HomeMy WebLinkAbout2019-12-17 Oxoboxo Mtg Min 19#16-063
Oxoboxo Lofts, Uncasville , CT
MEETING MINUTES #19
PROJECT: Oxoboxo Lofts
42 Pink Row
Uncasville, CT
DATE: December 17, 2019
TIME: 10:00 a.m.
LOCATION: Job Site
Present:
Eric Kuczarski (EK) DP EKuczarski@DakotaPartners.net
Frank Brachanow (FB) Dakota Partners (DP) FBrachanow@DakotaPartners.net
Gifford Perry (GP) MC Gifford@MaggioreCos.com
Peter Lentine (PL) MC Peter@MaggioreCos.com
Susan Odell (SO) Paul B. Bailey Architect (PBBA) SOdell@pbbarchitect.com
Sam Kirby (SK) PBBA SKirby@pbbarchitect.com
Frank Vacca (FV) BSC FVacca@BSCGroup.com
Pat Callahan (PC) AZT PCallahan@aztecheng.com
Tim Carr (TC) Down To Earth Consulting (DTEC) Tim@DownToEarthConsulting.com
Dan Morrissey (DM) Morrissey Engineers (ME) daniel.morrissey@morrisseyengineers.com
Minutes to:
Paul Maggiore (PM) MC Paul@MaggioreCos.com
Dave Mann (DM) Maggiore Construction (MC) Dave@MaggioreCos.com
Karl Walsh DP KWalsh@DakotaPartners.net
Marc Daigle DP MDaigle@DakotaPartners.net
Roberto Arista (RA) DP RArista@DakotaPartners.net
Evan Fink (EF) DP EFink@DakotaPartners.net
Matt Abraham (MA) DP MAbraham@DakotaPartners.net
Alycia Quintiliani DP aquintiliani@dakotapartners.net
Bill Rundlett DP Brundlett@dakotapartners.net
Kurt Prochorena (KP) BSC Group (BSC) KProchorena@BSCGroup.com
Brandon Handfield (BH) Yantic River Consultants Brandon@yrc-ne.com
Dean Azzam (DA) Aztech Engineers, Inc. (AZT) DAzzam@aztecheng.com
James Sexton (JS) SHPO/NPS Consultant jmbjcs@hotmail.com
CONSTRUCTION DATES: Dam Removal: Start Date: Oct 18, 2019 EST. End Date: Unknown
Lofts Construction: Start Date: August 1, 2019 End Date: November 1, 2020
Responsible
Party
Priority
Level
1.0 CONSTRUCTION SCHEDULE & PROGRESS
1.1 CONSTRUCTION SCHEDULE:
1.1.1 Status:
10/25 GP: Still behind schedule. Helical pile installation starts 10/28,
weather permitting.
11/01 GP: Same on schedule. Helical pile installation underway.
11/05, 11/12, 11/19, 11/26 Not reviewed.
12/03 GP: MC is at a standstill at several areas and cannot start
work and the construction schedule is being severely delayed due
to some of the following:
Plumbing design
AZT
HIGHEST
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #19
12/17/2019
Page 2 of 8
Bldg B floor
Bldg F structure & HVAC design
SHPO
RFI’s
Shop drawings submittals
Field reports
12/10 GP: Add waterproofing to the list above.
12/17 Reviewed status of items above w/all of the design team.
ME
PBA/ME/AZT
PBA/JC/MC
PBA/ME/AZT
/BSC
PBA/AZT
ME
PBA
HIGHEST
HIGHEST
HIGHEST
HIGHEST
HIGHEST
HIGHEST
HIGHEST
1.2 CONSTRUCTION PROGRESS:
1.2.1 Status:
12/10 GP: Insulating M underway. Have permit sign off for M & K.
Decking over those areas, starting walls soon after. J & G are
decked over & walls have started. Some plumbing at J & G
underway. Mason on site doing samples & washing. Starting A
knee walls next week. On hold on F & B.
12/17 Not reviewed.
2.0 CONSTRUCTION TOPICS
2.1 SITE/CIVIL TOPICS:
2.1.1 Site/Civil Submittals & RFI’s:
12/10 FV: Have CSK-001 95% ready which will answer RFI’s 27 &
28. Pending coordination w/GP, SO & answer from FM on FD
connection style (sent via email to FM yesterday).
12/17 FV: Will issue final CSK-01 by end of day to answer most of
RFI’s 27 & 28. CSK-02 will follow by end of week to answer
remaining portion. Submittals on site lighting & site misc metals
will be returned by end of week.
BSC/FV
High
2.1.2 Encroachment Permit for Guardrail on Route 32:
12/10 FV: Have sketch to review w/Mayor (Traffic Authority) that
pulls our driveway just outside the ConDOT’s jurisdiction by
replacing the existing curb cut in its existing location. Mayor may
want the driveway to be entrance only. Eliminating sidewalk
connection to ConDOT jurisdiction (stopping it at the bus stop),
not touching the guardrail that is under ConDOT’s jurisdiction,
which will remove all of our work from ConDOT’s jurisdiction.
Have to confirm exact location of right of way w/surveyor. We will
not have to meet w/ConDOT if everything works out.
12/17 FV: Meeting w/Mayor today.
BSC/FV
Medium
2.1.3 Coordination w/AZT:
12/10 FV: Will issue CSK to show all gas lines that are going into
& out of Bldg F. SO to send AZT dwgs to FV.
12/17 FV: Will continue to coordinate w/AZT. Will benchmark
top of arch that crosses river at Bldg’s H/K to confirm location
of sanitary line & possible need for bracing of line. Will check
new sanitary & gas line locations that AZT will show &
coordinate utility plan. Will show ejector pit needed for Bldg J.
(See below under MEP)
AZT & FV
High
2.1.4 Concrete site walls:
11/26 GP: There are many different site walls – cheek walls, etc.
We could be working on them if we had details. SK: Will send
Addendum 8 drawings for all changes to FV for his review. FV:
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #19
12/17/2019
Page 3 of 8
Landings, stairs & ramps for the raised floors were shown on our
drawings but not detailed.
12/03 FV: Part of RFI 27, will review w/GP today.
12/10 FV: Have some further questions on site walls to review
w/GP today.
12/17 FV: CSK-02 will provide details of landings, stairs & ramps &
info on ready-rock wall behind generator. Will be issued by
12/20/19.
BSC/FV
High
2.1.5 Site Lighting:
12/17 Site lighting submittal reviewed at meeting. Site pole
lighting to all be as shown on site lighting plan, not some Razar as
in submittal. FV to coordinate w/lighting rep to provide wall
sconces at all exterior doors – gooseneck industrial style discussed
to meet SHPO review – EK wants pricing on this. CSK-03 will be
updated site lighting plan that shows wall sconces at exterior
doors, solar removal. AZT informed that electrical site plan needs
updating to include all formerly solar light poles.
BSC/FV
High
2.1.6 Bldg B Basement Floor Level:
12/17 MC to verify floor level. Pending results, BSC to add area
drain at exterior door.
MC/PL
High
2.1.7 Bldg M basement access:
12/17 Discussion of FMC approval of Basement of Bldg M – our
request to leave the basement open has not been approved – so
BSC will wait to detail new entrances into Bldg M Basement.
2.2 DEEP TOPICS: FMC, CONSENT ORDER, WORK AT
RIVER (BSC & YANTIC RIVER CONSULTANTS –
BRANDON HANDFIELD):
2.2.1 FMC Application to DEEP:
12/03, 12/10, 12/17 See consent order topic below.
2.2.2 Consent Order:
12/10 BH is finalizing remediation plan after MC review. Plan
shows helical piles to remain. PL: The plan gives us 5 days from
installation of silt fence to removing everything.
12/17 Remediation work at river bed near Bldg J is underway
today.
2.2.3 Helical Pile Installation:
11/26 FV: How much work remains? GP: 2 days for helical piles, 1
or 2 weeks for grout bags. Helical pile contractor has asked when
they can come back. Do we know? FV: We do not know.
12/03, 12/10, 12/17 Not reviewed.
2.2.4 Grout Bag Submittal:
12/03 SO: Reviewed BH’s comments w/GP & Susan Weglein. GP:
We will resubmit the submittal.
12/10, 12/17 Not reviewed.
MC/GP
Medium
2.3 ENVIRONMENTAL REMEDIATION TOPICS (DOWN
TO EARTH – TIM CARR):
2.3.1 Environmental Submittals & RFI’s:
12/17 No RFI’s or submittals outstanding.
2.3.2 RAP Application to DEEP:
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #19
12/17/2019
Page 4 of 8
12/10 TC: Testing of buildings is almost complete. Data package
available but no formal submittal to the state. Will submit mid-
January. 1 sample in Bldg D has to be re-taken, scheduled for
tomorrow.
12/17 TC: Sample in Bldg D taken last week. Might need to do
indoor air sampling in Bldgs H & J based on conversation w/DEEP
yesterday. Talked to DEEP yesterday – meeting to be scheduled in
January about the RAP & the path forward.
DTEC
High
2.3.3 Injection System: (related topic below: equipment in Bldg M
Basement)
11/05 TC: Still on hold. Winter will dictate the work – have to
pump 40k gallons of water into the ground. (Extended discussion
of where the water might come from) RA: Work on hold until
Dakota owns the property. TC: Process & results of injection
takes about 1 year.
11/12, 11/19, 11/26, 12/03 Not reviewed.
12/10, 12/17 TC: Still on hold.
2.3.4 Abandoned Brownfield Application to DEEP:
10/25 TC: Working on DEEP sign-off, then DECD has to sign off.
Need approval before closing since we can’t get into that program
after purchase. FB: Anything we need to do? TC: Nothing for
construction – this is more legal. Had a call yesterday w/RA &
Attorney so process is moving forward.
11/01, 11/05, 11/12, 11/19, 11/26, 12/03,12/10 Not reviewed.
12/10, 12/17 TC: Status uncertain.
2.3.5 SVE Equipment:
12/10 TC: Installed 4 soil vapor extraction wells last week. The
new SVE equipment (soil vapor extraction pump & controls) will
be brought in on a 4’x4’x6’ skid rig. Proposed to go in the
southeast corner of F. SK: That is where we show it. Be aware
that there is a raised floor in that area. TC: Ok.
12/17 TC: Will submit description of sound-proofing needed. SO:
We don’t need sound-proofing inside Bldg F – it is all mechanical
space now.
2.3.6 Remediation in Courtyard:
12/10 TC: Removed 30 tons of soil from courtyard, took 15
samples, 1 exceeded. Tentatively scheduled to return tomorrow
pending weather.
12/17 TC: Did not excavate because it is in the floodway. Stockpile
is outside the floodway, working on permits for disposal.
DTEC
Medium
2.3.7 Equipment in M Basement:
12/03 SO: RFI answer from Aztech remains outstanding.
12/10 SO: Same on RFI. TC: Equipment has to keep running over
the winter.
12/17 SO: RFI to be answered in updated elec dwgs.
AZT
Highest
2.3.8 Contaminated soils under removed oil tank:
12/10 TC: Contaminated still removal tentatively scheduled for
tomorrow. FB: Scope? TC: We will excavate to 2 foot depth but
depth of actual contamination is somewhat unknown. Will test
soil that remains.
12/17 TC: Excavated area last week.
DTEC
High
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #19
12/17/2019
Page 5 of 8
2.3.9 Haz-Mat Removal Reports:
12/10 TC: Need copies of all hazardous material removal reports
- Bill of ladens – for haz mat work done inside the buildings. GP:
Ok, will send.
12/17 GP: Underway - asked the subs for these.
MC/GP
Medium
2.3 STRUCTURAL TOPICS:
2.3.1 Structural Submittals & RFI’s:
12/10 DM: Reviewing record set of cold-formed metal framing-
will complete tomorrow. RFI-25 answered. RFI-31 sketch for Bldg
D will be issued today. Need info from PBA to answer Bldg B
portion of RFI-31 – will issue sketch on Bldg B tomorrow.
12/17 DM: Still need answer from PBA for RFI 31.
PBA/SK
Highest
2.3.2 Bldg B: Floors, Various column issues:
12/17 DM: Will issue all sketches Wednesday or Thursday
ME
Highest
2.3.3 SKS for support for water heater tanks in Bldg H:
12/17 DM: Issued. SO: Missed them, will find & forward to GP.
PBA/SO
Highest
2.3.4 Bldg B floor deflection:
12/17 DM: Need confirmation on construction method. Answer:
High point of floors will be top of sleepers. DM: Will issue sketch
this week.
ME
Highest
2.4 MEP TOPICS:
2.4.1 MEP Submittals & RFI’s:
12/17 PC: Pumps, tanks, heat exchanger, Berto elec wall & unit
heaters, VFD’s for pumps returned. Plumbing fixtures & HWH’s
will be returned by 12/18. Generator review was halted by info
needed – info received & submittal will be returned by 12/20.
Light fixtures & media boxes will be returned by 12/20. Panel
boards & load centers will be returned by 12/27.
AZT
Highest
2.4.2 Ejector Pit Redesign/Elimination:
12/17 PC: Working on plumbing dwgs due 12/20. Plumber
informed at mtg that Bldg J will need an ejector pump – location
to be outside on the north side of the bldg. Will try to incorporate
this new info & still issue dwgs by 12/20.
AZT/PC
Highest
2.4.3 Egress from Electrical Rooms:
12/17 PC: DA reviewed, thinks some equipment needs to be
relocated to achieve required clearances. SO: Electrician indicated
this morning that he is re-working layout based on these
comments & will issue new submittal.
AZT/DA
High
2.5 ARCHITECTURAL TOPICS:
2.5.1 Architectural Submittals & RFI’s:
12/03 RFI’s 10, 19, 21, 23, 24, 26, 28 outstanding. Submittals for
drywall & window shop dwgs outstanding.
12/10, 12/17 SO: All outstanding RFI’s & submittals will be
returned by Dec. 20.
PBA
Highest
2.5.2 Updated package of drawings for permit:
12/10 SO: Stopped by BO’s office last Thursday & reviewed some
items. Set tentative mtg for Thursday of this week, pending their
confirmation. Prepping for the mtg by collating code issues
(including venting of space under Bldgs G, H,J)
PBA/SO
Highest
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #19
12/17/2019
Page 6 of 8
12/17 SO & EK went to BO office after mtg to check status of
review. DJ indicated that review has not moved forward but SO
answered add’l questions & noted add’l items that BO requested.
2.5.3 Flood Vents:
12/03 SK: Details underway.
12/10, 12/17 Same.
PBA
Low
2.5.4 Existing Connections between B & D and D & E:
12/03 SK: Dwgs are ready to issue as soon as crash of connector
into window of Bldg B is resolved. We will review the site
condition today.
12/10, 12/17 Same.
PBA/SK
Medium
2.5.5 Insulation & Waterproofing where Bldg K crosses the stream:
12/03 SO: Same. Insulation above the floor is limited at the river
crossing at Bldg K, so will definitely need some insulation below
the floor.
12/10 SO: Same.
12/17 SO: Will be issued by 12/20.
PBA
Medium
2.5.6 Below grade waterproofing at A, B, C, D, F:
11/19 SO: Paul Bailey reviewed results of test pits & directed that
wall should be rebuilt from the exterior w/concrete. FB: Cost will
be extraordinary. Any other solution? Solution discussion
followed. DM/PBA to review/issue alternate solutions.
11/26 SO: Same. PL: In my absence, there has been backfill
against wall of G w/no waterproofing. SO: Should not put soil
against a brick wall where there was no soil before without
waterproofing. PL: Agreed, need waterproofing details.
12/03 PBA & ME reviewed solution after the meeting. PBA to
create dwgs to show solution.
12/10 SO: Same.
12/17 SO: Will be issued by 12/20.
PBA
Highest
2.5.7 Mason’s mortar samples:
11/19 SO: Mason has samples installed on site but indicated that
they need additional washing before we review.
11/26, 12/03 Not reviewed.
12/10 Reviewed mason’s samples. Sample on M: color is good,
needs more washing to reveal more aggregate. Established 7
areas of brick color to submit to SHPO. Need to verify if there are
7 corresponding areas of mortar color (probably fewer). Mason
should prep samples for all mortar colors.
12/17 Not reviewed.
2.5.8 Existing windows in M and F:
11/26 SK: Details are almost complete – will issue ASAP.
12/03 SK: Getting missing details on site today.
12/10 SK: Same.
12/17 SO: Bldg M window details are done. SO measured DH
window in Bldg F after mtg. Bldg F transom windows (accessible
only by very tall ladder or climbing onto lower roof) still need to
be measured.
PBA
High
2.5.9 Gutters:
11/19 SO: We show gutters on all buildings but they go to splash
blocks, not to underground drainage system. Could be cost
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #19
12/17/2019
Page 7 of 8
savings to eliminate them in areas, such as courtyard. We would
keep them where drainage is a problem, such as around Bldg C.
EK: Please review where elimination is possible.
11/26, 12/03, 12/10, 12/17 SO: Same
PBA
Low
2.5.10 Bldg B “Attic” triangle:
12/03 GP: BO says that the area qualifies as an attic & will need
sprinklers. SO: We will review.
12/10 SO: Review in process. Solution of moving knee wall back
reviewed.
12/17 SO: Detail will be issued by 12/20.
PBA/SK
High
2.6 SHPO APPROVALS
2.6.1 NPS Approval of Roofing Details:
11/26 GP: Fascia board was painted. SO: Will go to site to
photograph completed roof mock-up & send to JS for review.
12/03 SO: Photos taken, noticed that the existing edge material
is taller than the new edge – might give us some extra height for
insulation.
12/10 SO: Need access to roof mock-up to measure the existing
metal edge.
12/17 SO: Same, pending good weather day.
PBA/JS
MC/SO
Highest
Highest
2.7 CONSTRUCTION TOPICS:
2.7.1 Pricing for raising floors in Bldgs G, H & J above 500 year flood:
11/19 GP: Sprinkler change estimate will be sent soon. Insulation
cost to follow. SO: We will review insulation detail for G,H,J. We
agreed on site today to 6” batt for M & K.
11/26 GP: Price for insulation sent for approval. Need answer to
keep construction moving. EK: Will provide.
12/03 GP: Received approval for insulation on M&K. Need
approval for insulation on G,H & J. FB: Ok.
12/10 GP: Approvals received. SO: At DP’s request, re-examining
need for sprinklers below the raised floors. Have NFPA section to
review w/BO. Reviewed w/AZT who agreed that it would apply.
12/17 SO: Reviewed w/BO after mtg who referred the issue to
the FM. SO to meet w/FM to resolve.
PBA/SO
Highest
2.7.2 Transformers/Eversource Coordination/Electric Meter location:
11/26 GP: Sent contact info to FB. Electrician has been calling
Eversource daily w/no response on receiving revised site layout.
12/03 GP: Same. FB: Have not called yet.
12/10 GP: Eversource returned Electrician’s call at the end of
last week & indicated that they are just starting to look at our
project.
12/17 Not reviewed.
2.7.3 Telephone/Cable lines:
11/19 EK: Waiting on proposal from Frontier. No luck yet
reaching local cable company.
11/26 EK: Same.
12/03 FB: Same.
12/10 Not reviewed.
12/17 EK: Same.
EK
High
2.7.4 Mechanical Work on Hold Until BO reviews Addendum 8:
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #19
12/17/2019
Page 8 of 8
12/10 GP: Mechanical can’t move forward until BO gives
approval. SO: I will check in w/BO today for new meeting date
which was to follow their review – our tentative meeting date
has passed.
3.0 CHANGE ORDERS
3.1 Status:
12/10, 12/17 Not reviewed.
4.0 REQUISITIONS
4.1 Status:
12/03, 12/10 Not reviewed.
12/17 Req is being processed & signed.
Alternating job site meetings/conference calls will be held weekly. Next up is a conference call at 10:30
am on December 23, 2019.
Recorded by Susan Odell, AIA, CPHC, Senior Project Architect, Paul B. Bailey Architect, LLC
These minutes are meant to convey & record the general content of the meeting, but do not represent a
verbatim recording. Please promptly respond to the Architect with any comments or questions.