HomeMy WebLinkAboutStaff ReportC:\Users\twilliams\Desktop\DoyleRd217-M57L5A-Soderberg modification Staff Report 1-20-11.doc
Scott Soderberg
217 Doyle Road
Modification of 210 IWC 17
211 IWC 1
Meeting Date: February 17, 2011
Date Received by Commission: February 17, 2011
Terminal Date: April 22, 2011
C:\Users\twilliams\Desktop\DoyleRd217-M57L5A-Soderberg modification Staff Report 1-20-11.doc
Assessors/Wetlands Map
Applicant Request
- Work within regulated area for the installation patio area
o Another tier to wall
o 2x2x4 foot column at end of wall
o 4 foot round patio with 4 ft fire pit in center
Activity Description
Wetland Disturbance Area 0sq ft
Upland Review Disturbance Area 1,000 sq ft
Watercourse/ Waterbody Disturbance Area 0
Staff Comments
- Commission approved original application on
- Modification is for the creation of a patio area that will have a fire pit
C:\Users\twilliams\Desktop\DoyleRd217-M57L5A-Soderberg modification Staff Report 1-20-11.doc
Draft Motion
After giving due consideration to all relevant factors including those in Section 10 and or
Section 4 of the Montville Inland Wetland Regulation and Section 22a-41 of the
Connecticut General Statutes, I move to approve application
211 IWC 3 Scott Soderberg: An application for the modification of permit 210 IWC 17 to
include the creation of a patio are and a new tier of retaining wall on the property located at 217
Doyle Road, Montville, Ct. As shown on Assessor’s Map 57 Lot 5A as depicted on the plan titled
“Modified plan for Retaining Wall and Fence Project for 217 Doyle Road” and the application
and narrative dated 1/5/11
This is a conditional approval. Each and every condition is an integral part of the
Commission decision. Should any of the conditions, on appeal from this decision, be
found to be void or of no legal effect then this conditional approval is likewise void.
Should any of the conditions not be implemented by the applicant or his successors
within the specified permit time period, then this conditional approval is void.
Conditions of approval are:
C:\Users\twilliams\Desktop\DoyleRd217-M57L5A-Soderberg modification Staff Report 1-20-11.doc
Standard Reasons for Approval
1. The environmental impact of the proposed project does not have a significant
effect on the inland wetland's and watercourse's capacity to support fish and
wildlife, to prevent flooding, to supply and protect surface and groundwater, to
control sediment, to facilitate drainage, to control pollution, to support
recreational activities, and to promote public health and safety.
2. The Commission has determined that the relationship between the short-term
uses of the environment and the maintenance and enhancement of long-term
productivity will have no impact on the surrounding wetland system
3. The proposed activity will not have irreversible and irretrievable commitments
of resources.
4. The proposed project will not change the character and or add degree of injury
to, or interference with, safety, health, or the reasonable use of property, including
abutting or downstream property.
5. The proposed activity use is suitable to the area.
6. The applicant has taken all feasible measures to mitigate the impact of any
aspect of the proposed regulated activity.