HomeMy WebLinkAbout2019-12-03 Oxoboxo Mtg Min 17#16-063
Oxoboxo Lofts, Uncasville , CT
MEETING MINUTES #17
PROJECT: Oxoboxo Lofts
42 Pink Row
Uncasville, CT
DATE: December 3, 2019
TIME: 10:00 a.m.
LOCATION: Job Site
Present:
Frank Brachanow (FB) Dakota Partners (DP) FBrachanow@DakotaPartners.net
Susan Odell (SO) Paul B. Bailey Architect (PBBA) SOdell@pbbarchitect.com
Gifford Perry (GP) MC Gifford@MaggioreCos.com
Sam Kirby (SK) PBBA SKirby@pbbarchitect.com
Frank Vacca (FV) BSC FVacca@BSCGroup.com
Pat Callahan (PC) AZT PCallahan@aztecheng.com
Dan Morrissey (DM) Morrissey Engineers (ME) daniel.morrissey@morrisseyengineers.com
Minutes to:
Paul Maggiore (PM) MC Paul@MaggioreCos.com
Dave Mann (DM) Maggiore Construction (MC) Dave@MaggioreCos.com
Karl Walsh DP KWalsh@DakotaPartners.net
Marc Daigle DP MDaigle@DakotaPartners.net
Roberto Arista (RA) DP RArista@DakotaPartners.net
Evan Fink (EF) DP EFink@DakotaPartners.net
Matt Abraham (MA) DP MAbraham@DakotaPartners.net
Alycia Quintiliani DP aquintiliani@dakotapartners.net
Bill Rundlett DP Brundlett@dakotapartners.net
Kurt Prochorena (KP) BSC Group (BSC) KProchorena@BSCGroup.com
Dean Azzam (DA) Aztech Engineers, Inc. (AZT) DAzzam@aztecheng.com
Brandon Handfield (BH) Yantic River Consultants Brandon@yrc-ne.com
Peter Lentine (PL) MC Peter@MaggioreCos.com
Tim Carr (TC) Down To Earth Consulting (DTEC) Tim@DownToEarthConsulting.com
Eric Kuczarski (EK) DP EKuczarski@DakotaPartners.net
James Sexton (JS) SHPO/NPS Consultant jmbjcs@hotmail.com
CONSTRUCTION DATES: Dam Removal: Start Date: Oct 18, 2019 EST. End Date: Unknown
Lofts Construction: Start Date: August 1, 2019 End Date: November 1, 2020
Responsible
Party
Priority
Level
1.0 CONSTRUCTION SCHEDULE & PROGRESS
1.1 CONSTRUCTION SCHEDULE:
1.1.1 Status:
10/25 GP: Still behind schedule. Helical pile installation starts 10/28,
weather permitting.
11/01 GP: Same on schedule. Helical pile installation underway.
11/05, 11/12, 11/19, 11/26 Not reviewed.
12/03 GP: MC is at a standstill at several areas and cannot start
work and the construction schedule is being severely delayed due
to some of the following:
Plumbing design
AZT
HIGHEST
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #17
12/03/2019
Page 2 of 9
Bldg B floor
Bldg F structure & HVAC design
SHPO
RFI’s
Shop drawings submittals
Field reports
PBA/ME
PBA/ME/AZT
PBA/JC/MC
PBA/ME/AZT
/BSC
PBA/AZT
ME
HIGHEST
HIGHEST
HIGHEST
HIGHEST
HIGHEST
HIGHEST
1.2 CONSTRUCTION PROGRESS:
1.2.1 Status:
11/19 GP: New wood framing over existing wood floor underway
in M. New metal knee wall framing underway in J and G. Demo
of existing wood below knee walls underway. Washing of
exterior masonry underway. Plumber doing layout. Sandblasting
complete.
11/26 GP: Need answer on insulation below raised floor in M & K
to keep construction moving; currently at a standstill. EK: Will
review w/Peter Harding to get answer today.
12/03 Not reviewed.
2.0 CONSTRUCTION TOPICS
2.1 SITE/CIVIL TOPICS:
2.1.1 Site/Civil Submittals & RFI’s:
11/12 FV: All submittals returned this morning via 2 emails. RFI for
site walls – will highlight their location on a site plan & send so it
can be sent to Structural or Geotech Engineer & reviewed for any
SHPO impact.
11/19 FV: Site plan for site walls sent to PBA.
11/26 FV: Reviewing RFI 27 & 28 now. GP: We can modify the RFI
27 #1 for drainage behind Bldg G – we should discuss after the call.
We need answers for #5 today.
12/03 FV: Returned draft of RFI 27 to GP today. Will work on them
today on site. Still looking into RFI 28. GP: Moving water line back
to west side of Bldg B. RFI 28 moves to PBBA to respond to interior
changes to Bldg B Subbasement. SO to forward GP’s sketch to FV
& PC.
PBA/SO
BSC/FV
Medium
High
2.1.2 Encroachment Permit for Guardrail on Route 32:
11/12 FV: Tentative meeting on Thursday w/ConDot but will likely
cancel it because we have a way to solve the problem that will
eliminate the need for an encroachment permit all together.
Revising the entrance to keep it where it is. FB: What about
guardrail? FV: It may be able to be removed because it was to
protect against falling into the raceway, but the raceway was
since filled in.
11/19 FV: Looking into alternate entrance design.
11/26 FV: Getting more info on the right of way.
12/03 FV: Same.
BSC/FV
Medium
2.1.3 Gas Company Coordination:
11/26 PC: Walked site w/Mike last week. High pressure welded
steel connection to handle 199 psi high pressure will remain. He
wanted to move our connection that drops it to 20 psi closer to
this. FV: It can move wherever he wants it to. PC: Mike will send
info on meter assembly. AZT to send layout of gas lines to him.
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #17
12/03/2019
Page 3 of 9
Have to look at lines coming from Bldg F back out to the 2
generators & the boilers in B & H. Can we send lines
underground to B between F & G & F & C? FV: All concrete in
that area is being replaced so the lines can go underground. PC:
If we can move boilers closer to the south in B sub-basement, it
would minimize the gas lines & vent lines. GP: Let’s review
layout of B sub-basement on site next week.
12/03 FV: Sent latest utility plan draft to PC yesterday. Change
was modifying connection to existing gas service – removed
about 100’ of piping.
AZT Medium
2.1.4 FMC Application to DEEP:
11/05 RA: Consent order has put a hold on the FMC application.
Consent order will take a couple of weeks to issue & get
approved. New estimate is January for approval of FMC.
11/12 FV: Coordinating with BH – he now has our temporary
hydraulic model for interim condition to submit to DEEP.
11/19 FV: DEEP has latest information. Awaiting response.
11/26 FV: Same.
12/03 FV: See consent order topic below.
2.1.5 Helical Pile Installation:
11/05 Work stopped. See consent order topic below.
11/12, 11/19 Same.
11/26 FV: How much work remains? GP: 2 days for helical piles, 1
or 2 weeks for grout bags. Helical pile contractor has asked when
they can come back. Do we know? FV: We do not know.
12/03 Not reviewed.
2.1.6 Consent Order:
11/26 FV: BH did submit to DEEP. Waiting for DEEP’s review. They
should respond ASAP because it is currently in violation.
11/27 SO phone w/BH: BH: Submitted our information to DEEP on
Nov. 14. Legal side of DEEP is involved – might come from AG’s
office.
12/03 FV: Notice of violation was filed, submitted to Dakota & GC
on Nov. 27. Requested remediation plan to be due Nov. 27 –
worked w/BH on some items. Don’t know if it was submitted
yesterday.
2.1.7 Grout Bag Submittal:
11/26 SO: Will follow up w/BH.
11/27 SO phone w/BH: BH: Grout bag submittal was sent to me
before DEEP issue. When I was on site for the DEEP issue, I
discussed w/Susan Weglein from Schumack changes needed to
grout bag submittal, and am expecting to receive an updated
submittal. I would approve materials only on the submittal but
until DEEP issue is worked out, I don’t want to sign anything
indicating that I am approving the work to be done.
12/03 SO: Reviewed BH’s comments w/GP & Susan Weglein. GP:
We will resubmit the submittal.
MC/GP
Medium
2.1.8 Concrete site walls:
11/26 GP: There are many different site walls – cheek walls, etc.
We could be working on them if we had details. SK: Will send
Addendum 8 drawings for all changes to FV for his review. FV:
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #17
12/03/2019
Page 4 of 9
Landings, stairs & ramps for the raised floors were shown on our
drawings but not detailed.
12/03 FV: Part of RFI 27, will review w/GP today.
BSC/FV
High
2.2 ENVIRONMENTAL REMEDIATION TOPICS:
2.2.1 Environmental Submittals & RFI’s:
12/03 No RFI’s or submittals outstanding.
2.2.2 RAP Application to DEEP:
11/05 TC: Results of soil vapor readings inside other buildings
should arrive next Monday. Have to test building B when it is
available – it was under containment at the time we tested.
11/12 Testing Bldg B is still pending completion of abatement.
11/19 Not reviewed.
11/26 PL: To my knowledge, TC has tested Bldg B.
12/03 Not reviewed.
DTEC
High
2.2.3 Injection System: (related topic below: equipment in Bldg M
Basement)
11/05 TC: Still on hold. Winter will dictate the work – have to
pump 40k gallons of water into the ground. (Extended discussion
of where the water might come from) RA: Work on hold until
Dakota owns the property. TC: Process & results of injection
takes about 1 year.
11/12, 11/19, 11/26, 12/03 Not reviewed.
2.2.4 Abandoned Brownfield Application to DEEP:
10/25 TC: Working on DEEP sign-off, then DECD has to sign off.
Need approval before closing since we can’t get into that program
after purchase. FB: Anything we need to do? TC: Nothing for
construction – this is more legal. Had a call yesterday w/RA &
Attorney so process is moving forward.
11/01, 11/05, 11/12, 11/19, 11/26, 12/03 Not reviewed.
2.2.5 SVE Equipment:
11/05 RA: Owner does not want to fit out Bldg F in the future. TC
to issue specs on the new SVE equipment that will be installed so
that Aztech can supply power.
11/12 SO: TC sent electrical requirements for SVE equipment,
will forward to AZT.
11/19 SO: Sent electrical requirements to AZT, asked TC for sizes
of equipment.
11/26 PL: TC will be on site Friday to resolve what goes under the
floor of J.
12/03 Not reviewed.
DTEC
Medium
2.2.6 Remediation in Courtyard:
11/12 PL: TC’s work in the courtyard is done but pile of soil
remains in the parking lot.
11/19 Not reviewed.
11/26 PL: How long will pile of soil in parking lot be on site?
12/03 Not reviewed.
DTEC
Medium
2.2.7 Transformers removed from Courtyard:
11/05 TC: Transformers have disappeared. They were empty &
there were no PCB’s in the soil below them. I prep the final
environmental sign-offs and I will indicate in that reporting that
they were stolen but that they did not contain hazardous
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #17
12/03/2019
Page 5 of 9
material. PM: Do we need a police report? RA: Should have a
report. TC should request it.
11/12, 11/19, 11/26, 12/03 Not reviewed.
DTEC
Medium
2.2.8 Equipment in M Basement:
11/19 GP: RFI issued with electrical requirements noted. SO:
Forwarded RFI to AZT.
11/26 Not reviewed.
12/03 SO: RFI answer from Aztech remains outstanding.
2.2.9 Contaminated soils under removed oil tank:
11/26 PL: TC indicates that the soils are contaminated. He will be
here Friday – will ask him the procedure for removal.
12/03 Not reviewed.
2.3 STRUCTURAL TOPICS:
2.3.1 Structural Submittals & RFI’s:
11/26 GP: Please return the steel shops that are still relevant. SK:
Will do.
12/03 DM: Will issue field report on arches in Bldgs H & J. GP: RFI’s
24, 25 & 31 are outstanding.
ME
High
2.3.2 Steel in Bldg F:
12/03 PC approved layout of equipment shown on architectural
floor plan, which will allow DM to complete their work. DM:
Should be completed by the end of the week.
ME
High
2.3.3 Helical Pile Installation:
11/05 DM: Will need a final submittal on the helical piles that is
the logs for installation. GP: Noted.
11/12 GP: Will have the final submittal soon.
11/19 GP: Same.
11/26 GP: Logs sent to DM this week.
12/03 See topic under site topics. CLOSED.
2.3.4 Special Inspections:
11/12 DM: Revised statement sent to DP. EK: SO, please issue via
an ASI. SO: Will do.
11/19, 11/26, 12/03 SO: Same.
PBA/SO
High
2.3.5 Bldg J:
11/05 PL: Discovered 2 openings under the slab on the courtyard
wall that had been covered by plants. Have photo but cannot
currently access them.
11/12 On hold until we have access to the creek side of Bldg J.
11/19, 11/26, 12/03 Same.
12/03 SO: We should try to investigate since we are framing the
floors in J now, in case it involves any work to the slab. GP: Will
see if we can put some ladders at a window to access the area.
DM: If the openings are deep, will need to use confined spaces
rules, which involve oxygen tanks, etc.
MC/ME
High
2.3.6 Bldg B Floors:
12/03 Reviewed after meeting – decision to put sleepers under
plywood where the depth of gypcrete would exceed 3”, to limit
the depth of gypcrete to 3”. PBA to check floor to ceiling heights,
revise #’s so all are negative from zero, identify areas that would
need sleepers, and send to ME.
PBA
High
2.3.7 Poor condition of existing masonry arches in walls of J & H:
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #17
12/03/2019
Page 6 of 9
11/19 DM: Will review on site today & issue memo.
11/26 PL: Would like to install lintels & flat arch in wall that is in
the Laundry Rm in Bldg H. SO: Will review w/JS to determine
impact on SHPO approval.
12/03 DM: Issuing field report today.
PBA/SO
ME
High
High
2.4 MEP TOPICS:
2.4.1 MEP Submittals & RFI’s:
11/26 PC: Returned several submittals yesterday. Released
boilers, still holding pumps due to redesign. GP: Gear submittals
will be issued soon.
12/03 GP: RFI’s 20 & 30 outstanding. Some submittals are getting
significantly behind – need to catch up on those.
AZT
High
2.4.2 Ejector Pit Redesign/Elimination:
12/03 PC: Will have rough draft issued by end of week.
AZT/PC
Highest
2.4.3 Sprinkler System:
12/03 PC: Will update dwgs for Bldg A closet. Will handle dry
system under floor of Bldg J in shop dwgs.
AZT/PC
Medium
2.4.4 Egress from Electrical Rooms:
11/19 SO: Elec Rm layout in D received. Waiting on official sign-off
from AZT that 1 egress from Bldg D Elec Rm is adequate. Will check
that I forwarded it to AZT.
11/26 PC: DA is working on this.
12/03 PC: Same.
AZT/DA
Medium
2.5 ARCHITECTURAL TOPICS:
2.5.1 Architectural Submittals & RFI’s:
11/12 SO: RFI 18 will be issued by end of day tomorrow.
11/19 Exterior door construction reviewed w/GP. SO/SK: Will
issue RFI 18 ASAP.
11/26 SK: Will issue RFI 18 today.
12/03 RFI’s 10, 19, 21, 23, 24, 26, 28 outstanding. Submittals for
drywall & window shop dwgs outstanding.
PBA
Highest
2.5.2 Updated package of drawings for permit:
11/19 FB: PBA, pls send 3 sets to BO, 1 set to FB. BO sets need live
stamps on cover page only. SO: We will send by end of week.
11/26 SO: Delay in sending. Circulating cover page now for wet
stamps. Will deliver sets of dwgs to BO next Tuesday. FB: Please
call the BO to let him know, & resolve issue of venting and/or
conditioning crawl space of G. SO: Will do.
12/03 SO: Delivering 3 sets of dwgs to BO today. Leaving 1 set for
FB in trailer.
PBA/SO
Highest
2.5.3 Flood Vents:
12/03 SK: Details underway.
PBA
Low
2.5.4 Existing Connections between B & D and D & E:
12/03 SK: Dwgs are ready to issue as soon as crash of connector
into window of Bldg B is resolved. We will review the site
condition today.
PBA/SK
Medium
2.5.5 Insulation & Waterproofing where Bldg K crosses the stream:
12/03 SO: Same. Insulation above the floor is limited at the river
crossing at Bldg K, so will definitely need some insulation below
the floor.
PBA
Medium
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #17
12/03/2019
Page 7 of 9
2.5.6 Below grade waterproofing at A, B, C, D, F:
11/19 SO: Paul Bailey reviewed results of test pits & directed that
wall should be rebuilt from the exterior w/concrete. FB: Cost will
be extraordinary. Any other solution? Solution discussion
followed. DM/PBA to review/issue alternate solutions.
11/26 SO: Same. PL: In my absence, there has been backfill
against wall of G w/no waterproofing. SO: Should not put soil
against a brick wall where there was no soil before without
waterproofing. PL: Agreed, need waterproofing details.
12/03 PBA & ME reviewed solution after the meeting. PBA to
create dwgs to show solution.
PBA
High
2.5.7 Mason’s mortar samples:
11/19 SO: Mason has samples installed on site but indicated that
they need additional washing before we review.
11/26, 12/03 Not reviewed.
2.5.8 Existing windows in M and F:
11/26 SK: Details are almost complete – will issue ASAP.
12/03 SK: Getting missing details on site today.
PBA
High
2.5.9 Toilet locations:
11/19 GP: Toilets on floor plans are off center in space btwn wall
& vanity. We need this ASAP as plumber is doing layout now.
SK: Center line of toilet should be 1’-6” off the wall, typ. SO:
We will review why they are showing off center.
11/26 SK: Will review areas between walls & vanities to make
sure they are all at least 3 ft wide, & will return RFI.
12/03 SK: Will return RFI today.
PBA/SK
High
2.5.10 Gutters:
11/19 SO: We show gutters on all buildings but they go to splash
blocks, not to underground drainage system. Could be cost
savings to eliminate them in areas, such as courtyard. We would
keep them where drainage is a problem, such as around Bldg C.
EK: Please review where elimination is possible.
11/26, 12/03 SO: Same
PBA
Low
2.5.11 Unit K4:
11/26 FB: Please look at flipping unit K4 so bathroom is not over
the river. SK: Will do.
12/03 SK: Revised unit layout reviewed w/GP & Plumber prior to
meeting. Layout is approved – will issue dwgs.
PBA/SK
High
2.5.12 Bldg B “Attic” triangle:
12/03 GP: BO says that the area qualifies as an attic & will need
sprinklers. SO: We will review.
PBA/SO
High
2.6 SHPO APPROVALS
2.6.1 NPS Approval of Roofing Details:
11/26 GP: Fascia board was painted. SO: Will go to site to
photograph completed roof mock-up & send to JS for review.
12/03 SO: Photos taken, noticed that the existing edge material
is taller than the new edge – might give us some extra height for
insulation.
PBA/JS
Highest
2.7 CONSTRUCTION TOPICS:
2.7.1 Pricing for raising floors in Bldgs G, H & J above 500 year flood:
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #17
12/03/2019
Page 8 of 9
11/19 GP: Sprinkler change estimate will be sent soon. Insulation
cost to follow. SO: We will review insulation detail for G,H,J. We
agreed on site today to 6” batt for M & K.
11/26 GP: Price for insulation sent for approval. Need answer to
keep construction moving. EK: Will provide.
12/03 GP: Received approval for insulation on M&K. Need
approval for insulation on G,H & J. FB: Ok.
2.7.2 Transformers/Eversource Coordination/Electric Meter location:
11/26 GP: Sent contact info to FB. Electrician has been calling
Eversource daily w/no response on receiving revised site layout.
12/03 GP: Same. FB: Have not called yet.
MC
High
2.7.3 Telephone/Cable lines:
11/19 EK: Waiting on proposal from Frontier. No luck yet
reaching local cable company.
11/26 EK: Same.
12/03 FB: Same.
EK
High
2.7.4 Hiring of Testing Agency:
11/19 EK: Received 2 quotes, will hire one.
11/26 EK: Waiting on add’l quote but can sign up Materials
Testing if needed. GP: Yes, please sign up Materials Testing.
12/03 FB: Will follow up.
EK
High
2.7.5 Masonry add’l scope – T & M:
11/12 GP: Many poor existing conditions – can we proceed T&M
on the repairs? FB: I want to review the scope on site.
11/19 FB: Same.
11/26 FB: Will review today.
12/03 FB: Verbal approval given. CLOSED.
MC/FB
High
2.7.6 RFI, Submittal, Sketch, Change Estimate & Change Order Logs:
11/26 FB: Logs received. Will post logs on Egnyte site.
12/03 CLOSED.
2.7.7 Next Site Meeting:
11/26 EK: There are a lot of issues to resolve on site next week.
Need all consultants there & plan to be there all day.
12/03 CLOSED.
BSC/DTEC/
ME/AZT/
PBA/DP/MC
High
3.0 CHANGE ORDERS
3.1 Status:
11/26 GP: No update.
12/03 GP: FB, please sign off on sprinkler change estimate #14.
FB: Ok.
4.0 REQUISITIONS
4.1 Status:
11/26 GP: No update.
12/03 Not reviewed.
Alternating job site meetings/conference calls will be held weekly. Next up is a site meeting at 10:00 am
for GC, Owner & Architect, followed by Aztech at 11am, Morrissey Engineers at 1pm and BSC at 2pm on
December 10, 2019.
Recorded by Susan Odell, AIA, CPHC, Senior Project Architect, Paul B. Bailey Architect, LLC
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #17
12/03/2019
Page 9 of 9
These minutes are meant to convey & record the general content of the meeting, but do not represent a
verbatim recording. Please promptly respond to the Architect with any comments or questions.