshall & design Engineer, fire protection needs.
Underway with Frank Vacca.
3. PBBA/AZTEC/Williamson to confirm pump capacity avoids backups in the sanitary sewer.
Pending possible redesign.
4. PBBA/AZTEC to locate water meters.
On hold for possible redesign to gravity only system.
4
1
1
3
2
CLOSED
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
NUMBER
RFI-001
RFI-002
RFI-003
RFI-004
RFI-005
RFI-006
RFI-007
RFI-008
RFI-009
RFI-010
RFI-011
RFI-012
RFI-013
RFI-014
RFI-015
RFI-016
RFI-017
RFI-018
RFI-019
RFI-020
RFI-021
RFI-022
RFI-023
RFI-024
RFI-025
RFI-026
RFI-027
RFI-027R1
RFI-028
RFI-029
RFI-030
RFI-031
RFI-032
RFI-033
RFI-034
RFI-035
RFI-036
RFI-037
RFI-038
RFI-039
TITLE
Missing Landscape Plans
Aluminum Windows
Window and Door Schedules
Missing MEP Details
Civil CAD files
Light Fixtures
Building Permit
Stacked Meters
Missing Partition Tags
Missing Window Designations
Not Issued
Location of Window Elevations
Pex Tubing for Domestic Water
Various Electrical Questions
PVC Waste Piping
Smoke Detector Locations
Pex Tubing for HVAC
Various HVAC questions
Plaster Walls at Building B
Roof Penetrations
Roof Gutters
Roof Insulation
Window Review
Fire Alarm Questions
Fire Alarm Questions
Fire Alarm Questions
Roof Ventilation
Roof Ventilation
Low Voltage
Window Screens
Double-Hung Window Units
Electrical Code Update
Electrical Panels
Windows
Civil CAD files - existing conditions
Electrical Drawing Update
Walls at Bathtubs
Sewer Ejector
Gas Service
Finish Flooring
RECEIVED
12/28/2018
12/28/2018
12/28/2018
1/2/2019
1/3/2019
1/3/2019
1/3/2019
1/3/2019
1/7/2019
1/7/2019
12/1/2018
1/7/2019
1/7/2019
1/7/2019
1/7/2019
1/7/2019
1/7/2019
1/7/2019
1/8/2019
1/8/2019
1/8/2019
1/8/2019
1/10/2019
1/10/2019
1/11/2019
1/11/2019
1/11/2019
1/11/2019
1/11/2019
1/18/2019
1/21/2019
1/21/2019
2/4/2019
2/4/2019
2/4/2019
2/6/2019
2/7/2019
2/12/2019
2/12/2019
2/28/2019
FORWARD
1/4/2019
1/4/2019
1/4/2019
1/4/2019
1/9/2019
1/9/2019
1/9/2019
1/9/2019
1/9/2019
1/9/2019
1/14/2019
1/14/2019
1/14/2019
1/14/2019
1/14/2019
2/1/2019
2/8/2019
2/6/2019
2/13/2019
2/13/2019
RETURN
1/17/2019
1/14/2019
1/14/2019
2/1/2019
1/29/2019
1/14/2019
1/14/2019
1/17/2019
2/1/2019
1/14/2019
12/1/2018
1/14/2019
1/29/2019
2/1/2019
1/29/2019
2/1/2019
2/1/2019
1/29/2019
1/14/2019
2/1/2019
1/14/2019
2/1/2019
1/14/2019
2/1/2019
1/30/2019
2/1/2019
1/14/2019
2/1/2019
1/30/2019
2/1/2019
2/1/2019
2/1/2019
3/5/2019
2/14/2019
2/8/2019
2/25/2019
2/14/2019
2/28/2019
DUE
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/1/2019
2/15/2019
2/11/2019
2/11/2019
2/13/2019
2/14/2019
2/20/2019
2/20/2019
3/7/2019
RESPONDENT
BSC
PBA
PBA
Aztech
BSC
PBA
PBA
Aztech
PBA
PBA
PBA
PBA
Aztech
Aztech
Aztech
Aztech
Aztech
Aztech
PBA
Aztech
PBA
PBA
PBA
Aztech
Aztech
Aztech
PBA
PBA
Aztech
PBA
PBA
Aztech
Aztech
PBA
PBA/BSC/Surveor
Aztech
PBA
BSC/Aztech
BSC/Aztech
PBA
ADDENDUM
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
DRAWINGS
NOTES
list of changes due 2/13 and revised drawings due 2/25