HomeMy WebLinkAbout2019-12-31 Oxoboxo Mtg Min 21#16-063 Oxoboxo Lofts, Uncasville , CT MEETING MINUTES #21 PROJECT: Oxoboxo Lofts 42 Pink Row Uncasville, CT DATE: December 31, 2019 TIME: 10:00 a.m. LOCATION: Job Site/Conf Call Present: Eric Kuczarski (EK) DP EKuczarski@DakotaPartners.net Frank Brachanow (FB) Dakota Partners (DP) FBrachanow@DakotaPartners.net Gifford Perry (GP) MC Gifford@MaggioreCos.com Peter Lentine (PL) MC Peter@MaggioreCos.com Susan Odell (SO) Paul B. Bailey Architect (PBBA) SOdell@pbbarchitect.com Frank Vacca (FV) BSC FVacca@BSCGroup.com Pat Callahan (PC) AZT PCallahan@aztecheng.com Minutes to: Paul Maggiore (PM) MC Paul@MaggioreCos.com Dave Mann (DM) Maggiore Construction (MC) Dave@MaggioreCos.com Karl Walsh DP KWalsh@DakotaPartners.net Marc Daigle DP MDaigle@DakotaPartners.net Roberto Arista (RA) DP RArista@DakotaPartners.net Evan Fink (EF) DP EFink@DakotaPartners.net Matt Abraham (MA) DP MAbraham@DakotaPartners.net Alycia Quintiliani DP aquintiliani@dakotapartners.net Bill Rundlett DP Brundlett@dakotapartners.net Kurt Prochorena (KP) BSC Group (BSC) KProchorena@BSCGroup.com Brandon Handfield (BH) Yantic River Consultants Brandon@yrc-ne.com Dean Azzam (DA) Aztech Engineers, Inc. (AZT) DAzzam@aztecheng.com Sam Kirby SK) PBBA SKirby@pbbarchitect.com Tim Carr (TC) Down To Earth Consulting (DTEC) Tim@DownToEarthConsulting.com Dan Morrissey (DM) Morrissey Engineers (ME) daniel.morrissey@morrisseyengineers.com James Sexton (JS) SHPO/NPS Consultant jmbjcs@hotmail.com CONSTRUCTION DATES: Dam Removal: Start Date: Oct 18, 2019 EST. End Date: Unknown Lofts Construction: Start Date: August 1, 2019 End Date: December 18, 2020 Responsible Party Priority Level 1.0 CONSTRUCTION SCHEDULE & PROGRESS 1.1 CONSTRUCTION SCHEDULE: 1.1.1 Status: 12/24 Plumbing design, Bldg B floor, Bldg F structure, typical waterproofing detail issued. Field reports are being issued by DM as needed – next one will answer RFI 16 for existing site walls. All remaining overdue RFI’s & Submittals are almost caught up with exception of ones involving SHPO issues. Atypical waterproofing detail at Bldg C will be issued ASAP. Bldg F HVAC design will be issued by 12/31. All SHPO issues will be reviewed on site w/JS on Monday 12/30. #16-063 Oxoboxo Lofts, Uncasville, CT Meeting Minutes #21 12/31/2019 Page 2 of 8 12/31 Not reviewed. 1.2 CONSTRUCTION PROGRESS: 1.2.1 Status: 12/17, 12/24, 12/31 Not reviewed. 2.0 CONSTRUCTION TOPICS 2.1 SITE/CIVIL TOPICS: 2.1.1 Site/Civil Submittals & RFI’s: 12/31 FV: Misc metals returned with revise/resubmit to get cost down. Light fixture submittal is in review, waiting for photometric calc’s. BSC/FV High 2.1.2 Encroachment Permit for Guardrail on Route 32: 12/24 FV: Mayor agreed w/shifting driveway over, as long as largest fire apparatus can access the site. Drawing in process – should be CSK-05 issued in the near future. Mayor also wants BSC to reach out to transit authority to make sure there is not an issue accessing the site. 12/31 FV: Moving forward on meetings w/transit authority.. BSC/FV Medium 2.1.3 Coordination w/AZT: 12/31 FV: Utility plan for gas line will be shown on CSK-04. I need to get sanitary inverts today in order to submit CSK-04. Will benchmark the top of arch under Bldg K today. 100 year elevation is the floodway – sanitary needs to be above the 100 year. Will wait to see final location on the ejector pits & will locate them on site plan. AZT & FV High 2.1.4 Site Lighting: 12/31 FV: All site lighting locations complete & sent to Sylvia at Apex to get new photometric plan. Handrail lighting changed to wall packs, solar poles changed to elec power poles. Bollards near Bldg M have been changed to wall packs. Sylvia on vacation until Thursday – will contact her on Thursday. Will submit CSK-03 as soon as she signs off on adequacy of wall packs. BSC/FV High 2.1.5 Bldg B Basement Floor Level: 12/31 FV: Working on revised drainage plan to pick up gutters/leaders. Will issue after Bldg B Basement is confirmed. PL: Will do that today. MC/PL High 2.1.6 Bldg M basement access: 12/17 Discussion of FMC approval of Basement of Bldg M – our request to leave the basement open has not been approved – so BSC will wait to detail new entrances into Bldg M Basement. 12/24, 12/31 On hold until FMC is resolved. 2.1.7 Bridge over Raceway: 12/31 DM indicated that a pre-fab bridge would be least expensive option. FV following up on selection. BSC/FV Medium 2.1.8 Site Walls: 12/31 FV: Sent plan yesterday showing walls that DM had identified as critical. Need direction from Owner on how much further, if any, to go on site wall replacement. Walls at G that DM identified would need to be coordinated with DEEP work if we decide to do it. DP/MC Medium #16-063 Oxoboxo Lofts, Uncasville, CT Meeting Minutes #21 12/31/2019 Page 3 of 8 2.2 DEEP TOPICS: FMC, CONSENT ORDER, WORK AT RIVER (BSC & YANTIC RIVER CONSULTANTS – BRANDON HANDFIELD): 2.2.1 FMC Application to DEEP: 12/03, 12/10, 12/17 See consent order topic below. 12/24 FV: Trying to set up meeting in January to keep FMC going. 12/31 FV: No word on a meeting with DEEP yet. 2.2.2 Consent Order: 12/24 EK: Consultants are preparing reports on work that was done last week to remove fill in the river & Attorney is contacting DEEP for direction. 12/31 EK: Still wrapping up paperwork for work at waterway. Will ask for meeting after that is wrapped up. 2.2.3 Helical Pile Installation: 11/26 FV: How much work remains? GP: 2 days for helical piles, 1 or 2 weeks for grout bags. Helical pile contractor has asked when they can come back. Do we know? FV: We do not know. 12/03, 12/10, 12/17, 12/24, 12/31 Not reviewed. 2.2.4 Grout Bag Submittal: 12/03 SO: Reviewed BH’s comments w/GP & Susan Weglein. GP: We will resubmit the submittal. 12/10, 12/17, 12/24, 12/31 Not reviewed. MC/GP Medium 2.3 ENVIRONMENTAL REMEDIATION TOPICS (DOWN TO EARTH – TIM CARR): 2.3.1 Environmental Submittals & RFI’s: 12/24, 12/31 Not reviewed. 2.3.2 RAP Application to DEEP: 12/10 TC: Testing of buildings is almost complete. Data package available but no formal submittal to the state. Will submit mid- January. 1 sample in Bldg D has to be re-taken, scheduled for tomorrow. 12/17 TC: Sample in Bldg D taken last week. Might need to do indoor air sampling in Bldgs H & J based on conversation w/DEEP yesterday. Talked to DEEP yesterday – meeting to be scheduled in January about the RAP & the path forward. 12/24, 12/31 Not reviewed. 2.3.3 Injection System: (related topic below: equipment in Bldg M Basement) 11/05 TC: Still on hold. Winter will dictate the work – have to pump 40k gallons of water into the ground. (Extended discussion of where the water might come from) RA: Work on hold until Dakota owns the property. TC: Process & results of injection takes about 1 year. 11/12, 11/19, 11/26, 12/03 Not reviewed. 12/10, 12/17 TC: Still on hold. 12/24, 12/31 Not reviewed. 2.3.4 Abandoned Brownfield Application to DEEP: 10/25 TC: Working on DEEP sign-off, then DECD has to sign off. Need approval before closing since we can’t get into that program after purchase. FB: Anything we need to do? TC: Nothing for #16-063 Oxoboxo Lofts, Uncasville, CT Meeting Minutes #21 12/31/2019 Page 4 of 8 construction – this is more legal. Had a call yesterday w/RA & Attorney so process is moving forward. 11/01, 11/05, 11/12, 11/19, 11/26, 12/03,12/10 Not reviewed. 12/10, 12/17 TC: Status uncertain. 12/24, 12/31 Not reviewed. 2.3.5 SVE Equipment: 12/10 TC: Installed 4 soil vapor extraction wells last week. The new SVE equipment (soil vapor extraction pump & controls) will be brought in on a 4’x4’x6’ skid rig. Proposed to go in the southeast corner of F. SK: That is where we show it. Be aware that there is a raised floor in that area. TC: Ok. 12/17 TC: Will submit description of sound-proofing needed. SO: We don’t need sound-proofing inside Bldg F – it is all mechanical space now. 12/24, 12/31 Not reviewed. 2.3.6 Remediation in Courtyard: 12/10 TC: Removed 30 tons of soil from courtyard, took 15 samples, 1 exceeded. Tentatively scheduled to return tomorrow pending weather. 12/17 TC: Did not excavate because it is in the floodway. Stockpile is outside the floodway, working on permits for disposal. 12/24, 12/31 Not reviewed DTE/TC Medium 2.3.7 Equipment in M Basement: 12/24, 12/31 Not reviewed. 2.3.8 Contaminated soils under removed oil tank: 12/10 TC: Contaminated still removal tentatively scheduled for tomorrow. FB: Scope? TC: We will excavate to 2 foot depth but depth of actual contamination is somewhat unknown. Will test soil that remains. 12/17 TC: Excavated area last week. 12/24, 12/31 Not reviewed. DTE/TC Medium 2.3.9 Haz-Mat Removal Reports: 12/10 TC: Need copies of all hazardous material removal reports - Bill of ladens – for haz mat work done inside the buildings. GP: Ok, will send. 12/17 GP: Underway - asked the subs for these. 12/24, 12/31 Not reviewed. MC/GP Medium 2.3 STRUCTURAL TOPICS: 2.3.1 Structural Submittals & RFI’s: 12/31 RFI 32 remains outstanding. ME Highest 2.3.2 Bridge over raceway behind Bldg B: 12/24 DM indicated that a prefab bridge would be least expensive option. 12/31 Topic moved to Site/Civil. CLOSED. 2.3.3 Bldg C Revisions to Structural Dwgs: 12/24: SO: PBA will send updated Revit model to ME next week so ME can update structural drawings. 12/31 SO: PBA sent updated Revit model to ME . ME High 2.3.4 Hatchway in floor 4 of Bldg B, North Tower: 12/24 DM: Will handle structural support of opening w/sleepers. 12/31 Not reviewed. ME High #16-063 Oxoboxo Lofts, Uncasville, CT Meeting Minutes #21 12/31/2019 Page 5 of 8 2.3.5 MEP running in J & H corridors at brick arches: 12/24 PL: Arches are too low to run MEP below them – need to cut hole in brick wall above. DM: Can be covered with lintel schedule previously issued. Needs to be minimum of 16” above arch. 12/31 Direction given to MC by DM. CLOSED. 2.3.6 New Issues from 12/24 Site Meeting: 12/31 DM waiting on feedback from MC before he can move forward. PL sent photos to DM but not sure they are enough. ME/MC High 2.3.7 Bldg B South Stair: 12/31 BO commented that wall supporting roof (inset wall at Level 4) needs support inside the south stair tower. DM to issue sketch. ME/DM High 2.3.8 Special Inspections: 12/31 Materials Testing issued 1st report, which needs to be reviewed by DM before going to BO. (See also topic below under Construction Topics) ME/DM High 2.4 MEP TOPICS: 2.4.1 MEP Submittals & RFI’s: 12/31 PC: RFI 30 & 33, Submittal for panel boards/load centers will be issued today. Remaining submittals will be issued by the due date. AZT Highest 2.4.2 Ejector Pit Redesign/Elimination: 12/24 Ejector pit shown on new plumbing dwgs. Location reviewed & communicated to FV. Alarm panel for pump will be in the Elec Rm of Bldg H. No vault needed – buried in pit on crushed stone. FV needs invert for pipe exiting the building. Jason of DEF provided to PC. 12/31 PC: Jason has been sending #’s from the field today. Coordination w/BSC ongoing. AZT High 2.4.3 Egress from Electrical Rooms: 12/31 PC: Submittal for revised Bldg D layout is due 1/6. AZT/DA High 2.4.4 Smoke detectors in Corridors: 12/24 Smoke detectors are shown in some corridors – BO questioned if they are required. GP: sent email to DA yesterday with this question. 12/31 Not reviewed. AZT/DA High 2.4.5 Generator Submittal: 12/24 GP: Submittal was returned, but design is incomplete. Will resubmit for final design (to include site lighting) after 12/31 deadline for electrical updates. 12/31 Not reviewed. MC High 2.4.6 Electrical Outlets on exterior walls: 12/24 PL: Can we run exposed from side walls? FB: Yes. 12/31 PL: SO was to review outlet locations on exterior walls. PBA/SO High 2.4.7 Supply & return water source loop: 12/24 Jason: Currently shown as dead ending – please review if they should be looped. PL: Ok. 12/31 Not reviewed. AZT/PC High 2.4.8 Updated Mechanical Schedules: AZT/PC High #16-063 Oxoboxo Lofts, Uncasville, CT Meeting Minutes #21 12/31/2019 Page 6 of 8 12/31 PC: Issued mark-up showing changes to schedules. Final version will be in updated dwgs. 2.4.9 Dates on PSK’s: 12/24 GP: Please add issuance dates to the PSK’s. PC: Will do. 12/31 PC: Dates were added, will issue. AZT/PC High 2.5 ARCHITECTURAL TOPICS: 2.5.1 Architectural Submittals & RFI’s: 12/31 SO: RFI 10: All existing windows have been measured & drawn. RFI 19: FM indicated no sprinklers req’d in Bldg L if use is light-duty storage. PBA to issue sketch showing this. Misc metal submittal returned. Lighting fixtures & window shops will remain outstanding due to SHPO/NPS review, but progress is being made on these. PBA Highest 2.5.2 Updated package of drawings for permit: 12/31 SO: Mtg w/BO went well. See Mtg Min of this mtg for complete details. CLOSED. 2.5.3 Existing Connections between B & D and D & E: 12/24 SO: Dwgs will be issued next week. 12/31 SO: Same. PBA Medium 2.5.4 Below grade waterproofing at A, B, C, D, F: 12/31 SO: Bldg C detail issued but will be revised per feedback from MC. GP: Waterproofing at Bldg A, B, D, F? SO: Have not talked about Bldg A until today – will take a look at it. Bldgs B & F – discussion previously held & decision was made to not waterproof here since walls that receive moisture will remain exposed for future examination, and these areas are mechanical areas, not residential areas. Bldg D would receive the typical waterproofing detail, unless excavation reveals unique circumstances. Test pits have not yet been done for Bldg D. PBA Highest 2.5.5 Mason’s mortar samples: 12/31 SO: Reviewed what needs to be submitted to SHPO w/JS yesterday - new item includes smokestack. Reviewed all mortar samples w/Mason today. Mason will continue to prep samples & will send some out for specialized color matching. SO will prep list of mortar samples to be submitted to SHPO so we can track progress. PBA/SO High 2.5.6 Existing windows in M and F: 12/31 SO: All existing windows have been measured & drawn. Topic moved to SHPO. CLOSED. 2.5.7 Gutters: 12/31 SO: Reviewed all gutter locations & sent sketch out for review that shows where gutters could be eliminated, and where leaders should be tied into underground drainage. Owner needs to review & comment. BSC is proceeding w/including all leaders in underground drainage. There should be credits for eliminated gutters but leaders going to underground drainage might be an add – architectural dwgs noted them connecting to underground drainage but drainage plan did not show them. 2.5.8 Crawl space below Bldg G, H, J: 12/24 PL: BO asked for wider passage – will modify 1 row of studs to accommodate. SO: Will also issue ASK showing 30”x36” #16-063 Oxoboxo Lofts, Uncasville, CT Meeting Minutes #21 12/31/2019 Page 7 of 8 insulated access hatches, with lock on the panel in the corridor. GP: Provide spec also. SO: Will do. 12/31 SO: ASK & spec for access hatches issued. Does MC need any dwgs on wider passage? PL/GP: No. CLOSED. 2.5.9 Updates to all drawings to reflect design changes: 12/24 SO: We are reviewing & updating all drawings to reflect design changes. RCP’s will be updated after revised electric dwgs are issued. Dwg list sheets will be issued ASAP – review revealed some corrections needed. Dimensions in corridors of Bldgs A, B & K will be checked & corrected as needed. 12/31 SO: Corrected dwg list sheets were issued. Other items underway. 2.5.10 Meeting w/Postmaster: 12/24 SO: Postponing this meeting until other items are caught up. 12/31 SO: Same. 2.6 SHPO APPROVALS 2.6.1 NPS Approval of Roofing Details: 12/24 SO: Will measure roof metal edge today, then revise details & review w/JS at Monday’s mtg. 12/31 SO: Measurement of roof edge showed max 1” gain at rakes only. Reviewed how to proceed w/JS yesterday – we will show a continuous taper of the insulation from the edge of the roof to the ridge. 2.6.2 Typical details to represent SHPO conditions: 12/31 SO: Both ASK’s were reviewed w/JS yesterday. Window clearance is fine to send, but MEP obstruction needs further info/review. Will review in the field w/MC today for Bldg J & revise sketch. Lively discussion held about options for where the MEP would go if it can’t go in the corridors. SO to check if any MEP’s can go through units without needing add’l fire protection. 2.6.3 Existing wood flooring in Bldgs A & B: 12/31 SO: Reviewed w/JS yesterday. We will submit to not reuse existing floors since they are so out of level. We will include locations of floor patches on the drawings so this can be a backup if needed. PBA to send all info to JS by Jan 6; JS to submit to SHPO by Jan 10. 2.6.4 Windows: 12/31 SO: Reviewed w/JS, who indicated that Bldgs A, B, C, D should have 6/6 DH’s (except for clerestory windows at Bldg B, 4th floor) and that Bldg E should have 2/2 DH’s. Bldg F should have matching 12/12 DH’s & clerestory windows per dwgs of existing windows. We should pursue aluminum clad wood windows in all of these bldgs. Windows for Bldgs G, H, J, K, L, M should proceed in metal with the request to make the lower portion operable as the reason to use metal. 2.6.5 Signage: 12/31 SO: Reviewed signage w/JS yesterday. EK selected an industrial look for the signage (white background, black letters, sans serif font) and confirmed w/signage supplier that a tin look can be achieved. EK indicated to send the site sign to EF for #16-063 Oxoboxo Lofts, Uncasville, CT Meeting Minutes #21 12/31/2019 Page 8 of 8 review. FM requested signage that identifies each building – EK & JS agreed that the temporary signage that MC did is fine as a model for the permanent solution. 2.7 CONSTRUCTION TOPICS: 2.7.1 Pricing for raising floors in Bldgs G, H & J above 500 year flood: 12/17 SO: Reviewed w/BO after mtg who referred the sprinkler issue to the FM. SO to meet w/FM to resolve. 12/24 SO: Mtg w/FM today. 12/31 SO: FM agreed that no sprinklers under floors in G, H & J are required. CLOSED. 2.7.2 Transformers/Eversource Coordination/Electric Meter location: 12/10 GP: Eversource returned Electrician’s call at the end of last week & indicated that they are just starting to look at our project. 12/17, 12/24 Not reviewed. 12/31 GP: Eversource is on vacation – no update. 2.7.3 Telephone/Cable lines: 12/31 EK: Using both services – Atlantic Broadband and Frontier. Will keep trying to connect with Frontier. FB will follow up w/Atlantic Broadband. GP: We should have meeting with Electrician on site soon. DP/FB High 2.7.4 Mechanical Work on Hold Until BO reviews Addendum 8: 12/31 SO: Spoke w/Dave Jensen today about Mech. His only issue is where the exhaust for the boilers in Bldg B will exit – it has to be 10 feet away from any operable opening. Will look at relocating it to the east side of the building. GP: Have they issued permit to the subs? PL, follow up w/Jason. PL: Will do. MC/PL High 2.7.5 Material Testing: 12/31 PL: Inspector from Materials Testing was on site & was not happy that we don’t have drawings documenting all conditions that exist in the field. Report reflects this. FB: Report from Materials Testing sent to DM for review. Do not send to BO until DM reviews & comments. ME/DM High 3.0 CHANGE ORDERS 3.1 Status: 12/31 GP: Will be issuing several change estimates in the next few days. 4.0 REQUISITIONS 4.1 Status: 12/24, 12/31 Not reviewed. Alternating job site meetings/conference calls will be held weekly. Next up is a conference call at 10:00 am on January 7, 2020. Recorded by Susan Odell, AIA, CPHC, Senior Project Architect, Paul B. Bailey Architect, LLC These minutes are meant to convey & record the general content of the meeting, but do not represent a verbatim recording. Please promptly respond to the Architect with any comments or questions.