Loading...
HomeMy WebLinkAbout2020-01-30 Oxoboxo Mtg Min 25#16-063 Oxoboxo Lofts, Uncasville , CT MEETING MINUTES #25 PROJECT: Oxoboxo Lofts 42 Pink Row Uncasville, CT DATE: January 30, 2020 TIME: 1:00 p.m. LOCATION: Job Site/Conf Call Present: Frank Brachanow (FB) Dakota Partners (DP) FBrachanow@DakotaPartners.net Gifford Perry (GP) MC Gifford@MaggioreCos.com Peter Lentine (PL) MC Peter@MaggioreCos.com Susan Odell (SO) Paul B. Bailey Architect (PBBA) SOdell@pbbarchitect.com Frank Vacca (FV) BSC FVacca@BSCGroup.com Pat Callahan (PC) AZT PCallahan@aztecheng.com Dan Morrissey (DM) Morrissey Engineers (ME) daniel.morrissey@morrisseyengineers.com Minutes to: Eric Kuczarski (EK) DP EKuczarski@DakotaPartners.net Paul Maggiore (PM) MC Paul@MaggioreCos.com Dave Mann (DM) Maggiore Construction (MC) Dave@MaggioreCos.com Karl Walsh DP KWalsh@DakotaPartners.net Marc Daigle DP MDaigle@DakotaPartners.net Roberto Arista (RA) DP RArista@DakotaPartners.net Evan Fink (EF) DP EFink@DakotaPartners.net Matt Abraham (MA) DP MAbraham@DakotaPartners.net Alycia Quintiliani DP aquintiliani@dakotapartners.net Bill Rundlett DP Brundlett@dakotapartners.net Kurt Prochorena (KP) BSC Group (BSC) KProchorena@BSCGroup.com Brandon Handfield (BH) Yantic River Consultants Brandon@yrc-ne.com Dean Azzam (DA) Aztech Engineers, Inc. (AZT) DAzzam@aztecheng.com Sam Kirby (SK) PBBA SKirby@pbbarchitect.com Tim Carr (TC) Down To Earth Consulting (DTEC) Tim@DownToEarthConsulting.com James Sexton (JS) SHPO/NPS Consultant jmbjcs@hotmail.com CONSTRUCTION DATES: Dam Removal: Start Date: Oct 18, 2019 EST. End Date: Unknown Lofts Construction: Start Date: August 1, 2019 End Date: December 18, 2020 Responsible Party Priority Level 1.0 CONSTRUCTION SCHEDULE & PROGRESS 1.1 CONSTRUCTION SCHEDULE: 1.1.1 Status: 01/16 FB: An updated construction schedule will be issued mid- Feb. 01/23 Same. 01/30 Not reviewed. DP/FB High 1.2 CONSTRUCTION PROGRESS: #16-063 Oxoboxo Lofts, Uncasville, CT Meeting Minutes #25 01/30/2020 Page 2 of 10 1.2.1 Status: 01/23 PL: Working in M K J H G – framing is substantially complete, rough wiring in M & K, High walls in JHG: Sheet rock & taping underway on high walls, insulated demising & bathroom walls. Site sub working drainage between B & D & out around E. Foundation sub installing footings for stair & elevator. Will have foundation for AB connector completed this week. Mason starts next week on elevator shaft. Steel is ordered & being fabricated for Bldgs B, A. Tubes & plates on site for replacement of rotted steel lintels. 01/30 Not reviewed. 2.0 CONSTRUCTION TOPICS 2.1 SITE/CIVIL TOPICS (BSC – FRANK VACCA): 2.1.1 Site/Civil Submittals & RFI’s: 01/16 FV: Working on sitework submittals today. Need to confirm some info with the Water Company. 01/23 FV: Returned sitework submittals. GP: Site Sub will talk to Montville to straighten out the issue of the old spec. 01/30 No submittals or RFI’s outstanding. GP: New RFI for step at door on west elev of Bldg F. 2.1.2 Encroachment Permit for Guardrail on Route 32: 12/24 FV: Mayor agreed w/shifting driveway over, as long as largest fire apparatus can access the site. Drawing in process – should be CSK-05 issued in the near future. Mayor also wants BSC to reach out to transit authority to make sure there is not an issue accessing the site. 12/31 FV: Moving forward on meetings w/transit authority. 01/07 FV: Received size of largest apparatus from FM today – readjusting the entrance so it will receive this equipment. 01/16, 01/23, 01/30 FV: Same. BSC/FV Medium 2.1.3 Site Lighting: 01/16 FV: Historic consultant indicated that the site lighting needs to change. Have communicated this to Sylvia – requested most affordable fixtures that we believe will meet the historic requirements. When received, will send to EK for review/approval, then run photometrics. 01/23 FV: Waiting for decision from Historic Consultant, then will tell Sylvia to run the photometrics. SO: Will need a cut sheet on the poles & bases. Bollards are fine as is. FV: Don’t have a direct answer on # of fixtures until photometrics are run. 01/30 FV: Corresponding w/Sylvia today – she is looking for a site pole base that is not fluted. BSC/FV High 2.1.4 Bldg M basement access: 12/17 Discussion of FMC approval of Basement of Bldg M – our request to leave the basement open has not been approved – so BSC will wait to detail new entrances into Bldg M Basement. 12/24, 12/31, 01/07, 01/16, 01/23, 01/30 On hold until FMC is resolved. 2.1.5 Bridge over Raceway: 01/07 FV: Forwarding contact info to GP for pre-fabricated bridge – we think steel truss pre-fab bridge will be least expensive. #16-063 Oxoboxo Lofts, Uncasville, CT Meeting Minutes #25 01/30/2020 Page 3 of 10 01/16 GP: Have initial design, cost ($18k) & photos on a bridge. FV: Would recommend that EK’s VE option be sent to DM for review. Longevity could be a concern. FB: FV, send it to DM for this review. 01/23, 01/30 FV: Researching options. BSC/FV Medium 2.1.6 Site Walls: 01/07 FV: Will remove site walls that DM indicated are unsafe, and will show sloped grade in those locations. Site walk to review walls followed this meeting. FV to document. 01/16 FV: Will modify plans for walls to be removed to show removal, re-grading & guardrail. When is this needed? GP: Need in 2 weeks, before encroachment design. 01/23 FV: About 75% done with plan. Running into some issues with grading – might need to move the transformer & generator near Bldg H by a few feet to the west. GP/SO: Ok to move them westward. FV: Will include this in CSK-07 along with the site walls. GP: Will mark the Eversource plan with the location of the switch gear vault & send to FV. 01/30 FV: Same. BSC/FV High 2.1.7 Cad Files: 01/16 GP: Site contractor has a Top-Con system. He needs all cad files updated with any recent changes, and 3 control points. If BSC can’t provide that, we will hire Civil Engineer. FV: We didn’t prepare the original survey. It came to us as relative line work with no control points, and it is not related to State Plane. The surveyor of record (Aeschliman) should be able to locate the survey on State Plane & give you the control points. FB: Send this in an email; I will forward to Aeschliman. 01/23 FV: Received original survey from Tim Carr. GP: FB & I talked to Aeschliman on Tuesday. He will try to send the info to us this week. 01/30 FV: Sent cad files yesterday. GP: Sent to Aeschliman – he has to review to confirm they are adequate. 2.1.8 Area between Bldgs F & G: 01/16 GP: What do we have for finish grade & surface treatment. FV: Cheapest option for surface treatment would be stone. If you want people to walk through it, it should be bituminous. SO: This area is the direct path for occupants of lower level of Bldg C to access the lower level of the site, so it should be walkable. FV: Will add bituminous path, swale, and drainage towards catch basin at the chimney side. PL: There is a significant grade difference – infill? FV: We can show a couple of stair risers to minimize infill. 01/23 FV: Same. PL: Would give the site sub work if we had the drainage. GP: Please complete it this month. 01/30 FV: Design in process. Trying to send today or tomorrow. PC: Sanitary line? FV: Sanitary line is now below grade. BSC/FV High 2.1.9 Site Sign: 01/16 SO: Per discussion w/Historic Consultant & Owner, site sign needs redesign. 2 black metal poles with text between was discussed. FV: We have done that before – will send an image. 01/23 FV: Will send image today. 01/30 FV: Just received photos – will send to SO. BSC/FV Medium #16-063 Oxoboxo Lofts, Uncasville, CT Meeting Minutes #25 01/30/2020 Page 4 of 10 2.1.10 Utility connectors from C to D, etc: 01/30 FV: Will show actual locations on a sketch if needed, but we typically only show them at a schematic level. 2.1.11 Wall Packs: 01/30 SO: Place them at 8’-0” above surface below. They should be in a color that blends with the building. Will send color for brick at Bldgs C & M. 2.1.12 Sewer Lateral out of Bldg M: 01/30 FV: Setting up camera of existing line for next week. If it is sound, we can reuse it. FB: Haven’t we already done the camera? FV: They camera’d the line from the manhole to the street but they did not camera our line. 2.2 DEEP TOPICS: FMC, CONSENT ORDER, WORK AT RIVER (BSC & YANTIC RIVER CONSULTANTS – BRANDON HANDFIELD): 2.2.1 FMC Application to DEEP: 01/16 FV: Need to add work in the floodway to the FMC application. GP: Can we work under Bldg K? Building staging? FV: If your staging goes into the floodway, then we need to submit it to DEEP. Need to have the meeting at DEEP to review status, including any work that the contractor needs to do in the floodway/stream bed. FB: We should meet to identify everything the contractor needs to do, so FV has the list prepared for the DEEP meeting. FV: We can meet next week. FB: BH’s involvement? FV: BH is on board to provide any temporary hydraulic diversions. 01/23 FV: Received 2nd notice of insufficiency. FMC has been handed off to BH. Will need list of construction work in the stream bed but will wait for BH to ask for it. 01/30 Not reviewed. BSC & MC High 2.2.2 Consent Order: 01/16 DEEP was on site Friday. Still waiting on meeting date. 01/23 EK: Received close-out on consent order. 01/30 Not reviewed. 2.2.3 Helical Pile Installation: 11/26 FV: How much work remains? GP: 2 days for helical piles, 1 or 2 weeks for grout bags. Helical pile contractor has asked when they can come back. Do we know? FV: We do not know. 12/03, 12/10, 12/17, 12/24, 12/31, 01/07, 01/16, 01/23, 01/30 Not reviewed. 2.2.4 Grout Bag Submittal: 12/03 SO: Reviewed BH’s comments w/GP & Susan Weglein. GP: We will resubmit the submittal. 12/10, 12/17, 12/24, 12/31, 01/07, 01/16, 01/23, 01/30 Not reviewed. MC/GP Medium 2.3 ENVIRONMENTAL REMEDIATION TOPICS (DOWN TO EARTH – TIM CARR): 2.3.1 Environmental Submittals & RFI’s: 01/23, 01/30 Not reviewed. 2.3.2 RAP Application to DEEP: #16-063 Oxoboxo Lofts, Uncasville, CT Meeting Minutes #25 01/30/2020 Page 5 of 10 01/16 TC: Waiting on meeting w/DEEP. Sending status report to DEEP by Jan. 31. 01/23 Same. 01/30 Not reviewed. DTE/TC High 2.3.3 Injection System: (related topic below: equipment in Bldg M Basement) 01/16 TC: My schedule proposes spring 2020 for this work. GP: Is there an as-built to locate the water lines from the vault to the building? TC: Will send what I have from AEI. 01/23 GP: Received documentation from TC & sent to the site sub. 01/30 Not reviewed. 2.3.4 Abandoned Brownfield Cleanup (ABC Program) Application to DEEP: 01/16 TC: Still working to get this approval. 01/23 TC: Should I reach out to DEEP or not? EK: Meeting w/DEEP yesterday focusing on the model itself. You should check in w/DEEP. 01/30 Not reviewed. 2.3.5 SVE Equipment: 01/16 TC: Should be no more than 2 days to get vacuum pipes through Bldg G & into Bldg F with a manifold. PL: This needs to be completed soon. 01/23 TC: Will try to schedule this for next week – need fittings & people & good weather to complete this. 01/30 Not reviewed. DTE/TC High 2.3.6 Remediation in Courtyard: 01/16 TC: Some soil left in the courtyard to remove but it is in the floodway. We have approval to dispose of stockpile, but the proposed facility had a fire & will take a few months to come back on line. We will find an alternate disposal location. 01/23 TC: Should know about new facility next week. 01/30 Not reviewed. DTE/TC Medium 2.3.7 Equipment in M Basement: 01/16 TC: It is the obligation of Pit Stop Holding (current owner) to keep it running – we will need it this winter. 01/23 See below for discussion on electric bill. 01/30 Not reviewed. 2.3.8 Contaminated soils under removed oil tank: 01/16 TC: A little bit more soil that we would like to remove – 2 feet of shallow soils around the stack foundation – seems to be impacted with same contaminates – on east side of stack near existing SVE well & where trailer was parked. Would be best to coordinate this removal & backfill with disposal of the stockpile. Prior LEP (AEI) did remediation previously – we don’t have any reports stating that remaining soil has to be removed. PL: We have a heater on the location now. TC: We can remove & replace in 1 day in the spring after the heater is removed. FB: We need this work on your schedule so we can track it & coordinate w/PL. 01/23 Same. 01/30 Not reviewed. DTE/TC High #16-063 Oxoboxo Lofts, Uncasville, CT Meeting Minutes #25 01/30/2020 Page 6 of 10 2.3.9 Haz-Mat Removal Reports: 01/16 GP: Still waiting for the reports. 01/23 GP: Received some waste manifests, but don’t think they are all of them. 01/30 Not reviewed. MC/GP Medium 2.3.10 Schedule/Status Report: 01/16 TC: Sending schedule today. Will issue update report to DEEP by Jan 31 to report on all work completed to date – soil sampling, tank removal, SVE system, air testing. 01/23 TC: Schedule sent to FB & EK. Working on deliverable for DEEP. 01/30 Not reviewed. DTE/TC High 2.3 STRUCTURAL TOPICS (MORRISSEY ENGINEERS – DAN MORRISSEY): 2.3.1 Structural Submittals & RFI’s: 01/07 RFI’s 32, 35 & 39 answered w/SKS’s 40-57. No RFI’s outstanding. Submittal for stair framing is due Jan. 16. 01/16 Not reviewed. 01/23 DM: RFI 44 was answered as if the soffit was below the ceiling. If it is above the ceiling, it doesn’t matter. 01/30 No RFI’s outstanding. 1 submittal on steel shop dwgs outstanding. ME/DM High 2.3.2 Header for clearance required in crawl space in Bldgs G, H, J: 01/07 DM: Will run #’s & provide size of header for BO’s requested clearance in crawl space. 01/16 GP: Still outstanding. 01/23 DM: Will send a memo answering this. 01/30 DM: Same. ME/DM High 2.3.3 B/D & D/E Connector: 01/07 DM to review architectural sketches & review condition of existing framing on site today, & provide framing dwgs as needed. 01/16 SO to review framing options w/DM. DM to provide sketch of preferred option. 01/23 DM: Framing plan underway for B/D connector. Framing plan for D/E connector not needed – reusing existing framing. 01/30 DM: Working on it. ME/DM High 2.3.4 New topics per today’s site walk: 01/07 New issues: masonry in Bldg H & new issues in Bldg B. 01/16 Not reviewed. 01/23 DM: Preparing a sketch for the masonry in Bldg H – where the separate layers of brick have delaminated. 01/30 DM: Working on that sketch – will issue by end of week. ME/DM High 2.3.5 Bldg B Elevator Shaft: Support of existing beam above Level 3 Elevator door opening: 01/23 DM: Will review. 01/30 DM: Detail will be issued shortly – will show angle bracket bolted to face of masonry. ME/DM High 2.3.6 Hanger Supports for MEP lines in corridors: 01/30 DM: I have designed the supports but do not locate the MEP lines. If everyone is ok with what I described in the emails, I #16-063 Oxoboxo Lofts, Uncasville, CT Meeting Minutes #25 01/30/2020 Page 7 of 10 will draw it up. Will draw all 3 versions & send them this afternoon. ME/DM High 2.3.7 Bldg F Structural Steel: 01/30 GP: Architectural Section shows steel columns from new lower floor to upper existing steel beams, so steel shops show these columns. Just cross them off of the shop dwgs. ME/DM High 2.4 MEP TOPICS (AZTECH ENGINEERS – PAT CALLAHAN): 2.4.1 MEP Submittals & RFI’s: 01/30 RFI 46 outstanding & overdue. 2 submittals overdue, 5 more submittals outstanding but not overdue. AZT Highest 2.4.2 Generator Submittal: 01/07 DA to confirm if site lighting needs to be on the generator. 01/16 GP resubmitted this submittal to finalize the design. PC: DA indicated that site lighting is currently on the generator due to CHFA requirements. 01/23, 01/30 PC: On hold for site lighting. AZT/DA High 2.4.3 Circuits for Heat Pumps & Condensate Pumps: 01/30 PC: Answer on the returned submittal. CLOSED. 2.4.4 Design Changes Outstanding: 01/16 SO: I reviewed the updated MEP drawings. Bldg E 1st Flr, Units C-3 & D-2 remain to be updated. PC: Yes, we will work on that next. 01/23 PC: In progress. 01/30 PC: Need Revit file. SO: Will send. Also, Bldg C – ventilation at waterproofing detail, Laundry Rms – check that power is adequate, add cable outlets for wi-fi. AZT/PC High 2.4.5 Cad files for MSK, PSK & MSK dwgs: 01/30 GP: Need these files for coordination. PC: Will send. AZT/PC High 2.5 ARCHITECTURAL TOPICS: 2.5.1 Architectural Submittals & RFI’s: 01/30 GP: Anything on kitchens is priority. RFI’s 45, 46 & 47 remain outstanding. PBBA Highest 2.5.2 Below grade waterproofing at A, B, C, D, F: 01/30 Bldg C revisions issued. CLOSED. 2.5.3 Mason’s mortar samples: 12/31 SO: Reviewed what needs to be submitted to SHPO w/JS yesterday - new item includes smokestack. Reviewed all mortar samples w/Mason today. Mason will continue to prep samples & will send some out for specialized color matching. SO will prep list of mortar samples to be submitted to SHPO so we can track progress. 01/07 PL: Mason is expecting mortar samples back by Friday. 01/16 SO: Will review w/Mason next Thursday on site. GP: Will tell the Mason to have samples ready. 01/23 GP: Mason still waiting for samples to come back. Estimated time 1.5 weeks. SO: Need to source 8x8 or 8x6 blocks for smokestack. Need to prep list of mortar & brick color samples. 01/30 GP: Samples will be ready early next week. PBBA/SO High #16-063 Oxoboxo Lofts, Uncasville, CT Meeting Minutes #25 01/30/2020 Page 8 of 10 2.5.4 Gutters: 01/23 SO: Previous location of gutters reviewed – we are putting new gutters at every location where gutters previously were. Will issue updated drawings to show sketched design more clearly. 01/30 SO: Same PBBA High 2.5.5 Updates to all drawings to reflect design changes: 01/07 RCP’s next. Drawing list sheets to be updated weekly. 01/16 SO: Updated drawing set is underway. Will post it on Egnyte site next Monday. 01/23 SO: Will issue next week. 01/30 SO: Same PBBA High 2.5.6 Meeting w/Postmaster: 01/07 FB: Should have this meeting soon – phone company was asking if units will have addresses. 01/16 EK: Spoke w/Postmaster – 2 delivery locations is ok. Postmaster is ok with Unit #’s as shown on Arch floor plans. 01/23 SO & EK need to review the 3rd delivery point. Owner is ok with unit #’s as shown on arch floor plans. 01/30 SO: Same. SO/EK High 2.5.7 Smoke detectors in Corridors: 12/31 SO to send inquiry (RFI-38)& answer to BO & FM. 01/16, 01/23, 01/30 SO: Same. PBBA High 2.5.8 Ceiling Paint Color: 01/07 EK: Review ceiling colors w/EF – currently all ceilings are white. 01/16 Not reviewed. 01/23 EK: Same. 01/30 Same. DP/EK & EF Medium 2.5.9 Meeting on Security: 01/07 Electrician requested that coordination meeting be scheduled sooner than was done at CC. GP: Security submittal was issued yesterday. 01/16 Not reviewed. 01/23 Tentative meeting on Feb. 6, 1:30pm 01/30 Same. DP needs to arrange for Management Company rep to be at this meeting. DP High 2.5.10 Flood Vent Color: 01/16 Same. Reviewed earlier this week w/2 Historic Consultants – agreed to not submit the color to SHPO/NPS. 01/23 SO: Need to supply color to MC. 01/30 Same. PBBA High 2.5.11 MC’s Priority: 01/30 SO: Will prioritize the RCP’s of the lower buildings for fixture placement. GP: Floor finishes are a priority. PBBA Highest 2.5.12 Bldg A Units A-4 & A-6: 01/23 PL: Toilets in these units sit on top of beams. PBBA needs to redesign bathroom layouts. 01/30 Same PBBA Highest 2.5.13 Window sills: #16-063 Oxoboxo Lofts, Uncasville, CT Meeting Minutes #25 01/30/2020 Page 9 of 10 01/30 Remove existing layer of mortar at all window sills? SO prefers to remove the mortar but Owner needs to approve since it is an extra. GP: Will get a price for it. 2.5.14 Bldg B Roof detail: 01/30 PBBA to update this detail. 2.6 SHPO APPROVALS 2.6.1 NPS Approval of Roofing Details: 01/16 Reviewed earlier this week w/2 Historic Consultants. Continuous taper from edge of roof to ridge discussed as the only viable option. 01/23 SO: PBBA to update proposed details with continuous taper. 01/30 FB: What is holding this up? SO: We need to revise our details but this was put on the priority list after windows & floors. GP: Will talk to roofer about continuous taper of insulation. PBBA MC/GP High High 2.6.2 Typical details to represent SHPO conditions: 01/16 Reviewed earlier this week w/2 Historic Consultants. Agreed to follow Owner’s request to not submit these ASK’s to SHPO/NPS, but to make sure that construction is following them. GP: Pics of full-size mock-ups of 3 conditions of MEP runs in corridors provided to SO. SO: Will review. 01/23 SO: Reviewing MEP mock-ups today. 01/30 MEP mockups reviewed. Various options discussed & rejected. Mockups approved as shown. CLOSED. 2.6.3 Existing wood flooring in Bldgs A & B: 01/16 Reviewed earlier this week w/2 Historic Consultants. On recommendation of newly engaged Historic Consultant, swapping all LVT in the project to another vinyl product. EK: Sent this to EF, who is working on alternate products. PBBA to update documentation with this info. 01/23 SO: Direction from DP is to use engineered wood everywhere we are showing LVT. Will update floor finish pattern drawings right after window drawings. 01/30 SO: Will prioritize updating the floor finish pattern drawings so GP can move ahead with them. PBBA High 2.6.4 Windows: 01/16 Met w/S&L & 2 Historic Consultants this week. Agreed to stay w/metal windows. PBBA to change munton patterns in several buildings per JS’s research, & create elevation drawings of the existing window types. DP & MC working to find a window manufacturer w/shorter lead time. As soon as window manufacturer is decided, PBBA to issue sketches of existing & proposed windows for submission to SHPO/NPS. 01/23 EK: Will have answer on window manufacturer by end of day tomorrow. SO: Will do window drawings on Saturday. 01/30 Decision on windows was postponed for accurate pricing. SO: Quaker window details reviewed. They should not give us any more issues than the Graham window details do. DP/MC PBBA Highest Highest 2.6.5 Signage: #16-063 Oxoboxo Lofts, Uncasville, CT Meeting Minutes #25 01/30/2020 Page 10 of 10 01/16 Reviewed earlier this week w/2 Historic Consultants. Stenciling on the exterior of the buildings suggested. This item is the lowest priority to submit to SHPO/NPS, since it is not needed until close to the end of construction. 01/23, 01/30 SO: Same. 2.6.6 Design Changes: 01/16 Reviewed earlier this week w/2 Historic Consultants. Agreed that Bldg E vestibule & changing windows to doors should be submitted to SHPO/NPS. Girders in Bldg B & change of use of Bldgs F & L do not need to be submitted. 01/23, 01/30 SO: Same. 2.7 CONSTRUCTION TOPICS: 2.7.1 Transformers/Eversource Coordination/Electric Meter location: 01/23 GP: Met w/Eversource today. Eversource delivered their design at mtg, which locates transformers & switch gear. Eversource needs town-approved A-2 survey to start easement process. He has Attorney & Survey contact info. Transformer location at Bldg D: Put it right in front of the electric room. 01/30 GP: Sent marked up dwg showing correct locations of transformer and dog house & specs for the vault to EK & FV. FB to follow up on getting town-approved A-2 survey to Eversource. DP/FB High 2.7.2 Telephone/Cable lines: 01/30 GP: Both companies have delivered their cables. CLOSED. 2.7.3 Electrical Utility Cost: 01/23 GP: Owner – Ryan Gussette – was here last week – the electrical service is still in their name, so they are getting bills. Should we move the service to our name? PL: Power company charges $2500/month delivery charge whether power is used or not. Our temporary service is being powered through this service. Kent Rice is the manager of this property for the Owner. EK: Will contact Kent Rice. 01/30 FB will follow up w/EK. DP/FB High 3.0 CHANGE ORDERS 3.1 Status: 01/30 Change orders signed by SO & GP. 4.0 REQUISITIONS 4.1 Status: 01/07, 01/16, 01/23, 01/30 Not reviewed. Job site meetings will be held weekly on Thursdays at 10:00 am. Next up is a job site meeting at 10:00 am on February 6, 2020. Recorded by Susan Odell, AIA, CPHC, Senior Project Architect, Paul B. Bailey Architect, LLC These minutes are meant to convey & record the general content of the meeting, but do not represent a verbatim recording. Please promptly respond to the Architect with any comments or questions.