Oxoboxo Lofts, Uncasville , CT
MEETING MINUTES #18
PROJECT: Oxoboxo Lofts
42 Pink Row
Uncasville, CT
DATE: December 10, 2019
TIME: 10:00 a.m.
LOCATION: Job Site
Present:
Eric Kuczarski (EK) DP EKuczarski@DakotaPartners.net
Frank Brachanow (FB) Dakota Partners (DP) FBrachanow@DakotaPartners.net
Gifford Perry (GP) MC Gifford@MaggioreCos.com
Peter Lentine (PL) MC Peter@MaggioreCos.com
Susan Odell (SO) Paul B. Bailey Architect (PBBA) SOdell@pbbarchitect.com
Sam Kirby (SK) PBBA SKirby@pbbarchitect.com
Frank Vacca (FV) BSC FVacca@BSCGroup.com
Pat Callahan (PC) AZT PCallahan@aztecheng.com
Dean Azzam (DA) Aztech Engineers, Inc. (AZT) DAzzam@aztecheng.com
Tim Carr (TC) Down To Earth Consulting (DTEC) Tim@DownToEarthConsulting.com
Dan Morrissey (DM) Morrissey Engineers (ME) daniel.morrissey@morrisseyengineers.com
Minutes to:
Paul Maggiore (PM) MC Paul@MaggioreCos.com
Dave Mann (DM) Maggiore Construction (MC) Dave@MaggioreCos.com
Karl Walsh DP KWalsh@DakotaPartners.net
Marc Daigle DP MDaigle@DakotaPartners.net
Roberto Arista (RA) DP RArista@DakotaPartners.net
Evan Fink (EF) DP EFink@DakotaPartners.net
Matt Abraham (MA) DP MAbraham@DakotaPartners.net
Alycia Quintiliani DP aquintiliani@dakotapartners.net
Bill Rundlett DP Brundlett@dakotapartners.net
Kurt Prochorena (KP) BSC Group (BSC) KProchorena@BSCGroup.com
Brandon Handfield (BH) Yantic River Consultants Brandon@yrc-ne.com
James Sexton (JS) SHPO/NPS Consultant jmbjcs@hotmail.com
CONSTRUCTION DATES: Dam Removal: Start Date: Oct 18, 2019 EST. End Date: Unknown
Lofts Construction: Start Date: August 1, 2019 End Date: November 1, 2020
Responsible
Party
Priority
Level
1.0 CONSTRUCTION SCHEDULE & PROGRESS
1.1 CONSTRUCTION SCHEDULE:
1.1.1 Status:
10/25 GP: Still behind schedule. Helical pile installation starts 10/28,
weather permitting.
11/01 GP: Same on schedule. Helical pile installation underway.
11/05, 11/12, 11/19, 11/26 Not reviewed.
12/03 GP: MC is at a standstill at several areas and cannot start
work and the construction schedule is being severely delayed due
to some of the following:
Plumbing design
AZT
HIGHEST
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #18
12/10/2019
Page 2 of 7
Bldg B floor
Bldg F structure & HVAC design
SHPO
RFI’s
Shop drawings submittals
Field reports
12/10 GP: Add waterproofing to the list above.
ME
PBA/ME/AZT
PBA/JC/MC
PBA/ME/AZT
/BSC
PBA/AZT
ME
PBA
HIGHEST
HIGHEST
HIGHEST
HIGHEST
HIGHEST
HIGHEST
HIGHEST
1.2 CONSTRUCTION PROGRESS:
1.2.1 Status:
12/10 GP: Insulating M underway. Have permit sign off for M & K.
Decking over those areas, starting walls soon after. J & G are
decked over & walls have started. Some plumbing at J & G
underway. Mason on site doing samples & washing. Starting A
knee walls next week. On hold on F & B.
2.0 CONSTRUCTION TOPICS
2.1 SITE/CIVIL TOPICS:
2.1.1 Site/Civil Submittals & RFI’s:
12/10 FV: Have CSK-001 95% ready which will answer RFI’s 27 &
28. Pending coordination w/GP, SO & answer from FM on FD
connection style (sent via email to FM yesterday).
BSC/FV
High
2.1.2 Encroachment Permit for Guardrail on Route 32:
12/10 FV: Have sketch to review w/Mayor (Traffic Authority) that
pulls our driveway just outside the ConDOT’s jurisdiction by
replacing the existing curb cut in its existing location. Mayor may
want the driveway to be entrance only. Eliminating sidewalk
connection to ConDOT jurisdiction (stopping it at the bus stop),
not touching the guardrail that is under ConDOT’s jurisdiction,
which will remove all of our work from ConDOT’s jurisdiction.
Have to confirm exact location of right of way w/surveyor. We will
not have to meet w/ConDOT if everything works out.
BSC/FV
Medium
2.1.3 Gas Company Coordination:
12/10 FV: Will issue CSK to show all gas lines that are going into
& out of Bldg F. SO to send AZT dwgs to FV.
SO & FV
Medium
2.1.4 FMC Application to DEEP:
12/03, 12/10 See consent order topic below.
2.1.5 Helical Pile Installation:
11/26 FV: How much work remains? GP: 2 days for helical piles, 1
or 2 weeks for grout bags. Helical pile contractor has asked when
they can come back. Do we know? FV: We do not know.
12/03, 12/10 Not reviewed.
2.1.6 Consent Order:
12/10 BH is finalizing remediation plan after MC review. Plan
shows helical piles to remain. PL: The plan gives us 5 days from
installation of silt fence to removing everything.
2.1.7 Grout Bag Submittal:
12/03 SO: Reviewed BH’s comments w/GP & Susan Weglein. GP:
We will resubmit the submittal.
12/10 Not reviewed.
MC/GP
Medium
2.1.8 Concrete site walls:
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #18
12/10/2019
Page 3 of 7
11/26 GP: There are many different site walls – cheek walls, etc.
We could be working on them if we had details. SK: Will send
Addendum 8 drawings for all changes to FV for his review. FV:
Landings, stairs & ramps for the raised floors were shown on our
drawings but not detailed.
12/03 FV: Part of RFI 27, will review w/GP today.
12/10 FV: Have some further questions on site walls to review
w/GP today.
BSC/FV
High
2.1.9 Bldg M basement access:
12/10 SO to send Addendum 8 dwgs showing new
Basement/Courtyard access to FV so he can work on site design
portion.
PBA/SO
High
2.2 ENVIRONMENTAL REMEDIATION TOPICS:
2.2.1 Environmental Submittals & RFI’s:
12/10 No RFI’s or submittals outstanding.
2.2.2 RAP Application to DEEP:
12/10 TC: Testing of buildings is almost complete. Data package
available but no formal submittal to the state. Will submit mid-
January. 1 sample in Bldg D has to be re-taken, scheduled for
tomorrow.
DTEC
High
2.2.3 Injection System: (related topic below: equipment in Bldg M
Basement)
11/05 TC: Still on hold. Winter will dictate the work – have to
pump 40k gallons of water into the ground. (Extended discussion
of where the water might come from) RA: Work on hold until
Dakota owns the property. TC: Process & results of injection
takes about 1 year.
11/12, 11/19, 11/26, 12/03 Not reviewed.
12/10 TC: Still on hold.
2.2.4 Abandoned Brownfield Application to DEEP:
10/25 TC: Working on DEEP sign-off, then DECD has to sign off.
Need approval before closing since we can’t get into that program
after purchase. FB: Anything we need to do? TC: Nothing for
construction – this is more legal. Had a call yesterday w/RA &
Attorney so process is moving forward.
11/01, 11/05, 11/12, 11/19, 11/26, 12/03,12/10 Not reviewed.
12/10 TC: Status uncertain.
2.2.5 SVE Equipment:
12/10 TC: Installed 4 soil vapor extraction wells last week. The
new SVE equipment (soil vapor extraction pump & controls) will
be brought in on a 4’x4’x6’ skid rig. Proposed to go in the
southeast corner of F. SK: That is where we show it. Be aware
that there is a raised floor in that area. TC: Ok.
2.2.6 Remediation in Courtyard:
12/10 TC: Removed 30 tons of soil from courtyard, took 15
samples, 1 exceeded. Tentatively scheduled to return tomorrow
pending weather.
DTEC
Medium
2.2.7 Transformers removed from Courtyard:
12/10 GP: Missing transformers were taken by the demo sub
because he thought it was part of his scope of work. The sub has
sent the necessary paperwork to TC. CLOSED.
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #18
12/10/2019
Page 4 of 7
2.2.8 Equipment in M Basement:
12/03 SO: RFI answer from Aztech remains outstanding.
12/10 SO: Same on RFI. TC: Equipment has to keep running over
the winter.
AZT
Highest
2.2.9 Contaminated soils under removed oil tank:
12/10 TC: Contaminated still removal tentatively scheduled for
tomorrow. FB: Scope? TC: We will excavate to 2 foot depth but
depth of actual contamination is somewhat unknown. Will test
soil that remains.
DTEC
High
2.2.10 12/10 TC: Need copies of all hazardous material removal reports
- Bill of ladens – for haz mat work done inside the buildings. GP:
Ok, will send.
MC/GP
Medium
2.3 STRUCTURAL TOPICS:
2.3.1 Structural Submittals & RFI’s:
12/10 DM: Reviewing record set of cold-formed metal framing-
will complete tomorrow. RFI-25 answered. RFI-31 sketch for Bldg
D will be issued today. Need info from PBA to answer Bldg B
portion of RFI-31 – will issue sketch on Bldg B tomorrow.
ME
Highest
2.3.2 Steel in Bldg F:
12/03 PC approved layout of equipment shown on architectural
floor plan, which will allow DM to complete their work. DM:
Should be completed by the end of the week.
12/10 DM: Sketches issued yesterday. CLOSED.
2.3.4 Special Inspections:
11/12 DM: Revised statement sent to DP. EK: SO, please issue via
an ASI. SO: Will do.
11/19, 11/26, 12/03 SO: Same.
12/10 SO: Issued ASI yesterday. CLOSED.
2.3.5 Bldg J:
12/10 Openings examined, photos taken. Approx 7 ft horizontal
distance from face of building under slab. DM: Not a concern
structurally. CLOSED.
2.3.6 Bldg B Floors:
12/10 DM: Sketches will be issued by Thursday.
ME
Highest
2.3.7 Poor condition of existing masonry arches in walls of J & H:
11/19 DM: Will review on site today & issue memo.
11/26 PL: Would like to install lintels & flat arch in wall that is in
the Laundry Rm in Bldg H. SO: Will review w/JS to determine
impact on SHPO approval.
12/03 DM: Issuing field report today.
12/10 DM: Field report issued.
PBA/SO
High
2.3.8 SKS for support for water heater tanks in Bldg H:
12/10 DM: Will issue by Thursday.
ME
Highest
Bldg B floor deflection:
12/10 GP: Will check w/sub on means & methods. DM: Sketches
will be issued ASAP. Will review base of columns in basement &
sub basement for potential rot.
2.4 MEP TOPICS:
2.4.1 MEP Submittals & RFI’s:
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #18
12/10/2019
Page 5 of 7
12/10 PC: Submittals for fire detection & alarm & hanger rods
returned. Overdue submittals: Pumps, tanks, heat exchanger;
Berto electric wall & unit heaters; VFD’s for pumps; Gas Generator
by Generac will be returned by 12/13. Plumbing fixtures & hot
water heaters will be returned by 12/18. Panel Boards & Load
Centers will be returned by 12/27. Outstanding but not overdue
submittals: Light fixtures & Media boxes are due on 12/17.
AZT
Highest
2.4.2 Ejector Pit Redesign/Elimination:
12/03 PC: Will have rough draft issued by end of week.
12/10 PC: Rough draft issued on Friday. For construction plumbing
dwgs will be issued by Dec 20 which will include all Addendum 8
design changes. New smaller ejector pump shown in Bldg B sub-
basement.
AZT/PC
Highest
2.4.3 Sprinkler System:
12/10 All Fire Protection updates will be handled in shop dwgs. No
revised FP dwgs will be issued. CLOSED.
2.4.4 Egress from Electrical Rooms:
11/19 SO: Elec Rm layout in D received. Waiting on official sign-off
from AZT that 1 egress from Bldg D Elec Rm is adequate. Will check
that I forwarded it to AZT.
11/26 PC: DA is working on this.
12/03, 12/10 PC: Same.
AZT/DA
Medium
2.5 ARCHITECTURAL TOPICS:
2.5.1 Architectural Submittals & RFI’s:
11/12 SO: RFI 18 will be issued by end of day tomorrow.
11/19 Exterior door construction reviewed w/GP. SO/SK: Will
issue RFI 18 ASAP.
11/26 SK: Will issue RFI 18 today.
12/03 RFI’s 10, 19, 21, 23, 24, 26, 28 outstanding. Submittals for
drywall & window shop dwgs outstanding.
12/10 SO: All outstanding RFI’s & submittals will be returned by
Dec. 20.
PBA
Highest
2.5.2 Updated package of drawings for permit:
12/10 SO: Stopped by BO’s office last Thursday & reviewed some
items. Set tentative mtg for Thursday of this week, pending their
confirmation. Prepping for the mtg by collating code issues
(including venting of space under Bldgs G, H,J)
PBA/SO
Highest
2.5.3 Flood Vents:
12/03 SK: Details underway.
12/10 Same.
PBA
Low
2.5.4 Existing Connections between B & D and D & E:
12/03 SK: Dwgs are ready to issue as soon as crash of connector
into window of Bldg B is resolved. We will review the site
condition today.
12/10 Same.
PBA/SK
Medium
2.5.5 Insulation & Waterproofing where Bldg K crosses the stream:
12/03 SO: Same. Insulation above the floor is limited at the river
crossing at Bldg K, so will definitely need some insulation below
the floor.
12/10 SO: Same.
PBA
Medium
2.5.6 Below grade waterproofing at A, B, C, D, F:
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #18
12/10/2019
Page 6 of 7
11/19 SO: Paul Bailey reviewed results of test pits & directed that
wall should be rebuilt from the exterior w/concrete. FB: Cost will
be extraordinary. Any other solution? Solution discussion
followed. DM/PBA to review/issue alternate solutions.
11/26 SO: Same. PL: In my absence, there has been backfill
against wall of G w/no waterproofing. SO: Should not put soil
against a brick wall where there was no soil before without
waterproofing. PL: Agreed, need waterproofing details.
12/03 PBA & ME reviewed solution after the meeting. PBA to
create dwgs to show solution.
12/10 SO: Same.
PBA
Highest
2.5.7 Mason’s mortar samples:
11/19 SO: Mason has samples installed on site but indicated that
they need additional washing before we review.
11/26, 12/03 Not reviewed.
12/10 Reviewed mason’s samples. Sample on M: color is good,
needs more washing to reveal more aggregate. Established 7
areas of brick color to submit to SHPO. Need to verify if there are
7 corresponding areas of mortar color (probably fewer). Mason
should prep samples for all mortar colors.
2.5.8 Existing windows in M and F:
11/26 SK: Details are almost complete – will issue ASAP.
12/03 SK: Getting missing details on site today.
12/10 SK: Same.
PBA
High
2.5.9 Toilet locations:
11/19 GP: Toilets on floor plans are off center in space btwn wall
& vanity. We need this ASAP as plumber is doing layout now.
SK: Center line of toilet should be 1’-6” off the wall, typ. SO:
We will review why they are showing off center.
11/26 SK: Will review areas between walls & vanities to make
sure they are all at least 3 ft wide, & will return RFI.
12/03 SK: Will return RFI today.
12/10 RFI returned. CLOSED.
2.5.10 Gutters:
11/19 SO: We show gutters on all buildings but they go to splash
blocks, not to underground drainage system. Could be cost
savings to eliminate them in areas, such as courtyard. We would
keep them where drainage is a problem, such as around Bldg C.
EK: Please review where elimination is possible.
11/26, 12/03, 12/10 SO: Same
PBA
Low
2.5.11 Unit K4:
12/10 SO: Dwg issued as ASK-03. CLOSED.
2.5.12 Bldg B “Attic” triangle:
12/03 GP: BO says that the area qualifies as an attic & will need
sprinklers. SO: We will review.
12/10 SO: Review in process. Solution of moving knee wall back
reviewed.
PBA/SO
High
2.6 SHPO APPROVALS
2.6.1 NPS Approval of Roofing Details:
11/26 GP: Fascia board was painted. SO: Will go to site to
photograph completed roof mock-up & send to JS for review.
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #18
12/10/2019
Page 7 of 7
12/03 SO: Photos taken, noticed that the existing edge material
is taller than the new edge – might give us some extra height for
insulation.
12/10 SO: Need access to roof mock-up to measure the existing
metal edge.
PBA/JS
MC/SO
Highest
Highest
2.7 CONSTRUCTION TOPICS:
2.7.1 Pricing for raising floors in Bldgs G, H & J above 500 year flood:
11/19 GP: Sprinkler change estimate will be sent soon. Insulation
cost to follow. SO: We will review insulation detail for G,H,J. We
agreed on site today to 6” batt for M & K.
11/26 GP: Price for insulation sent for approval. Need answer to
keep construction moving. EK: Will provide.
12/03 GP: Received approval for insulation on M&K. Need
approval for insulation on G,H & J. FB: Ok.
12/10 GP: Approvals received. SO: At DP’s request, re-examining
need for sprinklers below the raised floors. Have NFPA section to
review w/BO. Reviewed w/AZT who agreed that it would apply.
PBA/SO
Highest
2.7.2 Transformers/Eversource Coordination/Electric Meter location:
11/26 GP: Sent contact info to FB. Electrician has been calling
Eversource daily w/no response on receiving revised site layout.
12/03 GP: Same. FB: Have not called yet.
12/10 GP: Eversource returned Electrician’s call at the end of
last week & indicated that they are just starting to look at our
project.
2.7.3 Telephone/Cable lines:
11/19 EK: Waiting on proposal from Frontier. No luck yet
reaching local cable company.
11/26 EK: Same.
12/03 FB: Same.
12/10 Not reviewed.
EK
High
2.7.4 Hiring of Testing Agency:
11/19 EK: Received 2 quotes, will hire one.
11/26 EK: Waiting on add’l quote but can sign up Materials
Testing if needed. GP: Yes, please sign up Materials Testing.
12/03 FB: Will follow up.
12/10 EK: Testing agency hired. CLOSED.
3.0 CHANGE ORDERS
3.1 Status:
12/10 Not reviewed.
4.0 REQUISITIONS
4.1 Status:
12/03, 12/10 Not reviewed.
Alternating job site meetings/conference calls will be held weekly. Next up is a site meeting at 10:00 am
on December 17, 2019.
Recorded by Susan Odell, AIA, CPHC, Senior Project Architect, Paul B. Bailey Architect, LLC
These minutes are meant to convey & record the general content of the meeting, but do not represent a
verbatim recording. Please promptly respond to the Architect with any comments or questions.