HomeMy WebLinkAbout2020-02-27 Oxoboxo Mtg Min 29#16-063 Oxoboxo Lofts, Uncasville , CT MEETING MINUTES #29 PROJECT: Oxoboxo Lofts 42 Pink Row Uncasville, CT DATE: February 27, 2020 TIME: 10:00 a.m. LOCATION: Job Site/Conf Call Present: Eric Kuczarski (EK) DP EKuczarski@DakotaPartners.net Frank Brachanow (FB) Dakota Partners (DP) FBrachanow@DakotaPartners.net Gifford Perry (GP) MC Gifford@MaggioreCos.com Peter Lentine (PL) MC Peter@MaggioreCos.com Eric Marsh (EM) MC Eric@MaggioreCos.com Susan Odell (SO) Paul B. Bailey Architect (PBBA) SOdell@pbbarchitect.com Sam Kirby (SK) PBBA SKirby@pbbarchitect.com Frank Vacca (FV) BSC FVacca@BSCGroup.com Pat Callahan (PC) AZT PCallahan@aztecheng.com Dan Morrissey (DM) Morrissey Engineers (ME) daniel.morrissey@morrisseyengineers.com Tim Carr (TC) Down To Earth Consulting (DTEC) Tim@DownToEarthConsulting.com Minutes to: Paul Maggiore (PM) MC Paul@MaggioreCos.com Dave Mann (DM) Maggiore Construction (MC) Dave@MaggioreCos.com Karl Walsh DP KWalsh@DakotaPartners.net Marc Daigle DP MDaigle@DakotaPartners.net Roberto Arista (RA) DP RArista@DakotaPartners.net Evan Fink (EF) DP EFink@DakotaPartners.net Matt Abraham (MA) DP MAbraham@DakotaPartners.net Alycia Quintiliani DP aquintiliani@dakotapartners.net Bill Rundlett DP Brundlett@dakotapartners.net Kurt Prochorena (KP) BSC Group (BSC) KProchorena@BSCGroup.com Brandon Handfield (BH) Yantic River Consultants Brandon@yrc-ne.com Dean Azzam (DA) Aztech Engineers, Inc. (AZT) DAzzam@aztecheng.com James Sexton (JS) SHPO/NPS Consultant jmbjcs@hotmail.com CONSTRUCTION DATES: Dam Removal: Start Date: Oct 18, 2019 EST. End Date: Unknown Lofts Construction: Start Date: August 1, 2019 End Date: December 18, 2020 Responsible Party Priority Level 1.0 CONSTRUCTION SCHEDULE & PROGRESS 1.1 CONSTRUCTION SCHEDULE: 1.1.1 Status: 02/27 Not reviewed. 1.2 CONSTRUCTION PROGRESS: 1.2.1 Status: 02/27 Not reviewed. 2.0 CONSTRUCTION TOPICS #16-063 Oxoboxo Lofts, Uncasville, CT Meeting Minutes #29 02/27/2020 Page 2 of 7 2.1 SITE/CIVIL TOPICS (BSC – FRANK VACCA): 2.1.1 Site/Civil Submittals & RFI’s: 02/27 FV: No outstanding submittals or RFI’s. 2.1.2 Encroachment Permit for Guardrail on Route 32: 02/27 FV: Working on it now. Recommend that property line be surveyed again using the control CAD file that I sent last week. BSC/FV Medium 2.1.3 Site Lighting: 02/27 FV: Sylvia sent latest photometrics today, & CSK-03 submitted today showing updated site lighting. CLOSED. 2.1.4 Bldg M basement access: 02/20, 02/27 On hold until FMC is resolved. 2.1.5 Bridge over Raceway: 02/27 CLOSED. 2.1.6 Cad Files: 02/27 FV: CAD file sent to MC. CLOSED. 2.1.7 Site Sign: 02/20 EK: Will send image to sign sub for review. 02/27 EK: Same. (CLOSED - Topic moved to Owner) 2.1.8 Sewer Lateral out of Bldg M: 02/27 CLOSED. 2.1.9 CSK-10: 02/27 FV: Issued CSK-10 today showing new stair at east sides of Bldgs A & B. GP: Will need foundation design for the stairs. 2.1.10 CSK-6: 02/27 FV: This was supposed to be roof leaders. Do you need that or can it be handled in the field? GP: We need the sketch. FV: Roof leaders are also shown on the latest version of the grading plan which went with the FMC. Will send to MC. 2.1.11 Telephone connection from street to Bldg D Electric Room: 02/27 GP: The run from Bldg M is too long to feed the entire site, will probably need another connection from the street. Will contact Gerry for more specifics. Gerry: There is no interconnection between buildings which creates the problem. I have contacted Comcast & Frontier – waiting to hear back. Cat 6 is good for about 300 feet. 2.2 DEEP TOPICS: FMC, CONSENT ORDER, WORK AT RIVER (YANTIC RIVER CONSULTANTS – BRANDON HANDFIELD): 2.2.1 FMC Application to DEEP: 01/23 FV: Received 2nd notice of insufficiency. FMC has been handed off to BH. Will need list of construction work in the stream bed but will wait for BH to ask for it. 01/30 Not reviewed. 02/06 FV: Spoke w/BH this week. He is working on the model. 02/13 Not reviewed. 02/20 EK: Goal is to have all DEEP deficiency responses out to Brandon by Monday. 02/27 Not reviewed. BSC & MC High 2.2.2 Consent Order: 01/23 EK: Received close-out on consent order. #16-063 Oxoboxo Lofts, Uncasville, CT Meeting Minutes #29 02/27/2020 Page 3 of 7 01/30, 02/06, 02/13, 02/20, 02/27 Not reviewed. 2.2.3 Helical Pile Installation: 02/20, 02/27 Not reviewed. 2.2.4 Grout Bag Submittal: 02/20, 02/27 Not reviewed. 2.3 ENVIRONMENTAL REMEDIATION TOPICS (DOWN TO EARTH – TIM CARR): 2.3.1 RAP Application to DEEP: 02/20 TC: Meeting last week w/DEEP went well. Have some followup with them but they have internal discussions to have & get back to us. EK: There is no official approval on the RAP – just have to respond to DEEP comments. We are in good shape on the RAP application – not holding up construction. 02/27 TC: Same. 2.3.2 Injection System: (related topic below: equipment in Bldg M Basement) 02/20 TC: Still on hold until after closing. Shouldn’t be doing remediation on someone else’s property. EK: Any weather- driven dates? TC: Storing & mixing water-based solutions on the ground would require to hold off until after any threat of hard freeze. EK: May 1 start date? TC: Yes. Assume injection process will take 1 month, then monitor for 4 months. DEEP was helpful in being flexible with subsequent injections. After initial injection, the process runs through within 6 months. 80% chance of initial injection being successful. EK: Give me the exact cost of starting this before closing. 02/27 TC: Working on cost - meeting with vendor next Tuesday. Need Eversource contact to install insulating fleece on the wires because we will be within 10 feet of the wires. PL: Will send Eversource contact. DTE/TC High 2.3.3 SVE Equipment: 02/20 TC: Piping & wells are installed to Bldgs J,H & F. Finishing stub-ups to Bldg F today. Remaining: electrical supply for SVE blower & equipment installation after floor in Bldg F is installed. SK: Vents going through the living spaces of buildings? TC: No because we now have the crawl space to utilize. 02/27 TC: Adding stub-ups tomorrow. DTE/TC High 2.3.4 Remediation in Courtyard: 02/20 TC: Working on disposal of stockpile – we have approval for an alternate disposal location but waiting for final approval. EK: We would prefer to let stockpile remain until we can work in the flood plain again so there is only 1 mobilization. Approval of FMC is the key to this. PL: Parking is getting tight but we can wait for removal of stockpile. 02/27 TC: Same. DTE/TC High 2.3.5 Equipment in M Basement: 02/20 TC: Equipment could be moved & stored while it is shut down during the injection process. It is an old system – should be scrapped. The problem is if we need to use it again, it would need to be reconnected. I will try to find a temporary system that #16-063 Oxoboxo Lofts, Uncasville, CT Meeting Minutes #29 02/27/2020 Page 4 of 7 could be used. The only thing of real value is the air compressor – it is new. EK: TC to review equipment & instruct on what is to be saved. 02/27 TC: Same. 2.3.6 Contaminated soils under removed oil tank: 02/20 TC: Expect that there is boiler slag ash below the heater. Will review at Tuesday mtg. 02/27 CLOSED. (See expanded topic below) 2.3.7 Excavating and storing soils during storm drainage installation: 02/27 GP: There is enough ash in the soil that we need to dig test pits – planning to dig them tomorrow. TC: Surface is changing from industrial paved surface to residential landscaped surface. FB: Under a paved surface, you need 2 feet of cover over the ash. Under a landscaped surface, you need 4 feet of cover over the ash. 2.3 STRUCTURAL TOPICS (MORRISSEY ENGINEERS – DAN MORRISSEY): 2.3.1 Structural Submittals & RFI’s: 02/27 DM: No outstanding submittals or RFI’s. 2.3.2 Bldg F Structural Steel: 02/20 DM: On hold until we get answer on equipment. Several details are drawn – once we get answer on equipment we can turn this around quickly. PC: Will answer question on shortening the roof area. 02/27 DM: Just received info on equipment from AZT. ME/DM High 2.3.3 Gypcrete max thickness: 02/27 DM: Issued today. CLOSED. 2.3.4 Alternate design to turnbuckle: 02/27 DM: Sketches sent last week. CLOSED. 2.3.5 DEEP Deficiency Report: 02/27 DM: Revised report sent. 2.3.6 Revised Sketches for Bldg H: 02/27 DM: working on revised sketches. ME/DM High 2.4 MEP TOPICS (AZTECH ENGINEERS – PAT CALLAHAN): 2.4.1 MEP Submittals & RFI’s: 02/27 PC: Returned several submittals today. GP: Panel boards outstanding. AZT Highest 2.4.2 Generator Submittal: 02/27 PC: Site lighting is a negligible load – should be able to release the generator – just want to confirm w/DA. AZT/DA High 2.4.3 Laundry Rooms: 01/30 FB: From lessons learned at Columbus Commons: check that power is adequate, add cable outlets for wi-fi. 02/06 PC: Need updated Laundry Room layout in Bldg H. SO: Will send. 02/13 SO: Will send as soon as quantity is verified by Owner. 02/20, 02/27 PC: Still pending quantity verification. AZT/DA PBBA/SO High High 2.4.4 Smoke detectors in Corridors: #16-063 Oxoboxo Lofts, Uncasville, CT Meeting Minutes #29 02/27/2020 Page 5 of 7 02/27 PC: Added 1 smoke on Level 1, moved the one on Level 4 to the top of shaft – dwgs were sent. CLOSED. 2.4.5 Lighting fixtures at top floors of Bldgs A & B: 02/13 GP: Some fixtures will be very high – should they change to pendants? SO: Perimeter fixtures can remain as surface mounted; fixtures in center should be pendants. Will update RCP’s. 02/20, 02/27 SO: Same. 2.4.6 MEP in corridors of Bldgs A & B: 02/13 GP: Will be a very tight fit to keep MEP’s in corridors out of the zone of window interference that SHPO requested. SO: What about using the crawl space in Bldg A? 02/20 Not reviewed. 02/27 Same. 2.4.7 Wall Vents: 02/27 PC: Issued last week. CLOSED. 2.4.8 Site Lighting: 02/27 CSK-03 issued – need electrical design updates. AZT/DA High 2.4.9 Outlets on short walls: 02/27 Electrical Inspector wants outlets on short spans of walls – anything over 2 feet in length. GP to send RFI, AZT to review code. AZT/DA High 2.5 ARCHITECTURAL TOPICS: 2.5.1 Architectural Submittals & RFI’s: 02/27 SO: Access panel submittal outstanding – need to send to DM for review of how they are installed. 2.5.2 Gutters: 02/27 SO: Issuing roof plans today or tomorrow. PBBA/SO High 2.5.3 Updates to all drawings to reflect design changes: 02/27 SO: Same on RCPs. PBBA/SO Highest 2.5.4 NPS Approval of Roofing Details: 02/27 SO: Modified details will be sent to Historic Consultants tomorrow. PBBA/SK Highest 2.5.5 Existing wood flooring in Bldgs A & B: 02/27 SO: Sent to JS who is prepping package for SHPO/NPS. 2.5.6 Windows: 02/27 SO: Will be sent to Historic Consultants tomorrow. PBBA/SO Highest 2.5.7 Design Changes to SHPO/NPS: 01/16 Reviewed earlier this week w/2 Historic Consultants. Agreed that Bldg E vestibule & changing windows to doors should be submitted to SHPO/NPS. Girders in Bldg B & change of use of Bldgs F & L do not need to be submitted. 01/23, 01/30 SO: Same. 02/06 SO: Changing windows to doors in Bldgs A & B have been drafted. Will send to Historic Consultants for review. 02/13 SO: Sent Bldgs A & B to JS for review. 02/20 SO: JS approved Bldgs A & B. Need to add additional doors to east end of Bldg A. 02/27 SO: Working on add’l doors on Bldg A – will issue ASAP. PBBA/SO High 2.5.8 Window openings on west side of Bldg B, basement level: 02/06 PL: How to infill? Lintels are failing – can we support the opening with infill? SO: Will review field condition after mtg. 02/13 Not reviewed. #16-063 Oxoboxo Lofts, Uncasville, CT Meeting Minutes #29 02/27/2020 Page 6 of 7 02/20 DM: Ok to fill in openings with CMU block in lieu of replacing the lintels. PL: Openings are 30” thick. DM: 2 wythes of 8” block with brick on either side. EK: Brick should be inset no more than 1”. DM: Should put a tie from CMU to brick at middle of opening every 24” going up. PL: Durawall would be the tie. DM: Durawall is acceptable. SO: PBBA will draw this up & send to DM for review. Will issue by Thursday of next week at the latest. 02/27 SO: Same. PBBA/SK High 2.5.9 Bldg B Chase Wall: 02/20 PL: Electrical Lines out of Bldg D into Bldg B need a chase. SO: Bring across rated bedroom ceiling, then into corridor, then into north wall of elevator shaft. Will need a rated ceiling in front of this area also. 02/27 Not reviewed. 2.5.10 Bldg M Sprinkler Room: 02/20 PL: Cannot fit everything & stay 4 feet away from the window. SO: Move door to other side of room, tight to the exterior walls. 02/27 SO: PBBA to issue sketch showing this. PBBA/SK Medium 2.6 OWNER TOPICS: 2.6.1 Transformers/Eversource Coordination/Electric Meter location: 02/20 EK: Will check in with Joe Cassata at Eversource on easement status. 02/27 Not reviewed. DP/EK High 2.6.2 Meeting w/Postmaster: 02/13 Alternate locations of mailboxes reviewed. 02/20 EK: Will review at security meeting. 02/27 Not reviewed. SO/EK High 2.6.3 Ceiling Paint Color: 02/06 EK: We need mtg w/Interior Designer & EF to go through all paint colors & areas that get painted. (Ductwork, steel, etc) 02/13 SO: DP’s Interior Designer is reviewing colors. 02/20 EK: Conf call w/interior designer set up for tomorrow. 02/27 GP: We are proceeding w/priming walls & ceilings. SO: Do not paint the underside of roof decks and trusses/rafters in top levels of Bldgs A & B. EK: Will check in with Interior Designer on progress. DP/EK High 2.6.4 Meeting on Security: 02/13 FB: Scheduled for March 3, 10:30am. 02/20 Same. 02/27 Not reviewed. 2.6.5 Site Sign: 02/20 EK: Will send image to sign sub for review. 02/27 EK: Same. 2.7 CONSTRUCTION TOPICS: 2.7.1 Window sills: 01/30 Remove existing layer of mortar at all window sills? SO prefers to remove the mortar but Owner needs to approve since it is an extra. GP: Will get a price for it. 02/06 Not reviewed. 02/13 GP: Same. MC/GP High #16-063 Oxoboxo Lofts, Uncasville, CT Meeting Minutes #29 02/27/2020 Page 7 of 7 02/20, 02/27 Not reviewed. 2.7.2 Mason’s mortar samples: 02/27 SO: We will review the samples next week, in the morning when the mason is on site. 2.7.3 Sewer Lateral out of Bldg M: 02/27 PL: We are working on having the lateral camera’d. MC/PL High 3.0 CHANGE ORDERS 3.1 Status: 02/06 Change orders reviewed by EK, SO & GP. 02/13, 02/20 Not reviewed. 02/27 SO & SK reviewed 2 CE’s. Questions on Addendum 8 change order for rough framing in Bldgs B ($9.7k) & J/M ($?) & roof penetrations ($26k). GP to follow up. Questions on Bldg B extra framing CE - back-up text needs clarifying. MC/GP High 4.0 REQUISITIONS 4.1 Status: 02/06, 02/13, 02/20, 02/27 Not reviewed. Job site meetings will be held weekly on Thursdays at 10:00 am. Next up is a job site meeting at 10:00 am on March 5, 2020. Recorded by Susan Odell, AIA, CPHC, Senior Project Architect, Paul B. Bailey Architect, LLC These minutes are meant to convey & record the general content of the meeting, but do not represent a verbatim recording. Please promptly respond to the Architect with any comments or questions.