HomeMy WebLinkAbout2020-04-30 Oxoboxo Mtg Min 38#16-063
Oxoboxo Lofts, Uncasville , CT
MEETING MINUTES #38
PROJECT: Oxoboxo Lofts
42 Pink Row
Uncasville, CT
DATE: April 30, 2020
TIME: 10:00 a.m.
LOCATION: Conf Call
Present:
Eric Kuczarski (EK) DP EKuczarski@DakotaPartners.net
Frank Brachanow (FB) Dakota Partners (DP) FBrachanow@DakotaPartners.net
Gifford Perry (GP) MC Gifford@MaggioreCos.com
Peter Lentine (PL) MC Peter@MaggioreCos.com
Susan Odell (SO) Paul B. Bailey Architect (PBBA) SOdell@pbbarchitect.com
Sam Kirby (SK) PBBA SKirby@pbbarchitect.com
Frank Vacca (FV) BSC FVacca@BSCGroup.com
Pat Callahan (PC) AZT PCallahan@aztecheng.com
Dan Morrissey (DM) Morrissey Engineers (ME) daniel.morrissey@morrisseyengineers.com
Minutes to:
Paul Maggiore (PM) MC Paul@MaggioreCos.com
Dave Mann (DM) Maggiore Construction (MC) Dave@MaggioreCos.com
Karl Walsh DP KWalsh@DakotaPartners.net
Marc Daigle DP MDaigle@DakotaPartners.net
Roberto Arista (RA) DP RArista@DakotaPartners.net
Evan Fink (EF) DP EFink@DakotaPartners.net
Matt Abraham (MA) DP MAbraham@DakotaPartners.net
Alycia Quintiliani DP aquintiliani@dakotapartners.net
Bill Rundlett DP Brundlett@dakotapartners.net
Kurt Prochorena (KP) BSC Group (BSC) KProchorena@BSCGroup.com
Brandon Handfield (BH) Yantic River Consultants Brandon@yrc-ne.com
Dean Azzam (DA) Aztech Engineers, Inc. (AZT) DAzzam@aztecheng.com
Tim Carr (TC) Down To Earth Consulting (DTEC) Tim@DownToEarthConsulting.com
Eric Marsh (EM) MC Eric@Maggiore.Co
James Sexton (JS) SHPO/NPS Consultant jmbjcs@hotmail.com
CONSTRUCTION DATES: Dam Removal: Start Date: Oct 18, 2019 EST. End Date: Unknown
Lofts Construction: Start Date: August 1, 2019 End Date: December 29, 2020
Responsible Party Priority Level
1.0 CONSTRUCTION SCHEDULE & PROGRESS
1.1 CONSTRUCTION SCHEDULE:
1.1.1 Status:
04/30 EK: Work is slowing down significantly for month of May
due to delay in DEEP approvals. If we don’t hear from DEEP in
May, June could be slow as well.
1.1.2 Covid 19 Delays:
04/30 PL: Work is slowing down for other reasons, so nothing to
report on Covid delays.
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #38
04/30/2020
Page 2 of 6
1.2 CONSTRUCTION PROGRESS:
1.2.1 Status:
04/30 PL:
COMPLETE: Bldg C D E Mechanical & Electrical inspections,
framing on A/B connector to 3, temp heat on M & H.
UNDERWAY: Bldg M Sheetrocking, Bldg H elec room encasement
of secondary lines w/concrete per BO’s request, Bldg D exterior
brickwork
NEXT: Sheetrocking everywhere except Bldgs A & B.
2.0 CONSTRUCTION TOPICS
2.1 SITE/CIVIL TOPICS:
(BSC – Frank Vacca)
2.1.1 Site/Civil Submittals & RFI’s:
04/30 GP: No submittals or RFI’s outstanding
2.1.2 Bldg M basement access:
04/30 FV: This is underway. Will send tomorrow.
BSC/FV
High
2.1.3 Area west of Bldg B:
04/30 CLOSED.
2.1.4 Ramp in lieu of steps between Bldg G & F:
04/23 GP: Ramp would be less expensive than steps. FV: Drainage
could be an issue. GP: Move wall packs from C to F for path
lighting on site plan & elec plan.
AZT & BSC
High
2.2 DEEP TOPICS:
(Yantic River Consultants – Brandon Handfield)
2.2.1 FMC Application to DEEP:
04/30 Not reviewed.
2.2.2 Helical Pile Installation:
04/30 Completion of work remains outstanding until FMC is
approved.
2.2.3 Grout Bag Submittal:
04/30 Completion of work remains outstanding until FMC is
approved.
2.3 ENVIRONMENTAL REMEDIATION TOPICS:
(Down To Earth – Tim Carr)
2.3.1 RAP Application to DEEP:
04/30 Not reviewed.
2.3.2 Injection System: (related topic below: equipment in Bldg M
Basement)
04/30 Not reviewed.
2.3.3 SVE Equipment:
04/30 Not reviewed.
2.3.4 Remediation in Courtyard:
04/30 Not reviewed
2.3.5 Equipment in M Basement:
04/30 Not reviewed.
2.3.6 Excavating and storing soils during storm drainage installation:
04/30 Not reviewed.
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #38
04/30/2020
Page 3 of 6
2.4 STRUCTURAL TOPICS:
(Morrissey Engineers – Dan Morrissey)
2.4.1 Structural Submittals & RFI’s:
04/30 GP: No structural RFI’s or submittals outstanding.
2.4.2 Cooling Tower Relocation:
04/30 DM: Working with PC on this. The sump tank needs a seal
under it per manufacturer. EK: Keep it as simple as possible. GP:
Least expensive for the sump would be to pour a 4”
housekeeping pad. It is not on manufacturer’s list of
recommended options. DEF asked the manufacturer & they
didn’t really answer the question. EK: If there is any risk, let me
know – Owner needs to make that decision. PC, you should be
involved also in getting this answer. PC: Whatever the solution is,
it won’t be higher than 6”, so we can proceed with locating the
tower.
ME/DM
High
2.4.3 Bldg F lintel:
04/30 PL: Sent photo to DM of door opening on east side. It is a
8’-6” opening, has failing brick above, was “repaired” with
railroad ties. Similar to Bldg H to Bldg K opening. DM: The
solution for the H to K opening should work here also.
2.5 MEP TOPICS:
(Aztech Engineers – Pat Callahan)
2.5.1 MEP Submittals & RFI’s:
04/30 GP: RFI 61 & 64 is outstanding. PC: RFI 61 should go out
today. Just received 64. GP: Submittals: short circuit study, site
lighting outstanding. EK: We accepted the short circuit study as
presented. GP: DA needs to update his comments to reflect this.
PC: Will check w/DA on site lighting & short circuit study.
AZT/DA/PC
High
2.5.2 Relocation of Cooling Tower:
04/30 PC: Work underway. Clearances in alleyway will work, leave
3 feet min. between chiller & retaining wall. Stair will be in the
clearance but can still maneuver around it. Working w/DEF to
obtain field measurements so we can finalize it. Have to review
layout inside Bldg F – need to keep pump & filter above flood line.
AZT/PC
Highest
2.5.3 Add Annunciator Panel in Bldg B entrance:
04/30 PL: Will add annunciator to Bldg B lobby. SK: Will do interior
elevations to ensure that mailboxes & annunciator will fit.
AZT/PBBA
High
2.5.4 Heat Distribution inside Units:
04/30 PL: Will send sketches next week for pricing. EK: Target
Tues/wed of next week.
AZT/PC
High
2.5.5 Exterior outlets:
04/30 SO: Need at least 6 exterior outlets by code for the 6 units
that have entry doors directly to the exterior. EK followed with
add’l exterior outlet requests via email. AZT to show on a dwg. PC:
Will need convenience outlet for the cooling tower which should
already be on the dwgs. SK: Look at lighting also. PC: Will check if
there is a light on the tower.
EK &
AZT/DA
High
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #38
04/30/2020
Page 4 of 6
2.6 ARCHITECTURAL TOPICS:
(Paul Bailey Architect – Sam Kirby)
2.6.1 Architectural Submittals & RFI’s:
04/30 GP: Same on submittals. Door frames/hardware still the
priority. SK: Working on doors/hardware today.
PBBA/SK/SO
High
2.6.2 Code Mod for outlets on short walls:
04/30 SO: Don’t need mod, there is language in the code for foyers
and corridors. Showing these areas in all units on floor plans so I
can review w/BO.
PBBA/SO
High
2.6.3 Lighting fixtures at top floors of Bldgs A & B/RCP’s:
04/16 SO: Will be reviewing RCP’s on site tomorrow.
04/23 EK: Review w/EF.
04/30 SO: Same.
PBBA/SO
High
2.6.4 MEP in corridors of Bldgs A & B:
03/19 SO: Will review if anything can move to crawl space in Bldg
A. Bldg B Basement underway. Need to review all other Bldg B
corridors.
03/26, 04/02, 04/09, 04/16, 04/23, 04/30 SK: Same.
PBBA/SK
High
2.6.5 Fireproofing of Bldg B Basement Floor:
04/30 SK sent detail. CLOSED.
2.6.6 Paint Color Schedule:
04/30 EK: SO to send recommendations on the colors to Liz for
approval, and an SK showing where colors start & stop. GP: Every
corridor has different heights of MEP in the ceilings. EK: Light
fixture drop & transition to black color should be consistent. SO:
Will review on site.
PBBA/SO
High
2.6.7 Bldg F Cooling Tower Enclosure:
04/30 EK: PBBA to issue SK’s on Bldg F roof changes after cooling
tower move to the ground is resolved. Don’t need door anymore
– keep door trim around the door opening & add clapboard inside
the door opening. PL: The metal deck is installed but not the
concrete slab. FB: Fire access? GP: Sprinklers? EK: Put this on hold
for now.
PBBA/SK
High
2.6.8 Postal & Package Delivery:
04/30 PBBA to issue sketch showing revised package room &
adding door to Community Room. PBBA to review for # of boxes
& layout & provide interior elevations.
PBBA/SO/SK
High
2.6.9 Gutter Color:
04/30 SO: Working on exterior trim colors w/PBB. PBB likes the
green that is on the lower buildings Will send selections to EK for
approval. EK: Want to include window colors in this so we have
the complete picture. Want all bldgs. Included.
PBBA/SO/SK
High
2.6.10 Door Schedule/Hardware:
04/30 SK: Will include electronic strikes in hardware submittal.
Doors that are egress only: outside trim includes a key cylinder.
SO: no key cylinder on the egress door from Bldg B subbasement
due to clearance issues. EK: Keep key cylinders on the other egress
doors.
PBBA/SK
High
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #38
04/30/2020
Page 5 of 6
2.7 SHPO/NPS APPROVALS:
(Paul Bailey Architect – Susan Odell)
2.7.1 SHPO/NPS: Existing wood flooring in Bldgs A & B:
04/16 SHPO sent amendment approval on 4/13.
04/23 Not reviewed.
04/30 No change.
2.7.2 SHPO/NPS Approval of Roofing Details
04/30 EK: SHPO approved roofing details.
2.7.3 SHPO/NPS Windows:
04/23 Window package “A” was sent to SHPO. Window package
“B” will be sent ASAP.
04/30 EK: Received feedback from SHPO on window pkg A – we
need to review.
PBBA/SO
Highest
2.7.4 SHPO/NPS Lighting Fixtures:
04/30 SO: Fixture schedule sent to JS & AR. They need to review
& provide any final comments. EK: Interior Designer is reviewing
also.
2.7.5 SHPO/NPS Masonry:
03/19 SO: After windows, will package the photos of the mortar
samples for Bldgs D, E, G, H, J, K, L, M & send to Historic
Consultants for review. Samples underway by Mason for Bldgs
A,B,C,F.
03/26 SO: Bldg G mortar sample approved.
04/02, 09, 16, 23, 30 SO: Will be sent to SHPO after items above.
PBBA/SO
High
2.7.6 SHPO/NPS Signage:
04/30 SO: Will assemble this package after the ones listed above.
2.7.7 SHPO/NPS Design Changes:
04/09 SO: Will assemble these 2 packages after the ones listed
above. 2 packages are Bldg E Vestibule & changing windows to
doors.
04/16, 23 Not reviewed.
04/30 EK: Add cooling tower relocation to list of design changes.
2.8 OWNER TOPICS:
2.8.1 Transformers/Eversource Coordination/Electric Meter location:
04/02 GP: Gerry said that all easement paperwork is sitting on
Joe Cassata’s desk. PL: Joe Cassata said that office was pretty
much shut down & they are not allowed in. Asked him if they
would provide power without the easement finalized. He said
probably not. EK: I will call Joe to find out who I need to mail
the paperwork to to keep this moving? Joe’s cell: 860-447-5746.
04/09 EK: Same.
04/16 EK: Currently playing phone tag w/Joe.
04/23 Not reviewed.
04/30 EK: Same.
DP/EK
High
2.8.2 Site Sign:
04/30 EK: On hold for now. CLOSED.
2.8.3 Blower Door Test:
004/30 EK: Need to sign the contract for the aeroseal work.
Aeroseal recommends adding foam gaskets to all electrical &
DP/EK
High
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #38
04/30/2020
Page 6 of 6
data outlets. GP, add this to the SOW. GP: Only on demising
walls? EK: Correct.
MC/GP HIgh
2.8.4 Meeting on Security:
04/16 GP: Gerry to send today.
04/23 GP: Change request sent to DP & SO for review.
04/30 GP: Need resolution so wires can be run if needed. DP/SO
to review & set up conf call if needed to review.
DP/EK/FB
PBBA/SO
High
2.9 CONSTRUCTION TOPICS:
2.9.1 Sewer Lateral out of Bldg M:
04/16 PL: Camera’d the line after obstruction was removed. Line
looked great. Need to design house trap including vent for house
trap. PC/SO/FV: Vent to run up through the sprinkler room inside
the building & vent out the roof. GP to check w/Plumber to see if
sketch is needed.
04/23 Not reviewed.
04/30 GP: Waiting to hear back from plumber.
MC/GP
High
2.9.4 Site Lighting:
04/16 EK: Answer sent – want both, with option to override the
photocells so lights can be turned on mid-day for maintenance.
GP: Will follow up w/Gerry.
04/23 Not reviewed.
04/30 GP: Same.
MC/GP
High
3.0 CHANGE ORDERS
3.1 Status:
04/30 Not reviewed.
4.0 REQUISITIONS
4.1 Status:
04/30 Not reviewed.
Conference calls will be held weekly on Thursdays at 10:00 am. Job site meetings will be held weekly on
Thursdays at 1:00 pm. Next up is a conference call at 10:00 am on May 7, 2020.
Recorded by Susan Odell, AIA, CPHC, Senior Project Architect, Paul B. Bailey Architect, LLC
These minutes are meant to convey & record the general content of the meeting, but do not represent a
verbatim recording. Please promptly respond to the Architect with any comments or questions.