HomeMy WebLinkAboutASK053 -E-D1.1 BUILDING E DEMO PLANSREMOVE ALL NON-
STRUCTURAL INTERIOR
PARTITIONS AND CEILINGS
ENTIRELY
REMOVE ALL
WINDOWS ON
THIS LEVEL.
DEMO BRICK WALL
BELOW WINDOW
OPENING TO FLOOR
LEVEL FOR NEW
DOOR
REMOVE ALL NON-
STRUCTURAL INTERIOR
PARTITIONS AND CEILINGS
ENTIRELY
SHORE STRUCTURE.
DEMOLISH FLOOR AND
FRAMING TO ACCOMMODATE
NEW STAIR WELL.
REMOVE ALL WINDOWS
ON THIS LEVEL.
DEMO BRICK WALL BELOW
WINDOW OPENING TO FLOOR
LEVEL FOR NEW DOOR
REMOVE ALL EXISTING CONSTRUCTIONS AND FINISHES NECESSARY FOR THE COMPLETION OF THE WORK AS
DEPICTED ON THE DRAWINGS. INCLUDING BUT NOT LIMITED TO, ITEMS SHOWN ON THE PLANS WITH DASHED
LINES. NECESSARY DISCONNECTS AND ALTERATIONS TO EXISTING MECHANICAL AND ELECTRICAL SYSTEMS SHALL
BE INCLUDED. PATCH AS REQUIRED ALL CONSTRUCTIONS TO REMAIN IN ACCORDANCE WITH THE CONTRACT
DRAWINGS. WHERE CONTRACTOR IS DESIGNED TO MAKE REMOVALS, DISPOSITION OF MATERIALS IS THE
RESPOSIBILITY OF THE CONTRACTOR. VERIFY WITH OWNER, THE DISPOSITION AND REMOVAL OF ANY
COMPONENTS OF SALVAGEABLE VALUE.
REMOVE ONLY NON-BEARING CONSTRICTION AND PARTITIONS UNLESS OTHERWISE DESIGNATED. CONTRACTOR
TO VERIFY, PRIOR TO REMOVAL,THAT NO STRUCTURAL COMPONENTS, I.E. BEARING WALLS, BEAMS, HEADERS,
ETC. SUPPORTING FLOOR, ROOF OR CEILING JOISTS ARE DESIGNATED FOR REMOVAL. CONTACT THE ARCHITECT
PRIOR TO REMOVAL OF ANY WORK INDICATES HIS COMPLETE UNDERSTANDING THAT NO LOAD BEARING OR
STRUCTURAL WORK IS BEING ALTERED UNDER THIS CONTRACT.
ALL STRUCTURAL SYSTEMS SHALL BE MAINTAINED AND SHALL BE SUFFICIENT STRENGTH TO SUPPORT THE
DESIGN LOAD AND TO RESIST THE DEFORMATION CAUSED BY SUCH LOADS.
WHERE APPLICABLE LEVEL ALL EXISTING FLOORS AS REQUIRED TO RECEIVE NEW FLOOR FINISHES. INSTALL
REQUIRED TRANSITION PIECES BETWEEN VARIOUS FLOOR FINISHES SUITABLE FOR CONDITIONS AND ACCEPTABLE
TO THE OWNER. MATCH EXISTING WHEREVER POSSIBLE.
THE CONTRACTOR SHALL FIELD VERIFY ALL EXISTING CONDITIONS PRIOR TO THE COMMENCEMENT OF WORK. ANY
DISCREPANCIES SHALL BE BROUGHT TO THE ATTENTION OF THE ARCHITECT. NO DEMOLITION WORK SHALL
COMMENCE WITHOUT FIELD VERIFICATION BY THE CONTRACTOR, OWNER AND ARCHITECT.
IT IS THE CONTRACTOR'S RESPONSIBILITY TO LOCATE AND REMOVE ALL MECHANICAL, ELECTRICAL AND
MISCELLANEOUS EQUIPMENT AS REQUIRED TO COMPLETE THE WORK. REFER TO MECHANICAL, PLUMBING,
ELECTRICAL AND STRUCTURAL DRAWINGS FOR DEMOLITION INFORMATION.
THE CONTRACTOR SHALL PROVIDE ALL TEMPORARY STRUCTURAL BRACING AS REQUIRED DURING DEMOLITION
AND CONSTRUCTION.
ANY PORTION OF THE PROJECT TO REMAIN WHICH IS DAMAGED AS A RESULT OF CONSTRUCTION ACTIVITY,
SHALL BE REPAIRED OR REPLACED TO MATCH THE EXISTING CONDITION.
THE CONTRACTOR SHALL COORDINATE AND ARRANGE FOR THE DISCONNECTION OF ALL UTILITIES AND
EQUIPMENT WITH THE OWNER AND UTILITY COMPANIES. THE CONTRACTOR SHALL CAP OFF ALL UNUSED
UTILITIES.
THE CONTRACTOR SHALL REMOVE, DISCONNECT AND SALVAGE ALL MECHANICAL, ELECTRICAL AND
MISCELLANEOUS WALL MOUNTED EQUIPMENT FOR RECONNECT AND REINSTALLATION.
THE CONSTRUCTOR SHALL ALLOW NO DEBRIS TO ACCUMULATE ON THE SITE. IMMEDIATELY REMOVE ALL DEBRIS
AND SALVAGE FROM THE SITE.
THE OWNER HAS FIRST RIGHT TO ALL SALVAGE ITEMS. ITEMS NOT CLAIMED BY OWNER SHALL BECOME THE
CONTRACTOR'S RESPONSIBILITY AND SHALL BE PROMPTLY DISPOSED OF FROM THE SITE.
IT IS THE CONTRACTOR'S RESPOSIBILITY TO PROVIDE SECURE, DRY STORAGE WITHIN THE DESIGNATED
CONTRACTOR LAY-DOWN AREA OR AN AREA DESIGNATED BY OWNER FOR OWNER RETAINED ITEMS.
GENERAL DEMOLITION NOTES:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
LEGEND
DEMOLISHED ELEMENT
Scale
Date
Drawn By
Checked By
Project Number
UNCASVILLE, CT
42 PINK ROW
SKETCH NUMBER
RFI REFERENCE
SHEET NUMBER
DATE
As indicated
E-D1.1
BUILDING E
DEMO PLANS
Dakota
Partners, Inc.
OXOBOXO
LOFTS
Checker
Author
01/23/2020
16-063
1/8" = 1'-0"E-D1.1
1 BUILDING E - LEVEL 1 DEMOLITION PLAN
1/8" = 1'-0"E-D1.1
2 BUILDING E - LEVEL 2 DEMOLITION PLAN
E-D1.1
3 BUILDING E - DEMOLITION AXONOMETRIC
A
B
D E
C F
G H
J
K
L M
NORTH
SITE KEY PLAN
ASK-053
02/06/20