HomeMy WebLinkAbout2019-09-06 Oxoboxo Mtg Min 04#16-063
Oxoboxo Lofts, Uncasville , CT
MEETING MINUTES #04
PROJECT: Oxoboxo Lofts
42 Pink Row
Uncasville, CT
DATE: September 6, 2019
TIME: 9:00 a.m.
LOCATION: Conference Call
Present:
Frank Brachanow (FB) DP FBrachanow@DakotaPartners.net
Susan Odell (SO) Paul B. Bailey Architect (PBBA) SOdell@pbbarchitect.com
Sam Kirby (SK) PBBA SKirby@pbbarchitect.com
Dave Mann (DM) Maggiore Construction (MC) Dave@MaggioreCos.com
Gifford Perry (GP) MC Gifford@MaggioreCos.com
Peter Lentine (PL) MC Peter@MaggioreCos.com
Matt Abraham (MA) DP MAbraham@DakotaPartners.net
Frank Vacca (FV) BSC FVacca@BSCGroup.com
Tim Carr (TC) Down To Earth Consulting Tim@DownToEarthConsulting.com
Minutes to:
Dean Azzam Aztech Engineers, Inc. DAzzam@aztecheng.com
Patrick Callahan Aztech Engineers, Inc. PCallahan@aztecheng.com
Dan Morrissey Morrissey Engineers daniel.morrissey@morrisseyengineers.com
Karl Walsh DP KWalsh@DakotaPartners.net
Roberto Arista DP RArista@DakotaPartners.net
Marc Daigle DP MDaigle@DakotaPartners.net
Evan Fink DP EFink@DakotaPartners.net
Alycia Quintiliani DP aquintiliani@dakotapartners.net
Kurt Prochorena (KP) BSC Group (BSC) KProchorena@BSCGroup.com
Scott Shaw (SS) Dakota Partners (DP) SShaw@DakotaPartners.net
Bill Rundlett DP Brundlett@dakotapartners.net
CONSTRUCTION DATES: Dam Removal: EST. Start Date: Sept 16, 2019 EST. End Date: Sept 24, 2019
Lofts Construction: Start Date: August 1, 2019 End Date: November 1, 2020
1.0 CONSTRUCTION PROGRESS & SCHEDULE
1.1 Dam Removal Construction Schedule:
08/16 SS: Dam removal start range: August 21-29, 2019, with end range of August 29-
Sept 10. KP: Should be 7 business days total construction time, max 2 weeks.
08/30 FB: Recent rain has impacted the site. Construction start Sept. 3 anticipated if
materials arrive on time. FV: Construction delay until week after next at the earliest due
to DEEP notifications that still need to be done.
09/06 FV: Now is still the best time for dam removal, even with current increased flows
through the dam. If a decision is made to wait, it would have to wait until next August, as
spring is not a good time to do the work. DEEP FMC application is hinging on the fact that
the dam is being removed – don’t know how that would be affected if dam is not removed
this year. FB: The site is currently like Lake Superior – absolutely impossible to work now.
What is the time frame limitation on the current period? FV: Freeze.
1.2 Lofts Construction Schedule:
08/23 FB: Partial Permit issued for selective work. SS: Received Owner’s consent for
early access yesterday. SS: If everything goes according to plan, will pull full permit just
after closing around end of October. DM: Will mobilize & start on Monday.
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #04
09/06/2019
Page 2 of 7
09/06 FB: Lofts construction schedule end date was Sept 1, 2020 at Bank’s request. It is
now Nov 1, 2020 & the Bank is aware of this. GP: The restriction for demo only right now
is delaying the schedule. GP: Status of full building permit? FB: At least 4 weeks out.
1.3 Construction Progress:
09/06 GP: Working on demo & abatement in Bldgs M & K. Have approval from Fire Dept.
to isolate the building sprinkler systems from the (4) existing on-site fire hydrants so demo
of the building sprinkler systems can begin. That work is starting tomorrow. Smoke
stack/chimney repair contractor has started this week. Will be installing transformer on
Monday, then disconnecting permanent power & connecting to temp power early next
week.
MA: GP, please put all scheduled work in an email to be courteous to the Owner – want
to try to avoid the issues that arose around sprinkler demo in the future. SO: Do you have
an overall construction schedule &/or 3-week look ahead that you can start sharing for
these calls? GP: Yes.
2.0 CONSTRUCTION TOPICS
2.1 Dam Removal:
08/30 FB: Tuesday, it was a puddle. Today there is a significant amount of water. FV:
Regardless of rain, still items that contractor (Bill Pineas, Owner) needs to take care with
DEEP – submitting the online commencement of work – has to be done 7 days prior. Still
pulling in DEEP Dam Safety – have to have conversation with them. FB: Tuesday’s meeting
satisfied Steve’s notification requirements. FV: Yes but there is additional notification that
is needed. MA: Notification should go out on Tuesday. FV: MA, you should be able to do
it and cc Bill. It is a standard email directly to the DEEP line.
09/06 MA: Heard back from Bill – materials – piping - should be in in a week & ½. He is
working on schedule for work to be performed. FB: Is 30” pipe that is being ordered big
enough? FV: Will have to look into it. Upsizing the pipe will not help us if it will not fit
through the sluice.
2.2 Dam Removal, SHPO:
08/16 SS: James Sexton is submitting National Historic Register designation today to
Jenny Scofield at SHPO to be on Sept. Board agenda. Jenny has asked James to indicate
that the dam removal work will be done & to take photos & document after the dam is
removed so Jenny can write an amendment. FB: There is an outstanding SHPO request to
salvage 1 or 2 stones from the dam and relocate to our site & put a sign marker on them.
KP: I will follow up. If this is not on the drawings, we will suggest placement on the site.
08/23 FV: Do we need to salvage the lift gate gear? SO: No SHPO only asked that 1 or 2
stones be salvaged. SS: Everything submitted to Jenny, on agenda for Sept 20 for national
and state designation. James will document dam conditions once removal is completed
& send to Jenny before Sept 20.
08/30 SO: Delay in construction start will push tight against the timeline outlined above.
09/06 SO: Will notify James Sexton that dam removal will not occur in the anticipated
time frame.
2.3 RFI MC 001 - Access to Courtyard at Bldgs H, J, K, M:
08/16 SO: EF/PBB made decision during design to not have access through building into
the courtyard, based on the fact that someone could walk in under the bridges across the
stream. EF recently confirmed that this decision stands. GP/FB: Access under the bridges
is very limited – low headroom & slippery on the rocks. DM: We will provide whatever
access is needed during construction. The issue is permanent access after construction.
SO: Will put this topic on hold for now & revisit further into construction.
08/23, 08/30 Same.
09/06 SO: Topic remains on hold. GP: Why? SO: Technically, the Owner answered no to
the RFI so we could close it, but holding it open due to GP/FB starting that some type of
permanent access is needed. FB: Correct. If PBBA could sketch out something for review,
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #04
09/06/2019
Page 3 of 7
that would get a conversation going with the Owner. GP: Construction plan is to find a
convenient window opening to open up to the floor. Everyone needs to get in there –
remediation, window, site. PL: Creating temp access at top of existing ramp that will be
demo’d at the J/M connector. Currently there is a fire hydrant in the courtyard now but
it will not be used in the long term.
2.4 RFI MC 002 Method of construction for raising floors in Bldgs G, H & J above 500 year flood:
08/16 SO: Pending because SHPO wants the floors raised with wood framing, not
structural fill & concrete slab. Have asked Jeff Caiola at DEEP whether flood vents will be
needed in the walls along G and J & waiting for response. If flood vents are needed, this
needs to be communicated to SHPO because their decision might change. As soon as we
have this answer, drawings will be issued.
08/23 SO: Significant progress has been made, but still waiting for final resolution of
direction from SHPO/DEEP. Will answer ASAP.
08/30 SO: SHPO is almost ready to approve. Will issue drawings after approval.
09/06 SK: Sent drawings to Structural Engineer. GP: When will I have structural
drawings? SK: Will check with Engineer & give schedule.
2.5 RFI MC 003 Gas Company questions:
08/16 GP: We need this info to move forward with the gas company. SO: relative priority?
GP: Medium. SO: Will follow up with Aztech on status.
08/23 SK: Forwarded to Aztech on 7/29, no response to date. SO: We will have a call
with Aztech ASAP to review all of their outstanding items.
08/30 SO: DA reported that the gas company told him there are 2 lines – 1 has low
pressure which we can’t use. 2nd one has very high pressure – we would use this line but
will need regulators. DA wants to regulate at the meter. DM: Where are these 2 gas lines?
SO: Don’t know, didn’t discuss that w/DA.
09/06 FV: Need to follow up w/DA. SO: I can facilitate a conference call w/DA. FV: Yes,
would be good after next Tuesday.
2.6 RFI MC 004 Bldg M Basement:
08/16 GP/DM: We have several questions – details for closing off existing access, where
is new access & details for it, HVAC needed, moisture issues when envelope is tightened
up, environmental equipment remaining? SO/SK: New access via exterior stair on south
side of Bldg M is shown on the site drawings. We will follow up on other issues.
08/23 SO: Answering this is now contingent on the SHPO/DEEP resolution. Will answer
ASAP.
08/30 SO: SHPO is almost ready to approve, will answer RFI after their approval. In DEEP
application, requested exemption from NFIP requirement to fill basement based on
historical status. Did not mention the existing environmental equipment in this
application.
09/06 SO: We will start reviewing these questions.
2.7 Environmental Equipment in Bldg M Basement:
08/16 SS/TC: Equipment is currently functioning but scheduled to be shut off around
October. Then 1 or 2 rounds of soil injections will be performed on ???schedule.
Depending on results of soil injections, equipment may have to be turned back on, so it
must remain in basement until this is known. FB/DM/GP: Questions include: does it need
an enclosure &/or HVAC &/or acoustical isolation since it is quite loud. SO/SK: Also it is
below the flood elevation – don’t want DP to get to CO status & find out that it is not
allowed to be there. SS: All understood, but we will hold on this issue for now.
08/23 SO: SHPO/DEEP resolution could affect the location of this equipment, but the
goal is to leave it in place.
08/30 Same.
09/06 SO: Same issues of acoustics and being below the BFE if equipment has to be run
after occupancy. TC: No intent to run the equipment again after we shut it off, but should
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #04
09/06/2019
Page 4 of 7
leave in place until soil injections are complete just in case. FB: Schedule for soil
injections? TC: We could start the soil injections this fall. We are permitted for the work,
but will need the (4) monitoring wells that are proposed on other side of Pink Row – need
neighbors to be on board. There are existing access agreements with the neighbors but
not necessarily for drilling. Also need the utility companies on board – they have been
problematic on Pink Row in the past. FB: We should start installing these wells now - the
work should be done this year. TC: I need permission from Scott Shaw to move forward
on all of this. FB: Will set up call with SS and TC for next week.
2.8 RFI MC 005 Reuse of water lines off of Route 32:
08/30 SO: DA wants to keep (2) existing 8” lines for the fire service but we talked about
the possibility of tapping into Pink Row only for the domestic service. FV: Will talk to DA
– both lines feed off the same main, shouldn’t make a difference where we tap the 4”
domestic – either at the street or off the 8” should be the same pressure.
09/04 Pending conf call w/FV & DA.
2.9 RFI DP 101 Coordination of Ejector Pit Design:
08/30 FV: During field visit on Monday, realization that raising of floors will allow more
space for the needed slope of sanitary. Preliminary calc’s yesterday indicate that we can
gravity for the entire site. Need to coordinate w/DEEP on flood protection of this line.
09/06 Pending conf call w/FV & DA.
2.10 RFI DP 102 Reuse of sanitary lines & inverts:
08/23 FV: Have the inverts, will show tie-in to building. Aztech needs to confirm how it
is handled inside the building, connection to ejector pit, etc.
08/30 SO: Told DA about need for connection details. FV: Will follow up w/DA to finalize.
09/06 Pending conf call w/FV & DA.
2.11 RFI DP 104 Utility plan update with generator:
08/23 FV: On updated utility plan, will show gas connection from the building rather than
a separate gas meter for the generator.
08/30 GP: Send updated utility plan to me. FB: Return the RFI with the answer.
09/06 Pending conf call w/FV & DA.
2.12 RFI DP 105 Sanitary & water line questions:
08/30 SO: Reviewed w/DA. See above for fire line & domestic water lines. Pending
decision to change to gravity only for the sanitary.
09/06 Pending conf call w/FV & DA.
2.13 Updated Civil Drawings to WPCA & DTW:
08/23 FB: I owe plans to WPCA & DTW – need updated civil drawings. FV: we are
underway on update to the utility plan. Need water & sanitary RFI questions answered.
Number of lines & their connections will be coordinated on the same utility plan.
08/30 FB: Waiting for final answers & final drawings before sending.
09/06 FB: Running out of time for receiving these – needed for permit.
2.14 Transformers/Eversource Coordination/Electric Meter location:
08/23 DM: Maggiore & Electrical Contractor will take over coordination with Eversource.
SS: Keep PBBA & BSC in the loop – want to adapt the site design if transformer location
moves. SO: On other jobs, have had issues with Eversource allowing indoor meters, and
issues with getting past the Line Department to the Meter Department to make this
determination. Historic designation will help in getting meters inside.
08/30 SO: Will send proof of historic designation to DM/GP which will help with
Eversource agreeing to indoor meters.
09/06 DM: We are working with Eversource to confirm transformer locations. SO: Same
on sending historic designation to MC.
2.15 Water line from Pink Row:
08/23 FB: There is an existing 8” line coming off Pink Row near the bridge. We will send
RFI on Monday or Tuesday. SO: We will review with Aztech so we aren’t waiting for the
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #04
09/06/2019
Page 5 of 7
RFI. FB: We have both services – one from Pink Row & one from Route 32. Never
understood why we had both. If we could use 1, would be better. FV: We had both on the
plan, pending determination of which one was more viable. DM: Only 1 water line for
whole project means that there would be no partial CO for early occupancy of one portion
of the project. FB: That is probably not an issue, as we have probably run out of time for
that to happen. FV: If Aztech has already gone through a full design of their sprinklers, we
would be going backwards to go to only 1 water line just to save 1 connection. DM: Also
I would need to tell the sprinkler sub ASAP if we go to 1 line. SO: We will review with
Aztech ASAP.
08/30 FB/FV: It is actually a 6” line coming off Pink Row. See above for further info on
water lines. FV to follow up w/DA.
09/04 Pending conf call w/FV & DA. FB: Running out of time for all answers.
2.16 Project Documentation:
08/23 FB: Want one source to access all plans, all Addendums & ASI’s, and reviewed
submittals. SO: Will set up Egnyte for this, and give MC read/write access so they can
upload reviewed submittals. DM: Will issue submittals via email, but can upload reviewed
submittals to this location.
08/30 SO: Same.
09/06 SO: Same, will do today.
2.17 Mechanical VE:
08/23 DM: Status of mechanical VE? SO: Sent total figure for cost of redesign to SS, but
owe him an amendment so he can review it with DM & FB. SS: As long as VE savings
exceed cost of redesign, I approve the redesign. DM: Savings range from $100k to $175k
but can’t confirm until new design is priced. SS: DM, you have to be 1 dollar more than
$36k which is cost of redesign.
08/30 SK: starting working on this redesign – new units are Whalen, not the Trane units
in Bldg B. We have actual mechanical closets in Bldg B with doors but new units don’t
need doors. Remove? DM: Yes & we will issue a credit for the doors.
09/06 SK: Setting up meeting w/Aztech & HVAC unit rep next week. DM: Mech
contractor should attend as well. SK: Will forward meeting time ASAP.
2.18 SHPO/DEEP Application:
08/30 FV: DEEP application has been issued to DOH. Once we have generic approval
from them, we will submit 2 hard copies to them for formal submission. SO: SHPO review
is almost complete. GP: Please prioritize a new framing plan. SS: Once Julie approves the
amendment for the floors, does that require NPS approval on the floors, which would be
further 30 day delay? SO: Don’t know, will find out.
09/06 FV: Sending formal DEEP application to Nathan Karns at DOH today – they will
sign & submit to DEEP. There is a 90 day window for review. I will start calling DEEP next
week to ensure that they have everything they need for the review. SO: SHPO application
is proceeding fine so far. Do not know answer to SS’s question above yet. NPS was more
concerned about the finish floor material in their comments, so the method of raising the
floors (wood construction vs. slab on fill) should not be an issue with them.
2.19 Windows:
08/30 DM: Window vendor has extreme concerns on size of windows & the ability of
Vinyl to expand/contract. Base budget is now based on vinyl. $450k savings. SS: Will send
another window supplier to you if helpful. SO: Should look at Matthews Brothers for vinyl
historic window.
09/06 GP: Glass/glazing contractor will be on site in a couple of weeks to start
measuring. Asked them if we could change to vinyl in certain buildings. First reaction is
“probably not.” FB: Plan is to stay with the aluminum windows. Do we need SHPO
approval on them? SO: No, not on windows that are replacing replacement windows. We
will need SHPO review/approval on the handful of windows that we are calling out as
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #04
09/06/2019
Page 6 of 7
original windows to be repaired or replaced. Those include windows on Bldg F, all
basement windows on Bldg M, and (3) 1st floor windows on the south side of Bldg M. DM:
PL, have those 3 windows been demo’d yet? PL: No, we have demo’d windows of Bldg M
on north and west sides. We will preserve the 3 original windows. SO: Those 3 are the
ones that are currently inside the building due to the addition on the south side – that is
why they were never replaced in the past.
3.0 NEW TOPICS:
3.1 Permit for Smoke Stack/Chimney:
09/06 SO: Is the smoke stack/chimney under a separate permit? DM: No, under general
permit. SO: There is nothing in our drawings or specs for this work – what defines the
scope of work for the chimney? DM: There is a conditions report. SO: Was that report
given to the Building Inspector by Dakota? FB: No. SO: He should be made aware of it,
because if he only has our drawings and specs, he does not know about the scope of work
for the chimney. DM: ok.
3.2 Current Owner’s approval to disconnect existing sprinkler system:
09/06 PL: FB, do we have approval to disconnect the sprinkler system tomorrow? MA:
Owner emailed that he was fine with dismantling the sprinkler system as long as his
insurance provider was aware of it. We are still waiting on confirmation from the Owner’s
insurance company, should email this by end of day today. GP: We need confirmation by
end of business day today or it will severely impact the schedule. MA: Will follow up.
3.3 Allowed scope of work under partial permit:
09/06 GP: Can we start repointing while the weather is still good? FB: You should check
with the Building Inspector on that. GP: Are we ok to proceed with clearing & grubbing,
demo of all exterior structures? FB: Yes, that is all demo. GP: We will be installing
construction fencing & bringing job trailer on site. Is that ok? FB: Yes.
3.4 Fire Hydrants:
09/06 FB: FV, you will discuss with DA the # of fire hydrants on the site & where they
will be? FV: Yes. Should maintain existing hydrants on the site as long as possible. FB: For
new fire hydrants – there are 3 new ones and 1 existing to remain on Pink Row. FV:
Existing one will be a new hydrant in existing location. FB: The one in question is above J,
½ mile from connection to road. Could it be placed in a closer location? FV: That location
not coordinated with FM yet, I put it in the location shown on the drawings because
nothing else was in that spot, but will coordinate location w/FM & try to move it closer.
3.5 Flood Vents:
09/06 SO: As soon as SHPO approves drawings, will release elevations showing flood
vents in Bldgs G, H and J. Bldg M has always shown 5 flood vents in 5 of the basement
window openings, & these are still in the scope of work even though note on the drawing
identifying them as flood vents seems to have disappeared. These drawings have always
been diagrammatic - we owe a detail on how to fit an actual flood vent product into these
openings. We sent a cut sheet on a flood vent to the SHPO – will use that product &
forward the cut sheet also.
3.6 Bldg F Elevator:
09/06 FB: What is status of Bldg F elevator? DM: It is not in our budget any more. SO:
Need to review w/FV to find alternate path of accessibility between the upper and lower
levels of the project.
3.7 VE Items:
09/06 SO: DM, please share which VE items you have put into your budget, as we have
not currently been made aware of any VE officially taken. DM: I will put something
together on that.
#16-063 Oxoboxo Lofts, Uncasville, CT
Meeting Minutes #04
09/06/2019
Page 7 of 7
4.0 RFI’s
4.1 Status:
08/30 SO: Will follow up comments above with RFI answers.
09/06 SO: Same.
5.0 SUBMITTALS
5.1 Status:
08/23 SO: Request that MC start producing weekly submittal and RFI logs, sent ahead of
the weekly call so they can be reviewed on the call. DM: Will do.
08/30 GP: Status of elevator shops? SK: My review is complete, sent to Aztech for their
review. DM: Send to Structural as well for sign off on shaft.
09/06 SK: Waiting on elevator submittal from DA & DM. Sent concrete mix submittal to
DM.
6.0 CHANGE ORDERS
6.1 Status:
08/16, 08/23, 08/30, 09/06 Not reviewed.
7.0 REQUISITIONS
7.1 Status:
08/16, 08/23, 08/30 Not reviewed.
09/06 DM: 1st req will be Oct 1.
8.0 SITE WALK
8.1 Status:
08/16, 08/23, 08/30, 09/06 Meeting not held on site, so no site walk.
Regular conference calls will be held weekly. Next conference call will be 9:00 am, September 13, 2019.
Recorded by Susan Odell, AIA, CPHC, Senior Project Architect, Paul B. Bailey Architect, LLC
These minutes are meant to convey & record the general content of the meeting, but do not represent a
verbatim recording. Please promptly respond to the Architect with any comments or questions.