HomeMy WebLinkAbout2020-01-23 Oxoboxo Mtg Min 24#16-063
Oxoboxo Lofts, Uncasville , CT
MEETING MINUTES #24
PROJECT: Oxoboxo Lofts
42 Pink Row
Uncasville, CT
DATE: January 23, 2020
TIME: 10:00 a.m.
LOCATION: Job Site/Conf Call
Present:
Eric Kuczarski (EK) DP EKuczarski@DakotaPartners.net
Frank Brachanow (FB) Dakota Partners (DP) FBrachanow@DakotaPartners.net
Gifford Perry (GP) MC Gifford@MaggioreCos.com
Peter Lentine (PL) MC Peter@MaggioreCos.com
Susan Odell (SO) Paul B. Bailey Architect (PBBA) SOdell@pbbarchitect.com
Frank Vacca (FV) BSC FVacca@BSCGroup.com
Pat Callahan (PC) AZT PCallahan@aztecheng.com
Dan Morrissey (DM) Morrissey Engineers (ME) daniel.morrissey@morrisseyengineers.com
Tim Carr (TC) Down To Earth Consulting (DTEC) Tim@DownToEarthConsulting.com
Minutes to:
Paul Maggiore (PM) MC Paul@MaggioreCos.com
Dave Mann (DM) Maggiore Construction (MC) Dave@MaggioreCos.com
Karl Walsh DP KWalsh@DakotaPartners.net
Marc Daigle DP MDaigle@DakotaPartners.net
Roberto Arista (RA) DP RArista@DakotaPartners.net
Evan Fink (EF) DP EFink@DakotaPartners.net
Matt Abraham (MA) DP MAbraham@DakotaPartners.net
Alycia Quintiliani DP aquintiliani@dakotapartners.net
Bill Rundlett DP Brundlett@dakotapartners.net
Kurt Prochorena (KP) BSC Group (BSC) KProchorena@BSCGroup.com
Brandon Handfield (BH) Yantic River Consultants Brandon@yrc-ne.com
Dean Azzam (DA) Aztech Engineers, Inc. (AZT) DAzzam@aztecheng.com
Sam Kirby (SK) PBBA SKirby@pbbarchitect.com
James Sexton (JS) SHPO/NPS Consultant jmbjcs@hotmail.com
CONSTRUCTION DATES: Dam Removal: Start Date: Oct 18, 2019 EST. End Date: Unknown
Lofts Construction: Start Date: August 1, 2019 End Date: December 18, 2020
Responsible
Party
Priority
Level
1.0 CONSTRUCTION SCHEDULE & PROGRESS
1.1 CONSTRUCTION SCHEDULE:
1.1.1 Status:
01/16 FB: An updated construction schedule will be issued mid-
Feb.
01/23 Same.
DP/FB
High
1.2 CONSTRUCTION PROGRESS:
1.2.1 Status:
01/23 PL: Working in M K J H G – framing is substantially complete,
rough wiring in M & K, High walls in JHG: Sheet rock & taping
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #24
01/23/2020
Page 2 of 10
underway on high walls, insulated demising & bathroom walls.
Site sub working drainage between B & D & out around E.
Foundation sub installing footings for stair & elevator. Will have
foundation for AB connector completed this week. Mason starts
next week on elevator shaft. Steel is ordered & being fabricated
for Bldgs B, A. Tubes & plates on site for replacement of rotted
steel lintels.
2.0 CONSTRUCTION TOPICS
2.1 SITE/CIVIL TOPICS (BSC – FRANK VACCA):
2.1.1 Site/Civil Submittals & RFI’s:
01/16 FV: Working on sitework submittals today. Need to confirm
some info with the Water Company.
01/23 FV: Returned sitework submittals. GP: Site Sub will talk to
Montville to straighten out the issue of the old spec.
2.1.2 Encroachment Permit for Guardrail on Route 32:
12/24 FV: Mayor agreed w/shifting driveway over, as long as
largest fire apparatus can access the site. Drawing in process –
should be CSK-05 issued in the near future. Mayor also wants BSC
to reach out to transit authority to make sure there is not an issue
accessing the site.
12/31 FV: Moving forward on meetings w/transit authority.
01/07 FV: Received size of largest apparatus from FM today –
readjusting the entrance so it will receive this equipment.
01/16, 01/23 FV: Same.
BSC/FV
Medium
2.1.3 Site Lighting:
01/16 FV: Historic consultant indicated that the site lighting needs
to change. Have communicated this to Sylvia – requested most
affordable fixtures that we believe will meet the historic
requirements. When received, will send to EK for review/approval,
then run photometrics.
01/23 FV: Waiting for decision from Historic Consultant, then will
tell Sylvia to run the photometrics. SO: Will need a cut sheet on
the poles & bases. Bollards are fine as is. FV: Don’t have a direct
answer on # of fixtures until photometrics are run.
BSC/FV
High
2.1.4 Bldg M basement access:
12/17 Discussion of FMC approval of Basement of Bldg M – our
request to leave the basement open has not been approved – so
BSC will wait to detail new entrances into Bldg M Basement.
12/24, 12/31, 01/07, 01/16, 01/23 On hold until FMC is resolved.
2.1.5 Bridge over Raceway:
01/07 FV: Forwarding contact info to GP for pre-fabricated bridge
– we think steel truss pre-fab bridge will be least expensive.
01/16 GP: Have initial design, cost ($18k) & photos on a bridge.
FV: Would recommend that EK’s VE option be sent to DM for
review. Longevity could be a concern. FB: FV, send it to DM for
this review.
01/23 FV: Researching options.
BSC/FV
Medium
2.1.6 Site Walls:
01/07 FV: Will remove site walls that DM indicated are unsafe,
and will show sloped grade in those locations. Site walk to review
walls followed this meeting. FV to document.
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #24
01/23/2020
Page 3 of 10
01/16 FV: Will modify plans for walls to be removed to show
removal, re-grading & guardrail. When is this needed? GP: Need
in 2 weeks, before encroachment design.
01/23 FV: About 75% done with plan. Running into some issues
with grading – might need to move the transformer & generator
near Bldg H by a few feet to the west. GP/SO: Ok to move them
westward. FV: Will include this in CSK-07 along with the site walls.
GP: Will mark the Eversource plan with the location of the switch
gear vault & send to FV.
BSC/FV
High
2.1.7 Cad Files:
01/16 GP: Site contractor has a Top-Con system. He needs all cad
files updated with any recent changes, and 3 control points. If BSC
can’t provide that, we will hire Civil Engineer. FV: We didn’t
prepare the original survey. It came to us as relative line work with
no control points, and it is not related to State Plane. The surveyor
of record (Aeschliman) should be able to locate the survey on
State Plane & give you the control points. FB: Send this in an
email; I will forward to Aeschliman.
01/23 FV: Received original survey from Tim Carr. GP: FB & I
talked to Aeschliman on Tuesday. He will try to send the info to
us this week.
BSC/FV
High
2.1.8 Area between Bldgs F & G:
01/16 GP: What do we have for finish grade & surface treatment.
FV: Cheapest option for surface treatment would be stone. If you
want people to walk through it, it should be bituminous. SO: This
area is the direct path for occupants of lower level of Bldg C to
access the lower level of the site, so it should be walkable. FV: Will
add bituminous path, swale, and drainage towards catch basin at
the chimney side. PL: There is a significant grade difference –
infill? FV: We can show a couple of stair risers to minimize infill.
01/23 FV: Same. PL: Would give the site sub work if we had the
drainage. GP: Please complete it this month.
BSC/FV
High
2.1.9 Site Sign:
01/16 SO: Per discussion w/Historic Consultant & Owner, site sign
needs redesign. 2 black metal poles with text between was
discussed. FV: We have done that before – will send an image.
01/23 FV: Will send image today.
BSC/FV
Medium
2.1.10 Site walkway to Elec Rm in Bldg D:
01/16 GP: The walkway in this area was not extended to the new
electric room door. SO: Will ask FV to revise sketch to show this.
01/23 FV: We did this. See CSK-01. CLOSED.
BSC/FV
Medium
2.2 DEEP TOPICS: FMC, CONSENT ORDER, WORK AT
RIVER (BSC & YANTIC RIVER CONSULTANTS –
BRANDON HANDFIELD):
2.2.1 FMC Application to DEEP:
01/16 FV: Need to add work in the floodway to the FMC
application. GP: Can we work under Bldg K? Building staging? FV:
If your staging goes into the floodway, then we need to submit it
to DEEP. Need to have the meeting at DEEP to review status,
including any work that the contractor needs to do in the
floodway/stream bed. FB: We should meet to identify everything
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #24
01/23/2020
Page 4 of 10
the contractor needs to do, so FV has the list prepared for the
DEEP meeting. FV: We can meet next week. FB: BH’s
involvement? FV: BH is on board to provide any temporary
hydraulic diversions.
01/23 FV: Received 2nd notice of insufficiency. FMC has been
handed off to BH. Will need list of construction work in the
stream bed but will wait for BH to ask for it.
BSC & MC
High
2.2.2 Consent Order:
01/16 DEEP was on site Friday. Still waiting on meeting date.
01/23 EK: Received close-out on consent order.
2.2.3 Helical Pile Installation:
11/26 FV: How much work remains? GP: 2 days for helical piles, 1
or 2 weeks for grout bags. Helical pile contractor has asked when
they can come back. Do we know? FV: We do not know.
12/03, 12/10, 12/17, 12/24, 12/31, 01/07, 01/16, 01/23 Not
reviewed.
2.2.4 Grout Bag Submittal:
12/03 SO: Reviewed BH’s comments w/GP & Susan Weglein. GP:
We will resubmit the submittal.
12/10, 12/17, 12/24, 12/31, 01/07, 01/16, 01/23 Not reviewed.
MC/GP
Medium
2.3 ENVIRONMENTAL REMEDIATION TOPICS
(DOWN TO EARTH – TIM CARR):
2.3.1 Environmental Submittals & RFI’s:
01/23 Not reviewed.
2.3.2 RAP Application to DEEP:
01/16 TC: Waiting on meeting w/DEEP. Sending status report to
DEEP by Jan. 31.
01/23 Same.
DTE/TC
High
2.3.3 Injection System: (related topic below: equipment in Bldg M
Basement)
01/16 TC: My schedule proposes spring 2020 for this work. GP: Is
there an as-built to locate the water lines from the vault to the
building? TC: Will send what I have from AEI.
01/23 GP: Received documentation from TC & sent to the site
sub.
2.3.4 Abandoned Brownfield Cleanup (ABC Program) Application to
DEEP:
01/16 TC: Still working to get this approval.
01/23 TC: Should I reach out to DEEP or not? EK: Meeting w/DEEP
yesterday focusing on the model itself. You should check in
w/DEEP.
2.3.5 SVE Equipment:
01/16 TC: Should be no more than 2 days to get vacuum pipes
through Bldg G & into Bldg F with a manifold. PL: This needs to
be completed soon.
01/23 TC: Will try to schedule this for next week – need fittings
& people & good weather to complete this.
DTE/TC
High
2.3.6 Remediation in Courtyard:
01/16 TC: Some soil left in the courtyard to remove but it is in the
floodway. We have approval to dispose of stockpile, but the
DTE/TC
Medium
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #24
01/23/2020
Page 5 of 10
proposed facility had a fire & will take a few months to come back
on line. We will find an alternate disposal location.
01/23 TC: Should know about new facility next week.
2.3.7 Equipment in M Basement:
01/16 TC: It is the obligation of Pit Stop Holding (current owner)
to keep it running – we will need it this winter.
01/23 See below for discussion on electric bill.
2.3.8 Contaminated soils under removed oil tank:
01/16 TC: A little bit more soil that we would like to remove – 2
feet of shallow soils around the stack foundation – seems to be
impacted with same contaminates – on east side of stack near
existing SVE well & where trailer was parked. Would be best to
coordinate this removal & backfill with disposal of the stockpile.
Prior LEP (AEI) did remediation previously – we don’t have any
reports stating that remaining soil has to be removed. PL: We
have a heater on the location now. TC: We can remove & replace
in 1 day in the spring after the heater is removed. FB: We need
this work on your schedule so we can track it & coordinate w/PL.
01/23 Same.
DTE/TC
High
2.3.9 Haz-Mat Removal Reports:
01/16 GP: Still waiting for the reports.
01/23 GP: Received some waste manifasts, but don’t think they
are all of them.
MC/GP
Medium
2.3.10 Schedule/Status Report:
01/16 TC: Sending schedule today. Will issue update report to
DEEP by Jan 31 to report on all work completed to date – soil
sampling, tank removal, SVE system, air testing.
01/23 TC: Schedule sent to FB & EK. Working on deliverable for
DEEP.
DTE/TC
High
2.3 STRUCTURAL TOPICS
(MORRISSEY ENGINEERS – DAN MORRISSEY):
2.3.1 Structural Submittals & RFI’s:
01/07 RFI’s 32, 35 & 39 answered w/SKS’s 40-57. No RFI’s
outstanding. Submittal for stair framing is due Jan. 16.
01/16 Not reviewed.
01/23 DM: RFI 44 was answered as if the soffit was below the
ceiling. If it is above the ceiling, it doesn’t matter.
ME/DM
High
2.3.2 Special Inspections:
12/31 Materials Testing issued 1st report, which needs to be
reviewed by DM before going to BO. (See also topic below under
Construction Topics)
01/07 DM: General review – nothing jumped out. Will review
item by item & issue a report.
01/16 Not reviewed.
01/23 DM: Returned. CLOSED.
ME/DM
High
2.3.3 Header for clearance required in crawl space in Bldgs G, H, J:
01/07 DM: Will run #’s & provide size of header for BO’s
requested clearance in crawl space.
01/16 GP: Still outstanding.
01/23 DM: Will send a memo answering this.
ME/DM
High
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #24
01/23/2020
Page 6 of 10
2.3.4 B/D & D/E Connector:
01/07 DM to review architectural sketches & review condition of
existing framing on site today, & provide framing dwgs as
needed.
01/16 SO to review framing options w/DM. DM to provide sketch
of preferred option.
01/23 DM: Framing plan underway for B/D connector. Framing
plan for D/E connector not needed – reusing existing framing.
ME/DM
High
2.3.5 New topics per today’s site walk:
01/07 New issues: masonry in Bldg H & new issues in Bldg B.
01/16 Not reviewed.
01/23 DM: Preparing a sketch for the masonry in Bldg H – where
the separate layers of brick have delaminated.
ME/DM
High
2.3.6 Footing size for columns in Bldg F:
01/16 GP: Need this information.
01/23 DM: Columns in Bldg F sit on the existing steel, so no
footings are needed. CLOSED.
ME/DM
High
2.3.7 Bldg B Elevator Shaft: Support of existing beam above Level 3
Elevator door opening:
01/23 DM: Will review.
2.4 MEP TOPICS
(AZTECH ENGINEERS – PAT CALLAHAN):
2.4.1 MEP Submittals & RFI’s:
01/16 PC: Wrapping up chemical treatment which is due this
week. DA sent Revised Switch Gear & Bldg D Elec Rm Layout – he
thinks he answered both overdue submittals by returning this
one. GP: Ok, but please send back the other one for record.
01/23 PC: Chem Treatment is almost ready – just need to cross
reference with submittals on cooling tower, separator tower
filtration & plate & frame heat exchanger – will return all of these
Friday or Monday. GP: Prioritize any submittal that has a long
lead time.
AZT
Highest
2.4.2 Egress from Electrical Rooms:
01/16 GP: Submittal returned. CLOSED.
2.4.3 Generator Submittal:
01/07 DA to confirm if site lighting needs to be on the generator.
01/16 GP resubmitted this submittal to finalize the design. PC: DA
indicated that site lighting is currently on the generator due to
CHFA requirements.
01/23 PC: On hold for site lighting.
AZT/DA
High
2.4.4 Circuits for Heat Pumps & Condensate Pumps:
01/07 Electrician needs to know if heat pumps & condensate
pumps need separate circuits. Electrician recommends adding a
circuit, but will cost more. PC to clarify what is required.
01/16 PC: Rep responded that it is ok to not have a separate feed
from units that are 20 A or less. Otherwise they would need a
separate 120 V circuit. Will confirm on the submittal that we just
received.
01/23 PC: Will show separate feed, not dedicated.
AZT/PC
High
2.4.5 Design Changes Outstanding:
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #24
01/23/2020
Page 7 of 10
01/16 SO: I reviewed the updated MEP drawings. Bldg E 1st Flr,
Units C-3 & D-2 remain to be updated. PC: Yes, we will work on
that next.
01/23 PC: In progress.
AZT/PC High
2.5 ARCHITECTURAL TOPICS:
2.5.1 Architectural Submittals & RFI’s:
01/07 RFI’s 35 & 39 need architectural answers. Submittals are as
caught up as they can be – lighting & windows need SHPO
approval.
01/16 RFI’s 35 & 39 issued. Kitchen cabinet shop dwgs will be
returned by end of week. Continuing to work on lighting and
windows to get them ready to submit to SHPO & NPS.
01/23 SO: Kitchen shops, RFI’s 35 & 39 returned. RFI 45
outstanding.
PBBA
Highest
2.5.2 Existing Connections between B & D and D & E:
01/07 Dwgs issued. Structural needs to review.
01/16 SO to review framing options w/DM.
01/23 DM working on framing plan. CLOSED.
2.5.3 Below grade waterproofing at A, B, C, D, F:
01/07 PBBA needs to revise details for Bldg C & coordinate
w/BSC for drain.
01/16 SO: Same. Coordination w/AZT needs to occur also – need
to add mechanical ventilation in this area.
01/23 GP: Bldg C is priority. EK: Please record decision on
waterproofing for Bldgs F and B sub-basement. SO: Since the
walls in question in Bldg F & Bldg B sub-basement will remain
exposed & final grading/site solutions will lessen the amount of
water infiltration in the future, we decided to not waterproof
these walls. Leaving these walls exposed will allow any potential
future issues to be visible.
PBBA
High
2.5.4 Mason’s mortar samples:
12/31 SO: Reviewed what needs to be submitted to SHPO w/JS
yesterday - new item includes smokestack. Reviewed all mortar
samples w/Mason today. Mason will continue to prep samples &
will send some out for specialized color matching. SO will prep
list of mortar samples to be submitted to SHPO so we can track
progress.
01/07 PL: Mason is expecting mortar samples back by Friday.
01/16 SO: Will review w/Mason next Thursday on site. GP: Will
tell the Mason to have samples ready.
01/23 GP: Mason still waiting for samples to come back.
Estimated time 1.5 weeks. SO: Need to source 8x8 or 8x6 blocks
for smokestack. Need to prep list of mortar & brick color samples
PBBA/SO
High
2.5.5 Gutters:
01/07 Owner has reviewed. Owner requested PBBA to compare
existing gutter locations to proposed – should keep gutters
where gutters previously existed.
01/23 SO: Previous location of gutters reviewed – we are putting
new gutters at every location where gutters previously were. Will
issue updated drawings to show sketched design more clearly.
PBBA
High
2.5.6 Updates to all drawings to reflect design changes:
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #24
01/23/2020
Page 8 of 10
01/07 RCP’s next. Drawing list sheets to be updated weekly.
01/16 SO: Updated drawing set is underway. Will post it on
Egnyte site next Monday.
01/23 SO: Will issue next week.
PBBA
High
2.5.7 Meeting w/Postmaster:
01/07 FB: Should have this meeting soon – phone company was
asking if units will have addresses.
01/16 EK: Spoke w/Postmaster – 2 delivery locations is ok.
Postmaster is ok with Unit #’s as shown on Arch floor plans.
01/23 SO & EK need to review the 3rd delivery point. Owner is ok
with unit #’s as shown on arch floor plans.
SO/EK
High
2.5.8 Smoke detectors in Corridors:
12/31 SO to send inquiry (RFI-38)& answer to BO & FM.
01/16, 01/23 SO: Same.
PBBA
High
2.5.9 Ceiling Paint Color:
01/07 EK: Review ceiling colors w/EF – currently all ceilings are
white.
01/16 Not reviewed.
01/23 EK: Same.
DP/EK & EF
Medium
2.5.10 Meeting on Security:
01/07 Electrician requested that coordination meeting be
scheduled sooner than was done at CC. GP: Security submittal
was issued yesterday.
01/16 Not reviewed.
01/23 Tentative meeting on Feb. 6, 1:30pm
DP
High
2.5.11 Flood Vent Color:
01/16 Same. Reviewed earlier this week w/2 Historic Consultants
– agreed to not submit the color to SHPO/NPS.
01/23 SO: Need to supply color to MC.
PBBA
High
2.5.12 MC’s Priority:
01/16 GP: Updated RCP’s, Countertop overhang, RFI 39, 40.
01/23 SO: Countertop overhangs answered on kitchen shops;
RFI’s 39 & 40 answered. RCP’s are in process.
PBBA
Highest
2.5.13 Bldg A Units B-4 & B-6:
01/23 PL: Toilets in these units sit on top of beams. PBBA needs
to redesign bathroom layouts.
PBBA
Highest
2.6 SHPO APPROVALS
2.6.1 NPS Approval of Roofing Details:
01/16 Reviewed earlier this week w/2 Historic Consultants.
Continuous taper from edge of roof to ridge discussed as the only
viable option.
01/23 SO: PBBA to update proposed details with continuous
taper.
PBBA
High
2.6.2 Typical details to represent SHPO conditions:
01/16 Reviewed earlier this week w/2 Historic Consultants.
Agreed to follow Owner’s request to not submit these ASK’s to
SHPO/NPS, but to make sure that construction is following them.
GP: Pics of full-size mock-ups of 3 conditions of MEP runs in
corridors provided to SO. SO: Will review.
01/23 SO: Reviewing MEP mock-ups today.
PBBA/SO
High
2.6.3 Existing wood flooring in Bldgs A & B:
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #24
01/23/2020
Page 9 of 10
01/07 SO: Sent documentation to JS yesterday. On target to
submit to SHPO by end of the week.
01/16 Reviewed earlier this week w/2 Historic Consultants. On
recommendation of newly engaged Historic Consultant,
swapping all LVT in the project to another vinyl product. EK: Sent
this to EF, who is working on alternate products. PBBA to update
documentation with this info.
01/23 SO: Direction from DP is to use engineered wood
everywhere we are showing LVT. Will update floor finish pattern
drawings right after window drawings.
DP/EF
PBBA
High
High
2.6.4 Windows:
01/16 Met w/S&L & 2 Historic Consultants this week. Agreed to
stay w/metal windows. PBBA to change munton patterns in
several buildings per JS’s research, & create elevation drawings
of the existing window types. DP & MC working to find a window
manufacturer w/shorter lead time. As soon as window
manufacturer is decided, PBBA to issue sketches of existing &
proposed windows for submission to SHPO/NPS.
01/23 EK: Will have answer on window manufacturer by end of
day tomorrow. SO: Will do window drawings on Saturday.
DP/MC
PBBA
Highest
Highest
2.6.5 Signage:
01/16 Reviewed earlier this week w/2 Historic Consultants.
Stenciling on the exterior of the buildings suggested. This item is
the lowest priority to submit to SHPO/NPS, since it is not needed
until close to the end of construction.
01/23 SO: Same.
2.6.6 Design Changes:
01/16 Reviewed earlier this week w/2 Historic Consultants.
Agreed that Bldg E vestibule & changing windows to doors
should be submitted to SHPO/NPS. Girders in Bldg B & change of
use of Bldgs F & L do not need to be submitted.
01/23 SO: Same.
2.7 CONSTRUCTION TOPICS:
2.7.1 Transformers/Eversource Coordination/Electric Meter location:
01/23 GP: Met w/Eversource today. Eversource delivered their
design at mtg, which locates transformers & switch gear.
Eversource needs town-approved A-2 survey to start easement
process. He has Attorney & Survey contact info. Transformer
location at Bldg D: Put it right in front of the electric room.
2.7.2 Telephone/Cable lines:
12/31 EK: Using both services – Atlantic Broadband and Frontier.
Will keep trying to connect with Frontier. FB will follow up
w/Atlantic Broadband. GP: We should have meeting with
Electrician on site soon.
01/07 FB met w/Frontier Rep on site this morning.
01/16 Not reviewed.
01/23 PL: Frontier dropped off interior cable today. EK: Working
on agreements with the companies. FB: Both companies are
working with Gerry.
DP/FB
High
2.7.3 Electrical Utility Cost:
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #24
01/23/2020
Page 10 of 10
01/23 GP: Owner – Ryan Gussette – was here last week – the
electrical service is still in their name, so they are getting bills.
Should we move the service to our name? PL: Power company
charges $2500/month delivery charge whether power is used or
not. Our temporary service is being powered through this
service. Kent Rice is the manager of this property for the Owner.
EK: Will contact Kent Rice.
3.0 CHANGE ORDERS
3.1 Status:
01/16 Not reviewed.
01/23 Comprehensive review occurred after mtg.
4.0 REQUISITIONS
4.1 Status:
01/07, 01/16, 01/23 Not reviewed.
Job site meetings will be held weekly on Thursdays at 10:00 am, starting Jan. 16. Next up is a job site
meeting at 1:00 pm on January 30, 2020.
Recorded by Susan Odell, AIA, CPHC, Senior Project Architect, Paul B. Bailey Architect, LLC
These minutes are meant to convey & record the general content of the meeting, but do not represent a
verbatim recording. Please promptly respond to the Architect with any comments or questions.