MEETING MINUTES #32
PROJECT: Oxoboxo Lofts
42 Pink Row
Uncasville, CT
DATE: March 19, 2020
TIME: 10:00 a.m.
LOCATION: Job Site/Conf Call
Present:
Eric Kuczarski (EK) DP EKuczarski@DakotaPartners.net
Frank Brachanow (FB) Dakota Partners (DP) FBrachanow@DakotaPartners.net
Gifford Perry (GP) MC Gifford@MaggioreCos.com
Peter Lentine (PL) MC Peter@MaggioreCos.com
Eric Marsh (EM) MC Eric@Maggiore.Co
Susan Odell (SO) Paul B. Bailey Architect (PBBA) SOdell@pbbarchitect.com
Sam Kirby (SK) PBBA SKirby@pbbarchitect.com
Frank Vacca (FV) BSC FVacca@BSCGroup.com
Pat Callahan (PC) AZT PCallahan@aztecheng.com
Dan Morrissey (DM) Morrissey Engineers (ME) daniel.morrissey@morrisseyengineers.com
Minutes to:
Paul Maggiore (PM) MC Paul@MaggioreCos.com
Dave Mann (DM) Maggiore Construction (MC) Dave@MaggioreCos.com
Karl Walsh DP KWalsh@DakotaPartners.net
Marc Daigle DP MDaigle@DakotaPartners.net
Roberto Arista (RA) DP RArista@DakotaPartners.net
Evan Fink (EF) DP EFink@DakotaPartners.net
Matt Abraham (MA) DP MAbraham@DakotaPartners.net
Alycia Quintiliani DP aquintiliani@dakotapartners.net
Bill Rundlett DP Brundlett@dakotapartners.net
Kurt Prochorena (KP) BSC Group (BSC) KProchorena@BSCGroup.com
Brandon Handfield (BH) Yantic River Consultants Brandon@yrc-ne.com
Dean Azzam (DA) Aztech Engineers, Inc. (AZT) DAzzam@aztecheng.com
Tim Carr (TC) Down To Earth Consulting (DTEC) Tim@DownToEarthConsulting.com
James Sexton (JS) SHPO/NPS Consultant jmbjcs@hotmail.com
CONSTRUCTION DATES: Dam Removal: Start Date: Oct 18, 2019 EST. End Date: Unknown
Lofts Construction: Start Date: August 1, 2019 End Date: December 18, 2020
Responsible
Party
Priority
Level
1.0 CONSTRUCTION SCHEDULE & PROGRESS
1.1 CONSTRUCTION SCHEDULE:
1.1.1 Status:
03/19 PL: Will prep a 3-week look ahead starting next week for
weekly review. GP: FB, need updated construction schedule to
reflect reality through the end of March. FB: Will do.
MC/PL
DP/FB
High
High
1.2 CONSTRUCTION PROGRESS:
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #32
03/19/2020
Page 2 of 7
1.2.1 Status:
03/19 PL: Underway: Completing GWB in stair of Bldg B, hanging
supports for MEP in lower bldgs, framing of load-bearing walls in
C, installing ceilings in J H G, installing kitchens & bathrooms &
ductwork in all lower bldgs, Roof demo on lower bldgs, water line
installation from access road at RT 32, finishing electrical work in
area north of Bldg J.
Next week: Construction of stair in Bldg B, gyp-crete in A & B, Bldg
D southeast corner rebuild (pending weather), piping for Bldg D
Elec Rm, rotted exterior beam replacement on Bldg M,
installation of metal deck at F lower level.
2.0 CONSTRUCTION TOPICS
2.1 SITE/CIVIL TOPICS:
(BSC – Frank Vacca)
2.1.1 Site/Civil Submittals & RFI’s:
03/19 No outstanding submittals or RFI’s.
2.1.2 Encroachment Permit for Guardrail on Route 32:
03/19 FV: CSK sent out for review. We are now completely out of
the Route 32 right of way. Will clarify edge of right of way on the
drawing & review the drawing with the Transit Authority (per
Mayor’s request) & then the drawing can be submitted for
approval. EK: Keep it moving.
BSC/FV
Medium
2.1.3 Bldg M basement access:
03/19 On hold until FMC is resolved.
2.1.4 CSK-10:
03/19 FV: Minor changes to stairs at west side of Bldg B due to
water line installation. Will issue sketch for review. GP: Need
more design info for stair along Bldg A. FV: Will find a photo that
represents design intent.
BSC/FV
High
2.1.5 Roof Leaders:
03/19 FV: Roof leaders will be submitted as CSK-12.
BSC/FV
High
2.1.6 Site wall near J/M Connector:
03/19 FV/SO: Saw-cut existing wall & add brick cap. CLOSED.
2.1.7 Area between Bldgs F & G:
03/19 FV: Changes to this area are underway. PL: This is priority.
BSC/FV
Highest
2.2 DEEP TOPICS:
(Yantic River Consultants – Brandon Handfield)
2.2.1 FMC Application to DEEP:
03/19 EK: FMC was submitted last week. There is a 30 day public
notice period next. Need list of work from MC that needs to
occur in the floodway. I will set up a call w/BH for next Tuesday
to review the list & see if anything can be released. SO: Add
Courtyard access to the list.
MC/GP
DP/EK
High
High
2.2.2 Consent Order:
03/19 EK: Consent order has been resolved. CLOSED.
2.2.3 Helical Pile Installation:
03/19 Completion of work remains outstanding until FMC is
approved.
2.2.4 Grout Bag Submittal:
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #32
03/19/2020
Page 3 of 7
03/19 Completion of work remains outstanding until FMC is
approved.
2.3 ENVIRONMENTAL REMEDIATION TOPICS:
(Down To Earth – Tim Carr)
2.3.1 RAP Application to DEEP:
02/20 TC: Meeting last week w/DEEP went well. Have some
followup with them but they have internal discussions to have &
get back to us. EK: There is no official approval on the RAP – just
have to respond to DEEP comments. We are in good shape on the
RAP application – not holding up construction.
02/27 TC: Same.
03/05, 03/12, 03/19 Not reviewed.
2.3.2 Injection System: (related topic below: equipment in Bldg M
Basement)
02/20 TC: Still on hold until after closing. Shouldn’t be doing
remediation on someone else’s property. EK: Any weather-
driven dates? TC: Storing & mixing water-based solutions on the
ground would require to hold off until after any threat of hard
freeze. EK: May 1 start date? TC: Yes. Assume injection process
will take 1 month, then monitor for 4 months. DEEP was helpful
in being flexible with subsequent injections. After initial
injection, the process runs through within 6 months. 80% chance
of initial injection being successful. EK: Give me the exact cost of
starting this before closing.
02/27 TC: Working on cost - meeting with vendor next Tuesday.
Need Eversource contact to install insulating fleece on the wires
because we will be within 10 feet of the wires. PL: Will send
Eversource contact.
03/05, 03/12, 03/19 Not reviewed.
DTE/TC
High
2.3.3 SVE Equipment:
02/20 TC: Piping & wells are installed to Bldgs J,H & F. Finishing
stub-ups to Bldg F today. Remaining: electrical supply for SVE
blower & equipment installation after floor in Bldg F is installed.
SK: Vents going through the living spaces of buildings? TC: No
because we now have the crawl space to utilize.
02/27 TC: Adding stub-ups tomorrow.
03/05, 03/12, 03/19 Not reviewed.
DTE/TC
High
2.3.4 Remediation in Courtyard:
02/20 TC: Working on disposal of stockpile – we have approval for
an alternate disposal location but waiting for final approval. EK:
We would prefer to let stockpile remain until we can work in the
flood plain again so there is only 1 mobilization. Approval of FMC
is the key to this. PL: Parking is getting tight but we can wait for
removal of stockpile.
02/27 TC: Same.
03/05, 03/12, 03/19 Not reviewed.
DTE/TC
High
2.3.5 Equipment in M Basement:
02/20 TC: Equipment could be moved & stored while it is shut
down during the injection process. It is an old system – should be
scrapped. The problem is if we need to use it again, it would
need to be reconnected. I will try to find a temporary system that
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #32
03/19/2020
Page 4 of 7
could be used. The only thing of real value is the air compressor –
it is new. EK: TC to review equipment & instruct on what is to be
saved.
02/27 TC: Same.
03/05, 03/12, 03/19 Not reviewed.
DTE/TC
Medium
2.3.6 Excavating and storing soils during storm drainage installation:
02/27 GP: There is enough ash in the soil that we need to dig test
pits – planning to dig them tomorrow. TC: Surface is changing
from industrial paved surface to residential landscaped surface.
FB: Under a paved surface, you need 2 feet of cover over the ash.
Under a landscaped surface, you need 4 feet of cover over the
ash.
03/05, 03/12, 03/19 Not reviewed.
2.4 STRUCTURAL TOPICS:
(Morrissey Engineers – Dan Morrissey)
2.4.1 Structural Submittals & RFI’s:
03/19 DM: No submittals outstanding. GP: RFI’s 55 & 56 remain
outstanding.
2.4.2 Bldg F Structural Steel:
03/19 DM: RFI 55 – just received confirmation from AZT. Will
return this RFI today or tomorrow. FB to coordinate a follow-up
call to review drainage at the new concrete slab roof.
ME/DM
High
2.4.3 C/B Wall Repair:
03/19 DM: RFI 56 – will respond in writing to document verbal
agreement to build a new bearing wall in Bldg C.
ME/DM
Medium
2.4.4 Cracked Lintels in Bldg B:
03/19 DM: Sent approval. CLOSED.
2.4.5 Bldg A 2nd floor rotten headers over windows:
03/19 DM: Sent sketches this week. SK: Will forward SKS.
PBBA/SK
High
2.4.6 Columns in Bldg B North Tower:
03/19 DM: SKS’s 91 & 92 sent to document this. SK: Will forward
to GP ASAP.
PBBA/SK
High
2.5 MEP TOPICS:
(Aztech Engineers – Pat Callahan)
2.5.1 MEP Submittals & RFI’s:
03/19 PC: No submittals or RFI’s outstanding. GP: Seismic
restraint submittal outstanding – sent Feb 28. PC/SO: Did not
receive on Feb. 28. GP: Ok will send.
2.5.2 Laundry Room Redesign:
03/19 PC: Underway.
AZT/PC/DA
Highest
2.5.3 Site Lighting:
03/19 PC: DA asked for stripped down CAD file from FV but did not
receive. Will check with DA if he can work with the file. PC to
update EK on delivery schedule by end of day.
AZT/PC/DA
High
2.5.4 Ducts in Bldg B Basement Level:
03/12 SO: Clg height at beams is 7’-1”. We need to review all
ductwork in that level. PC: Send a redline plan to me & I will
review. SO: Will do.
03/19 SO: Same.
PBBA/SO
High
2.5.5 J/M Connector:
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #32
03/19/2020
Page 5 of 7
03/19 GP: Need full MEP drawings. SO: These are on hold until we
resolve where the courtyard access will occur.
2.6 ARCHITECTURAL TOPICS:
(Paul Bailey Architect – Sam Kirby)
2.6.1 Architectural Submittals & RFI’s:
03/19 GP: No submittals or RFI’s outstanding.
2.6.2 Gutters:
03/19 CLOSED
2.6.3 Updates to all drawings to reflect design changes:
03/19 SO: RCP’s are underway.
PBBA/SO/SK
High
2.6.4 Window openings on west side of Bldg B, basement level:
03/19 Details issued. CLOSED.
2.6.5 Bldg M Sprinkler Room:
03/19 Sketch issued. CLOSED.
2.6.6 Outlets on short walls:
03/19 SO: Need assistance with language of the request. Sent to
DA/PC for review today.
PBBA/SO
High
2.6.7 Lighting fixtures at top floors of Bldgs A & B:
02/13 GP: Some fixtures will be very high – should they change to
pendants? SO: Perimeter fixtures can remain as surface mounted;
fixtures in center should be pendants. Will update RCP’s.
02/20, 02/27, 03/05, 03/12 SO: Same.
03/19 SO: Will be answered on revised RCP’s.
PBBA/SO/SK
High
2.6.8 MEP in corridors of Bldgs A & B:
03/19 SO: Will review if anything can move to crawl space in Bldg
A. Bldg B Basement underway. Need to review all other Bldg B
corridors.
PBBA/SK
High
2.6.9 Fireproofing of Bldg B Basement Floor:
03/19 SO: We will provide a rating to spray fireproof the steel.
PBBA/SK
High
2.7 SHPO/NPS APPROVALS:
(Paul Bailey Architect – Susan Odell)
2.7.1 SHPO/NPS: Existing wood flooring in Bldgs A & B:
03/19 SO: JS sent the package to SHPO. Will ask JS for exact date
so we can track the 30 days.
PBBA/SO
Medium
2.7.2 SHPO/NPS Approval of Roofing Details
03/19 SO: Roof drawings reviewed by Historic Consultants this
week – we have 1 final comment on the drawings to complete –
will send package out on Friday. EK: We will have 1 final review
with historic consultants & Russ at DP on Friday or Monday
before releasing roofs to MC.
PBBA/SK/SO
Highest
2.7.3 SHPO/NPS Windows:
03/19 SO: Window details reviewed by Historic Consultants this
week – have 1 comment on the drawings to complete by end of
day today – will send revised package out & we can review when
we review the roofing details.
PBBA/SO
Highest
2.7.4 SHPO/NPS Lighting Fixtures:
03/19 SO: Cut sheets assembled, just need the fixture at the
exterior doors, then will send all cut sheets, lighting schedule &
plans to Historic Consultants for review.
PBBA/SO
High
2.7.5 SHPO/NPS Masonry:
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #32
03/19/2020
Page 6 of 7
03/19 SO: After windows, will package the photos of the mortar
samples for Bldgs D, E, G, H, J, K, L, M & send to Historic
Consultants for review. Samples underway by Mason for Bldgs
A,B,C,F.
PBBA/SO
High
2.7.6 SHPO/NPS Signage:
03/19 SO: Will assemble this package after the ones listed above.
2.7.7 SHPO/NPS Design Changes:
03/19 SO: Will assemble these 2 packages after the ones listed
above. 2 packages are Bldg E Vestibule & changing windows to
doors.
2.8 OWNER TOPICS:
2.8.1 Transformers/Eversource Coordination/Electric Meter location:
02/20 EK: Will check in with Joe Cassata at Eversource on
easement status.
02/27, 03/05, 03/12 Not reviewed.
03/19 EK: Same.
DP/EK
High
2.8.2 Meeting w/Postmaster:
03/19 EK: Locations reviewed on site, but remains unresolved.
SO/EK
High
2.8.3 Ceiling Paint Color:
03/19 SO: Colors sent to MC. Need to review Interior Designer’s
plan mark-up of color locations before issuing to MC. EK: Check
with me before issuing.
SO/EK
Medium
2.8.4 Meeting on Security:
03/19 EK: Electrical sub to circulate plan mark-up for confirm by
team. Electrical sub to price requested items in a Tier 1 and Tier 2
format.
MC/GP
High
2.8.5 Site Sign:
03/19 EK: On hold for now.
2.9 CONSTRUCTION TOPICS:
2.9.1 Window sills:
03/12 GP: Approx $3k to remove existing layer of mortar.
03/19 GP: Will send photos of sills to FB to review for approval.
MC/GP
Medium
2.9.2 Sewer Lateral out of Bldg M:
03/19 GP: Just sent instruction to DEF to camera the sewer line.
2.9.3 Electrical Installation:
03/19 GP: We have a existing pole support cable that is in the
way of a new manhole. PL: Eversource will relocate the pole
support.
3.0 CHANGE ORDERS
3.1 Status:
03/19 GP: Received several signed CO’s from EK yesterday.
4.0 REQUISITIONS
4.1 Status:
03/19 Not reviewed.
Conference calls will be held weekly on Thursdays at 10:00 am. Job site meetings will be held weekly on
Thursdays at 1:00 pm. Next up is a conference call at 10:00 am on March 26, 2020.
Recorded by Susan Odell, AIA, CPHC, Senior Project Architect, Paul B. Bailey Architect, LLC
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #32
03/19/2020
Page 7 of 7
These minutes are meant to convey & record the general content of the meeting, but do not represent a
verbatim recording. Please promptly respond to the Architect with any comments or questions.